WHARTON US0059 (6353-60-001)

Items: 52

County: WHARTON
Length: N/A
Highway: US0059
District: YOAKUM
Control Number: 6353-60-001
DBE Goal: N/A
Project: RMC - 635360001
Guaranty: N/A
Time: 730 CALENDAR DAYS
Engineer's Estimate: $1,344,400.00
Date: 02/07/2020 (6 years ago)
Contract Number: N/A
Type: METAL BEAM GUARDFENCE REPAIR (ON CALL)
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$1,344,400.00
$1,148,040.00
Over/Under Est: -14.61% -$196,360.00
Over/Under Est: -13.21% -$177,610.00
Amt Left: 1.63% $18,750.00
$1,187,747.00
Over/Under Est: -11.65% -$156,653.00
Amt Left: 3.46% $39,707.00
Delta: -1.80% -$20,957.00
Over/Under Est: -9.18% -$123,370.00
Amt Left: 6.36% $72,990.00
Delta: -2.80% -$33,283.00

Bid Items & Bid Tabulations

52 Total 0 of 52
WHARTON  |  US0059  |  YOAKUM  |  6353-60-001  |  02/07/2020  |  $1,344,400.00  |  RMC - 635360001  |  METAL BEAM GUARDFENCE REPAIR (ON CAL...  |  730 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
K-BAR SERVICES, INC.
ELITE CASTLE RESOURCES LLC
SHORT-LINE CORPORATION
T&L CLEANING SERVICES LLC
MOBILIZATION (CALLOUT)
EA 24.000 $1,500.000 $50.000 $50.000 $100.000 $300.000
MTL W-BEAM GD FEN (TIM POST)
LF 500.000 $15.000 $25.000 $25.000 $5.000 $24.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 10.000 $750.000 $500.000 $500.000 $100.000 $1,500.000
MTL BEAM GD FEN TRANS (T101)
EA 5.000 $500.000 $1,000.000 $1,000.000 $1,500.000 $1,000.000
MTL BEAM GD FEN TRANS (T6)
EA 5.000 $500.000 $500.000 $500.000 $100.000 $1,000.000
DRIVEWAY TERMINAL ANCHOR SECTION
EA 5.000 $850.000 $500.000 $500.000 $500.000 $2,000.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 5.000 $1,200.000 $1,500.000 $1,500.000 $1,500.000 $1,200.000
MTL BM GD FEN TRANS (ANCHOR PLATE)
EA 5.000 $300.000 $500.000 $500.000 $100.000 $300.000
GUARDRAIL END TREATMENT (INSTALL)
EA 5.000 $2,000.000 $3,250.000 $4,000.000 $2,500.000 $3,500.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 60.000 $25.000 $22.000 $22.000 $100.000 $30.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 60.000 $30.000 $22.000 $22.000 $100.000 $30.000
REPAIR RAIL ELEMENT (W - BEAM)
LF 6,000.000 $25.000 $25.000 $25.000 $25.000 $24.000
REPAIR RAIL ELEMENT (THRIE - BEAM)
LF 50.000 $50.000 $20.000 $20.000 $10.000 $20.000
REP RAIL ELMNT(THRIE-BM TRANS TO W -BM)
LF 40.000 $50.000 $20.000 $20.000 $10.000 $31.000
REPAIR RAIL ELEMENT (CURVED RAIL)
LF 750.000 $25.000 $10.000 $10.000 $15.000 $30.000
REM / REPL TIMBER/STL POST W/O CONC FND
EA 700.000 $40.000 $30.000 $50.000 $50.000 $50.000
REM / REPL TIMBER / STL POST W/CONC FND
EA 150.000 $50.000 $30.000 $30.000 $25.000 $50.000
REALIGN POSTS
EA 200.000 $20.000 $45.000 $45.000 $100.000 $10.000
REMOVE & REPLACE BLOCKOUT
EA 300.000 $10.000 $48.000 $48.000 $100.000 $10.000
REPLACE SINGLE GDRAIL TERMINAL RAIL
LF 600.000 $25.000 $25.000 $25.000 $15.000 $30.000
REPLACE SINGLE GDRAIL TERMINAL POST
EA 75.000 $50.000 $100.000 $100.000 $25.000 $60.000
REMOVE GDRAIL END TRT / REPL WITH SGT
EA 50.000 $2,100.000 $3,000.000 $3,800.000 $2,500.000 $3,300.000
REPL SINGLE GDRAIL TERM IMPACT HEAD
EA 20.000 $900.000 $850.000 $1,000.000 $500.000 $1,000.000
REM & RESET SGT IMPACT HEAD
EA 20.000 $100.000 $150.000 $150.000 $100.000 $50.000
REPLACE SGT CABLE ASSEMBLY
EA 20.000 $20.000 $50.000 $50.000 $100.000 $1.000
REPLACE SGT CABLE ANCHOR
EA 20.000 $20.000 $55.000 $55.000 $50.000 $1.000
REPLACE SGT STRUT
EA 50.000 $28.000 $55.000 $55.000 $20.000 $1.000
REPLACE SGT OBJECT MARKER
EA 100.000 $20.000 $1.000 $1.000 $10.000 $30.000
REPLACE POSTS (TL-3)
EA 1,750.000 $135.000 $20.000 $50.000 $25.000 $120.000
REPLACE POSTS (TL-4)
EA 1,750.000 $140.000 $100.000 $150.000 $150.000 $150.000
CABLE SPLICE / TURNBUCKLE (TL-3)
EA 10.000 $100.000 $50.000 $50.000 $1.000 $100.000
CABLE SPLICE / TURNBUCKLE (TL-4)
EA 10.000 $100.000 $50.000 $50.000 $100.000 $100.000
REPAIR CONCRETE FOUNDATION (TL-3)
EA 10.000 $100.000 $15.000 $15.000 $1.000 $50.000
REPAIR CONCRETE FOUNDATION (TL-4)
EA 10.000 $100.000 $15.000 $15.000 $1.000 $50.000
REPR OR REPLC CABLE BARR TERM SEC(TL-3)
EA 30.000 $500.000 $1,500.000 $1,500.000 $1,500.000 $1,000.000
REPR OR REPLC CABLE BARR TERM SEC(TL-4)
EA 30.000 $500.000 $1,000.000 $1,500.000 $1,500.000 $1,500.000
REPLACE CABLE (TL-3)
LF 1,000.000 $5.000 $1.000 $1.000 $0.500 $0.500
REPLACE CABLE (TL-4)
LF 1,000.000 $5.000 $1.000 $1.000 $0.500 $0.500
CHECK / RE-TENSION CABLE
EA 72.000 $200.000 $300.000 $300.000 $1.000 $200.000
REPLACE POST HARDWARE (TL-4)
EA 5,250.000 $25.000 $20.000 $15.000 $1.000 $3.000
REPLACE POST HARDWARE (TL-3)
EA 5,250.000 $25.000 $20.000 $5.000 $1.000 $3.000
REPLACE CCT POST (5 FT 3 IN)
EA 10.000 $200.000 $100.000 $100.000 $100.000 $100.000
REPLACE CCT POST (5 FT 11 IN)
EA 10.000 $200.000 $100.000 $100.000 $100.000 $100.000
RMV/REPL(VIA-SAND FILL PLASTIC BARRELS)
EA 100.000 $300.000 $380.000 $380.000 $1,000.000 $400.000
REPAIR (STL POST W/ DOUBLED W-BEAMS-T6)
LF 100.000 $75.000 $55.000 $55.000 $50.000 $100.000
REP METAL POST W/ BASE PLATE(T101 RAIL)
EA 10.000 $100.000 $280.000 $280.000 $100.000 $100.000
REPAIR (TY T101RC)
LF 100.000 $20.000 $50.000 $50.000 $1.000 $30.000
REPAIR (TY T1 - 101R)
LF 100.000 $20.000 $50.000 $50.000 $1.000 $30.000
REP METAL PST W/ BASE PLATE (TY T101RC)
EA 10.000 $150.000 $300.000 $300.000 $1.000 $100.000
REP METAL PST W/ BASE PLATE(TY T1-101R)
EA 10.000 $150.000 $300.000 $300.000 $1.000 $100.000
TMA (STATIONARY)
DAY 200.000 $150.000 $470.000 $10.000 $1,000.000 $200.000
1 LANE CLOSURE-4 LANE ROAD
EA 12.000 $1,500.000 $550.000 $550.000 $1,500.000 $1,000.000
Totals: $1,344,400.000 $1,148,040.000 $1,166,790.000 $1,187,747.000 $1,221,030.000