Show Job Controls
Bid Cobra

WHARTON VA (0913-09-116)

Items: 31

County: WHARTON
Length: N/A
Highway: VA
District: YOAKUM
Control Number: 0913-09-116
DBE Goal: N/A
Project: STP 2022(392)TAPS
Guaranty: N/A
Time: 120 WORKING DAYS
Engineer's Estimate: $650,044.00
Date: 09/07/2022 (3 years ago)
Contract Number: N/A
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Mail/Deliver Bids To: N/A
RYAN SIMPER
JEFFREY KALINA
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$650,044.00
$664,041.50
Over/Under Est: 2.15% $13,997.50
Over/Under Est: 14.6% $94,893.00
Amt Left: 12.18% $80,895.50
Over/Under Est: 16.64% $108,148.00
Amt Left: 14.18% $94,150.50
Delta: -1.78% -$13,255.00
Over/Under Est: 29.21% $189,875.90
Amt Left: 26.49% $175,878.40
Delta: -10.78% -$81,727.90

Bid Items & Bid Tabulations

31 Total 0 of 31
WHARTON  |  VA  |  YOAKUM  |  0913-09-116  |  09/07/2022  |  $650,044.00  |  STP 2022(392)TAPS  |  CONSTRUCT PEDESTRIAN INFRASTRUCT  |  120 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ENCINO LANDSCAPE, INC.
LUCANIA CONSTRUCTION LLC
FNH CONSTRUCTION, LLC
PROJECT ALLIED RESOURCES, LLC
REMOVING CONC (PAV)
SY 101.000 $35.000 $20.000 $25.000 $55.000 $18.700
REMOVING CONC (DRIVEWAYS)
SY 495.000 $30.000 $20.000 $25.000 $55.000 $18.700
REMOVING CONC (CURB AND GUTTER)
LF 307.000 $15.000 $10.000 $16.000 $20.000 $8.000
REMOVING STAB BASE AND ASPH PAV (2"-6")
SY 190.000 $35.000 $20.000 $24.000 $20.000 $10.300
FURNISHING AND PLACING TOPSOIL
CY 30.000 $40.000 $50.000 $150.000 $80.000 $52.000
BLOCK SODDING
SY 3,800.000 $7.500 $6.000 $7.500 $10.000 $3.660
VEGETATIVE WATERING
MG 60.000 $50.000 $20.000 $150.000 $50.000 $67.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 219.900 $60.000 $75.000 $160.000 $200.000 $80.000
CONC PVMT (JOINTED - CPCD) (6")
SY 33.000 $100.000 $190.000 $275.000 $300.000 $185.000
RC PIPE (CL III)(12 IN)
LF 12.000 $120.000 $100.000 $220.000 $85.000 $340.000
MOBILIZATION
LS 1.000 $60,000.000 $50,000.000 $45,000.000 $70,000.000 $84,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $3,000.000 $5,000.000 $3,700.000 $8,500.000 $5,800.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 65.000 $7.000 $5.000 $7.000 $4.000 $9.600
TEMP SEDMT CONT FENCE (REMOVE)
LF 65.000 $3.000 $1.000 $4.000 $2.000 $2.460
BIODEG EROSN CONT LOGS (REMOVE)
LF 430.000 $5.000 $1.000 $15.000 $9.000 $5.600
BIODEG EROSN CONT LOGS (INSTL) (6")
LF 430.000 $10.000 $8.000 $5.000 $18.000 $12.000
CONC CURB & GUTTER (TY I)
LF 11.000 $55.000 $35.000 $40.000 $55.000 $54.000
CONC CURB & GUTTER (TY II)
LF 104.000 $55.000 $40.000 $40.000 $55.000 $55.000
DRIVEWAYS (CONC)
SY 793.000 $95.000 $100.000 $115.000 $105.000 $126.000
CONC SIDEWALKS (5")
SY 3,616.000 $90.000 $100.000 $107.000 $75.000 $127.000
CURB RAMPS (TY 1)
SY 54.700 $200.000 $140.000 $200.000 $320.000 $195.000
CURB RAMPS (TY 2)
SY 45.000 $300.000 $140.000 $200.000 $320.000 $195.000
CURB RAMPS (TY 5)
SY 69.400 $200.000 $140.000 $200.000 $320.000 $195.000
CURB RAMPS (TY 7)
SY 30.000 $275.000 $140.000 $200.000 $320.000 $195.000
CURB RAMPS (TY 10)
SY 29.000 $300.000 $140.000 $200.000 $320.000 $195.000
MAILBOX INSTALL-S (WC-POST) TY 3
EA 7.000 $200.000 $250.000 $800.000 $850.000 $498.000
RELOCATE SM RD SN SUP&AM TY TWT
EA 11.000 $450.000 $500.000 $300.000 $850.000 $646.000
PREFAB PAV MRK TY C (W) (12") (SLD)
LF 673.000 $10.000 $20.000 $10.000 $20.000 $19.700
ELIM EXT PAV MRK & MRKS (12")
LF 70.000 $5.000 $10.000 $5.000 $20.000 $12.200
ELIM EXT PAV MRK & MRKS (18")
LF 74.000 $5.000 $10.000 $6.000 $20.000 $15.300
TMA (STATIONARY)
DAY 5.000 $500.000 $400.000 $600.000 $350.000 $513.000
Totals: $650,044.000 $664,041.500 $744,937.000 $758,192.000 $839,919.900