WHEELER IH 40 (0275-12-072)

Items: 55

County: WHEELER
Length: N/A
Highway: IH 40
District: CHILDRESS
Control Number: 0275-12-072
DBE Goal: N/A
Project: BR 2017(870)
Guaranty: N/A
Time: 170 WORKING DAYS
Engineer's Estimate: $4,645,145.84
Date: 03/07/2017 (9 years ago)
Contract Number: N/A
Type: BRIDGE REPLACMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$4,645,145.84
$2,923,330.68
Over/Under Est: -37.07% -$1,721,815.16
$3,058,869.57
Over/Under Est: -34.15% -$1,586,276.27
Amt Left: 4.64% $135,538.89
$3,320,994.68
Over/Under Est: -28.51% -$1,324,151.16
Amt Left: 13.6% $397,664.00
Delta: -8.57% -$262,125.11
$3,402,877.20
Over/Under Est: -26.74% -$1,242,268.64
Amt Left: 16.4% $479,546.52
Delta: -2.47% -$81,882.52
$3,946,999.00
Over/Under Est: -15.03% -$698,146.84
Amt Left: 35.02% $1,023,668.32
Delta: -15.99% -$544,121.80
Over/Under Est: -13.53% -$628,444.12
Amt Left: 37.4% $1,093,371.04
Delta: -1.77% -$69,702.72
$4,138,913.00
Over/Under Est: -10.9% -$506,232.84
Amt Left: 41.58% $1,215,582.32
Delta: -3.04% -$122,211.28

Bid Items & Bid Tabulations

55 Total 0 of 55
WHEELER  |  IH 40  |  CHILDRESS  |  0275-12-072  |  03/07/2017  |  $4,645,145.84  |  BR 2017(870)  |  BRIDGE REPLACMENT  |  170 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
COPPELL CONSTRUCTION CO., INC.
J. LEE MILLIGAN, INC.
GILVIN-TERRILL, LTD.
FNF CONSTRUCTION, INC.
RK HALL, LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
EARTH BUILDERS, L.P.
REMOVING CONC (PAV)
SY 1,396.000 $35.000 $13.750 $37.350 $20.000 $35.000 $30.000 $40.000 $25.000
REMOVING CONC (RIPRAP)
SY 936.000 $25.000 $8.500 $20.000 $10.000 $15.000 $17.000 $40.000 $15.000
REMOVING CONC (MISC)
CY 74.000 $225.000 $80.000 $155.000 $100.000 $250.000 $220.000 $40.000 $150.000
REMOVING STAB BASE AND ASPH PAV (6")
SY 924.000 $25.000 $5.000 $4.000 $10.000 $15.000 $15.000 $16.000 $10.000
REMOVING STAB BASE AND ASPH PAV(8")
SY 1,469.000 $15.000 $6.500 $3.300 $10.000 $10.000 $9.600 $10.000 $10.000
EXCAVATION (ROADWAY)
CY 358.000 $35.000 $17.500 $15.350 $30.000 $15.000 $33.500 $20.000 $25.000
EXCAVATION (CHANNEL)
CY 1,580.000 $40.000 $13.000 $15.250 $10.000 $12.000 $24.000 $20.000 $20.000
EXCAVATION (SPECIAL)
CY 636.000 $20.000 $18.250 $16.000 $10.000 $7.000 $40.000 $20.000 $20.000
EMBANKMENT (FINAL)(DENS CONT)(TY A)
CY 376.000 $65.000 $24.750 $40.000 $30.000 $3.000 $15.600 $30.000 $35.000
BACKFILL (TY A OR B)
STA 6.000 $800.000 $2,000.000 $1,500.000 $400.000 $1,200.000 $500.000 $1,200.000 $1,000.000
BLADING
HR 4.000 $400.000 $135.000 $365.000 $200.000 $110.000 $200.000 $60.000 $120.000
DRILL SEEDING (PERM) (RURAL) (SANDY)
AC 1.720 $5,000.000 $1,435.000 $1,840.000 $1,744.000 $550.000 $1,382.400 $2,000.000 $1,300.000
DRILL SEEDING (TEMP) (WARM)
AC 0.860 $3,500.000 $1,435.000 $1,815.000 $1,720.940 $800.000 $1,382.400 $2,000.000 $1,300.000
DRILL SEEDING (TEMP) (COOL)
AC 0.860 $3,500.000 $1,435.000 $1,815.000 $1,720.940 $400.000 $1,382.400 $2,000.000 $1,300.000
VEGETATIVE WATERING
MG 68.000 $50.000 $50.000 $45.000 $40.000 $16.000 $75.000 $1.000 $100.000
PROOF ROLLING
HR 20.000 $195.000 $145.000 $125.000 $200.000 $85.000 $105.000 $60.000 $120.000
CEMENT
TON 28.000 $225.000 $200.000 $160.000 $150.000 $190.000 $285.000 $200.000 $220.000
CEMENT TREAT (SUBGRADE)(9")
SY 1,962.000 $35.000 $6.000 $10.150 $10.000 $15.000 $15.000 $16.000 $20.000
PRIME COAT (MC-30)
GAL 588.000 $60.000 $6.000 $7.750 $7.500 $16.000 $7.500 $10.000 $10.000
D-GR HMA(SQ) TY-D SAC-A PG76-28
TON 432.000 $225.000 $185.000 $160.000 $140.000 $160.000 $245.000 $180.000 $180.000
CONC PVMT (CONT REINF - CRCP) (12")
SY 1,850.000 $150.000 $123.750 $125.000 $150.000 $163.000 $165.000 $175.000 $150.000
CEM STABIL BKFL
CY 77.000 $150.000 $313.000 $225.000 $200.000 $180.000 $280.000 $300.000 $150.000
FOUNDATON LOADTEST(D4945)(DRILLD SHAFT)
EA 2.000 $55,000.000 $33,000.000 $8,000.000 $17,500.000 $25,000.000 $31,946.400 $30,000.000 $17,500.000
DRILL SHAFT (24 IN)
LF 1,540.000 $175.000 $136.000 $157.000 $185.000 $180.000 $130.910 $140.000 $175.000
CL C CONC (ABUT)(HPC)
CY 53.600 $1,200.000 $1,200.000 $1,170.000 $1,500.000 $1,400.000 $1,625.000 $1,200.000 $1,500.000
CL C CONC (CAP)(HPC)
CY 43.800 $1,500.000 $1,200.000 $1,630.000 $1,500.000 $1,900.000 $2,000.000 $1,200.000 $1,500.000
CL C CONC (COLUMN)(HPC)
CY 13.800 $2,500.000 $1,200.000 $2,000.000 $1,500.000 $2,500.000 $2,700.000 $1,600.000 $1,500.000
REINF CONC SLAB (SLAB BEAM)(HPC)
SF 10,299.000 $45.000 $17.000 $21.300 $16.000 $12.000 $18.000 $21.000 $25.000
APPROACH SLAB (HPC)
CY 190.800 $500.000 $425.000 $495.000 $1,500.000 $600.000 $600.000 $750.000 $1,000.000
PRESTR CONC SLAB BEAM (4SB12)
LF 1,867.880 $175.000 $163.000 $155.000 $175.000 $195.000 $218.420 $162.000 $225.000
PRESTR CONC SLAB BEAM (5SB12)
LF 533.680 $200.000 $163.000 $164.000 $175.000 $195.000 $218.420 $162.000 $225.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 356.000 $160.000 $128.000 $60.000 $150.000 $140.000 $275.000 $200.000 $130.000
RIPRAP (MOW STRIP)(4 IN)
CY 23.000 $600.000 $1,000.000 $635.000 $600.000 $800.000 $825.000 $500.000 $500.000
RAIL (TY T223)(HPC)
LF 596.000 $150.000 $110.000 $91.200 $100.000 $160.000 $100.000 $130.000 $125.000
SEALED EXPANSION JOINT (4 IN) (SEJ - A)
LF 174.000 $90.000 $100.000 $120.000 $100.000 $150.000 $110.000 $100.000 $85.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 2.000 $20,000.000 $35,500.000 $51,750.000 $100,000.000 $80,000.000 $55,000.000 $200,000.000 $100,000.000
MOBILIZATION
LS 1.000 $361,516.600 $290,000.000 $300,000.000 $300,000.000 $337,000.000 $394,699.900 $375,000.000 $425,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $2,500.000 $4,500.000 $6,000.000 $5,580.000 $3,000.000 $2,507.730 $15,000.000 $10,000.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 480.000 $10.000 $7.000 $9.250 $6.000 $10.000 $7.560 $15.000 $8.000
CONSTRUCTING DETOURS
SY 3,289.000 $447.160 $222.000 $233.000 $200.000 $240.000 $350.000 $294.000 $335.000
RUMBLE STRIPS (SHOULDER)
LF 507.000 $15.000 $15.000 $14.750 $14.000 $14.000 $15.120 $20.000 $10.000
MTL W-BEAM GD FEN (STEEL POST)
LF 250.000 $75.000 $25.000 $24.800 $25.000 $22.000 $24.840 $30.000 $30.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 8.000 $2,200.000 $3,000.000 $2,215.000 $1,500.000 $1,500.000 $1,566.000 $2,200.000 $1,500.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $2,000.000 $1,550.000 $1,160.000 $1,600.000 $1,000.000 $1,458.000 $1,600.000 $2,000.000
REMOVE METAL BEAM GUARD FENCE
LF 250.000 $15.000 $5.000 $4.200 $12.000 $10.000 $3.240 $10.000 $100.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 2.000 $500.000 $440.000 $316.250 $850.000 $500.000 $216.000 $500.000 $150.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $2,500.000 $2,500.000 $2,900.000 $2,200.000 $2,000.000 $2,570.400 $2,400.000 $2,600.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $500.000 $450.000 $316.250 $750.000 $600.000 $216.000 $500.000 $250.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 140.000 $40.000 $4.000 $4.200 $4.000 $4.500 $4.320 $6.000 $5.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 1,450.000 $35.000 $4.000 $4.200 $4.000 $4.500 $4.320 $4.000 $5.000
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 120.000 $40.000 $4.000 $4.200 $4.000 $4.500 $4.320 $6.000 $5.000
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 740.000 $35.000 $4.000 $4.200 $4.000 $4.500 $4.320 $6.000 $5.000
PLOWABLE REFL PAV MRKR TY II-C-R
EA 14.000 $50.000 $80.000 $79.000 $75.000 $80.000 $81.000 $100.000 $80.000
PAV SURF PREP FOR MRK (4")
LF 3,040.000 $2.500 $2.000 $2.100 $2.000 $2.200 $2.160 $2.000 $2.000
TIP TESTING(DRILL SHAFT)
EA 6.000 $15,000.000 $3,700.000 $1,900.000 $3,800.000 $3,100.000 $3,607.200 $4,000.000 $3,000.000
Totals: $4,645,145.840 $2,923,330.680 $3,058,869.570 $3,320,994.697 $3,402,877.200 $3,946,999.031 $4,016,701.720 $4,138,913.000