Show Job Controls
Bid Cobra

WHARTON US0059 (6394-44-001)

Items: 39

County: WHARTON
Length: N/A
Highway: US0059
District: YOAKUM
Control Number: 6394-44-001
DBE Goal: N/A
Project: RMC - 639444001
Guaranty: N/A
Time: 730 CALENDAR DAYS
Engineer's Estimate: $1,142,050.00
Date: 04/06/2022 (4 years ago)
Contract Number: N/A
Type: METAL BEAM GUARD FENCE REPAIR
Mail/Deliver Bids To: N/A
MARK NETARDUS
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (3)
E
Engineer's Estimate
$1,142,050.00
$1,041,864.40
Over/Under Est: -8.77% -$100,185.60
$1,953,536.00
Over/Under Est: 71.06% $811,486.00
Amt Left: 87.5% $911,671.60
$2,151,350.00
Over/Under Est: 88.38% $1,009,300.00
Amt Left: 106.49% $1,109,485.60
Delta: -10.13% -$197,814.00

Bid Items & Bid Tabulations

39 Total 0 of 39
WHARTON  |  US0059  |  YOAKUM  |  6394-44-001  |  04/06/2022  |  $1,142,050.00  |  RMC - 639444001  |  METAL BEAM GUARD FENCE REPAIR  |  730 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
JCW CONSTRUCTION, LLC
DIGG COMMERCIAL, LLC
ISI CONTRACTING, INC.
MOBILIZATION (CALLOUT)
EA 24.000 $1,000.000 $1.000 $1.000 $2,500.000
MTL BM GD FEN TRANS (ANCHOR PLATE)
EA 5.000 $750.000 $1.000 $1,000.000 $1,400.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 60.000 $30.000 $30.000 $30.000 $15.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 60.000 $35.000 $30.000 $30.000 $22.000
REPAIR RAIL ELEMENT (W - BEAM)
LF 6,000.000 $25.000 $28.500 $34.000 $35.000
REPAIR RAIL ELEMENT (THRIE - BEAM)
LF 50.000 $50.000 $100.000 $60.000 $30.000
REP RAIL ELMNT(THRIE-BM TRANS TO W -BM)
LF 40.000 $35.000 $100.000 $50.000 $46.000
REPAIR RAIL ELEMENT (CURVED RAIL)
LF 750.000 $25.000 $30.000 $50.000 $75.000
REM / REPL TIMBER/STL POST W/O CONC FND
EA 700.000 $50.000 $40.000 $200.000 $41.000
REM / REPL TIMBER / STL POST W/CONC FND
EA 150.000 $55.000 $100.000 $300.000 $49.000
REALIGN POSTS
EA 200.000 $30.000 $105.000 $100.000 $100.000
REMOVE & REPLACE BLOCKOUT
EA 300.000 $37.000 $80.000 $30.000 $19.000
REPLACE SINGLE GDRAIL TERMINAL RAIL
LF 600.000 $25.000 $25.000 $30.000 $36.000
REPLACE SINGLE GDRAIL TERMINAL POST
EA 75.000 $65.000 $125.000 $300.000 $50.000
REMOVE GDRAIL END TRT / REPL WITH SGT
EA 50.000 $3,000.000 $3,750.000 $3,500.000 $3,755.000
REPL SINGLE GDRAIL TERM IMPACT HEAD
EA 20.000 $1,200.000 $500.000 $1,600.000 $1,275.000
REM & RESET SGT IMPACT HEAD
EA 20.000 $200.000 $100.000 $300.000 $156.000
REPLACE SGT CABLE ASSEMBLY
EA 20.000 $30.000 $1.000 $100.000 $140.000
REPLACE SGT CABLE ANCHOR
EA 20.000 $30.000 $1.000 $100.000 $101.000
REPLACE SGT STRUT
EA 65.000 $35.000 $1.000 $100.000 $86.000
REPLACE SGT OBJECT MARKER
EA 100.000 $35.000 $1.000 $50.000 $25.000
REPLACE POSTS (TL-3)
EA 1,000.000 $135.000 $0.010 $219.000 $282.000
REPLACE POSTS (TL-4)
EA 1,750.000 $140.000 $165.000 $280.000 $300.000
CABLE SPLICE / TURNBUCKLE (TL-3)
EA 10.000 $100.000 $0.010 $320.000 $243.000
CABLE SPLICE / TURNBUCKLE (TL-4)
EA 10.000 $100.000 $50.000 $320.000 $619.000
REPAIR CONCRETE FOUNDATION (TL-3)
EA 10.000 $100.000 $0.010 $100.000 $224.000
REPAIR CONCRETE FOUNDATION (TL-4)
EA 10.000 $100.000 $50.000 $100.000 $312.000
REPR OR REPLC CABLE BARR TERM SEC(TL-3)
EA 20.000 $1,200.000 $0.010 $3,000.000 $1,359.000
REPR OR REPLC CABLE BARR TERM SEC(TL-4)
EA 30.000 $1,400.000 $1,000.000 $3,300.000 $1,344.000
REPLACE CABLE (TL-3)
LF 750.000 $5.000 $1.000 $3.000 $4.000
REPLACE CABLE (TL-4)
LF 1,000.000 $5.000 $1.000 $3.000 $4.000
CHECK / RE-TENSION CABLE
EA 75.000 $300.000 $1.000 $130.000 $380.000
REPLACE POST HARDWARE (TL-4)
EA 5,000.000 $11.000 $0.010 $35.000 $40.000
REPLACE POST HARDWARE (TL-3)
EA 2,000.000 $10.000 $0.010 $26.000 $40.000
REPLACE CCT POST (5 FT 3 IN)
EA 10.000 $165.000 $200.000 $300.000 $258.000
REPLACE CCT POST (5 FT 11 IN)
EA 10.000 $165.000 $200.000 $400.000 $320.000
RMV/REPL(VIA-SAND FILL PLASTIC BARRELS)
EA 200.000 $325.000 $500.000 $250.000 $812.000
TMA (STATIONARY)
DAY 200.000 $150.000 $400.000 $200.000 $350.000
1 LANE CLOSURE-4 LANE ROAD
EA 12.000 $1,500.000 $1,500.000 $1.000 $4,500.000
Totals: $1,142,050.000 $1,041,864.400 $1,953,536.000 $2,151,350.000