WHARTON CR (0913-09-115)

Items: 52

County: WHARTON
Length: N/A
Highway: CR
District: YOAKUM
Control Number: 0913-09-115
DBE Goal: 500.0%
Project: BR 2022(482)
Guaranty: N/A
Time: 195 WORKING DAYS
Engineer's Estimate: $2,225,645.50
Date: 05/02/2024 (2 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
RYAN SIMPER
PAUL RODRIGUEZ
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$2,225,645.50
$2,292,072.07
Over/Under Est: 2.98% $66,426.57
Over/Under Est: 4.16% $92,633.76
Amt Left: 1.14% $26,207.19
$2,464,030.90
Over/Under Est: 10.71% $238,385.40
Amt Left: 7.5% $171,958.83
Delta: -6.29% -$145,751.64
$2,546,114.70
Over/Under Est: 14.4% $320,469.20
Amt Left: 11.08% $254,042.63
Delta: -3.33% -$82,083.80
Over/Under Est: 15% $333,824.00
Amt Left: 11.67% $267,397.43
Delta: -0.52% -$13,354.80
Over/Under Est: 66.11% $1,471,470.53
Amt Left: 61.3% $1,405,043.96
Delta: -44.45% -$1,137,646.53
Subcontractor Percentage Amount
HARDY HOLE DRILLING 15.71% $360,084.52
WILLOW CITY SIGN & RAIL, INC. 2.96% $67,845.33
J. R. (JOE) RAMON & SONS, INC. 2.41% $55,238.94
BLACKSMITH VENTURES LLC 1.75% $40,111.26
TORO BRAVO CONSTRUCTION, LLC 1.69% $38,736.02
LONE STAR PAVING COMPANY 1.23% $28,192.49
SOUTH TEXAS TRAFFIC ALLIANCE INC. 1.05% $24,066.76
WOOLERY CUSTOM FENCE CO. 0.56% $12,835.60
HOUSTON SAWING & DRILLING 0.39% $8,939.08
LONE STAR EROSION CONTROL 0.37% $8,480.67
Total: 28.12% $644,530.67

Bid Items & Bid Tabulations

52 Total 0 of 52
WHARTON  |  CR  |  YOAKUM  |  0913-09-115  |  05/02/2024  |  $2,225,645.50  |  BR 2022(482)  |  BRIDGE REPL  |  195 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
C. E. BARKER, LTD.
A GREATER AUSTIN DEVELOPMENT COMPANY, LLC
EARTH BUILDERS, L.P.
STX CIVIL
JOHN REED AND COMPANY, LLC
TEXAS MATERIALS GROUP, INC.
PREPARING ROW
STA 6.500 $4,000.000 $18,000.000 $10,560.000 $10,000.000 $8,891.000 $24,000.000 $12,300.000
EXCAVATION (ROADWAY)
CY 916.000 $30.000 $20.350 $27.800 $30.000 $20.000 $60.000 $40.500
EXCAVATION (CHANNEL)
CY 1,080.000 $25.000 $20.350 $25.750 $30.000 $22.000 $60.000 $42.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 225.000 $30.000 $33.390 $30.900 $35.000 $18.000 $60.000 $73.000
BLADING
HR 32.000 $150.000 $114.770 $61.800 $125.000 $212.000 $30.000 $148.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 2,905.000 $1.000 $1.040 $0.500 $0.800 $2.000 $0.300 $0.850
BROADCAST SEED (TEMP) (WARM)
SY 737.000 $75.000 $1.040 $0.350 $0.800 $2.000 $0.300 $2.300
BROADCAST SEED (TEMP) (COOL)
SY 737.000 $1.000 $1.040 $0.350 $0.800 $2.000 $0.300 $2.300
VEGETATIVE WATERING
MG 16.800 $80.000 $125.210 $200.000 $50.000 $58.000 $100.000 $365.000
FL BS (CMP IN PLC)(TY E GR 5)(FNL POS)
CY 484.000 $125.000 $185.720 $172.000 $180.000 $321.000 $160.000 $180.000
ASPH (RC-250)
GAL 435.000 $12.000 $10.430 $25.000 $20.000 $29.000 $40.000 $16.000
AGGR(TY-E GR-5 SAC-B)
CY 15.000 $900.000 $584.300 $1,465.000 $450.000 $2,337.000 $2,500.000 $1,400.000
AGGR(TY-PE GR-4 SAC-B)
CY 16.000 $900.000 $391.270 $1,450.000 $450.000 $2,921.000 $2,600.000 $1,300.000
ASPH (AC 20-5TR OR AC-20XP OR CRS-2P)
GAL 677.000 $6.000 $4.590 $17.850 $20.000 $18.000 $12.000 $12.000
CEM STABIL BKFL
CY 137.000 $220.000 $80.340 $270.000 $250.000 $175.000 $150.000 $365.000
DRILL SHAFT (18 IN)
LF 198.000 $240.000 $226.830 $125.000 $165.000 $141.000 $150.000 $192.000
DRILL SHAFT (24 IN)
LF 627.000 $300.000 $264.620 $206.800 $230.000 $199.000 $300.000 $330.000
DRILL SHAFT (36 IN)
LF 666.000 $265.000 $329.920 $305.300 $330.000 $278.000 $450.000 $645.000
CL C CONC (ABUT)
CY 74.600 $1,300.000 $859.430 $1,170.000 $1,500.000 $1,576.000 $1,600.000 $2,250.000
CL C CONC (CAP)
CY 46.800 $1,400.000 $1,751.780 $1,335.000 $1,500.000 $2,038.000 $1,600.000 $3,000.000
CL C CONC (COLUMN)
CY 18.800 $1,600.000 $1,343.420 $1,965.000 $1,500.000 $3,010.000 $1,600.000 $6,400.000
REINF CONC SLAB
SF 3,770.000 $23.000 $23.360 $34.000 $30.000 $23.000 $26.000 $52.000
REINF CONC SLAB (SLAB BEAM)
SF 3,900.000 $23.000 $23.250 $23.500 $25.000 $23.000 $15.000 $42.000
PRESTR CONC SLAB BEAM (5SB15)
LF 742.500 $225.000 $231.790 $211.100 $280.000 $187.000 $205.000 $306.000
PRESTR CONC GIRDER (TX28)
LF 573.180 $225.000 $274.020 $263.600 $240.000 $235.000 $260.000 $231.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 1,509.000 $175.000 $176.070 $195.400 $250.000 $254.000 $105.000 $271.000
RAIL (TY T223)
LF 686.000 $140.000 $105.340 $150.000 $150.000 $178.000 $110.000 $177.000
ARMOR JOINT (SEALED)
LF 108.000 $150.000 $104.340 $140.000 $150.000 $179.000 $78.000 $217.000
RC PIPE (CL III)(18 IN)
LF 172.000 $150.000 $84.240 $80.000 $95.000 $122.000 $80.000 $109.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 7.000 $2,000.000 $4,069.220 $2,815.000 $2,000.000 $2,461.000 $1,800.000 $1,800.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $35,500.000 $41,735.600 $27,500.000 $25,000.000 $44,370.000 $60,000.000 $69,800.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $60,000.000 $62,603.400 $47,000.000 $70,000.000 $89,442.000 $140,000.000 $99,000.000
REMOV STR (SMALL)
EA 5.000 $2,000.000 $3,651.870 $850.000 $2,500.000 $412.000 $750.000 $730.000
MOBILIZATION
LS 1.000 $199,000.000 $220,000.000 $230,000.000 $240,000.000 $210,000.000 $250,000.000 $602,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 13.000 $3,000.000 $3,130.170 $3,215.000 $2,000.000 $2,231.000 $2,000.000 $1,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,102.000 $4.000 $3.130 $3.900 $4.000 $6.000 $4.000 $6.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,102.000 $2.000 $1.570 $2.000 $2.000 $1.000 $1.000 $1.000
DRIVEWAYS (SURF TREAT)
SY 193.000 $70.000 $57.390 $120.000 $70.000 $234.000 $50.000 $4.500
DRIVEWAYS (BASE)
SY 14.000 $70.000 $41.740 $82.400 $55.000 $117.000 $60.000 $135.000
MTL W-BEAM GD FEN (TIM POST)
LF 87.500 $25.000 $33.920 $26.550 $45.000 $36.000 $31.000 $37.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 5.000 $2,300.000 $2,347.630 $2,630.000 $1,600.000 $1,877.000 $1,607.000 $2,600.000
MTL BEAM GD FEN TRANS (TL2)
EA 2.000 $1,800.000 $1,721.590 $1,290.000 $1,600.000 $1,247.000 $1,067.000 $1,900.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $2,000.000 $1,617.250 $1,340.000 $1,600.000 $1,727.000 $1,478.000 $1,800.000
GUARDRAIL END TREATMENT (INSTALL)
EA 5.000 $3,200.000 $3,234.510 $3,090.000 $2,800.000 $3,561.000 $3,048.000 $3,600.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 1.000 $27,000.000 $31,145.190 $32,455.000 $31,000.000 $31,544.000 $27,000.000 $34,200.000
WIRE FENCE (TY A)
LF 660.000 $20.000 $16.690 $20.000 $15.000 $20.000 $50.000 $21.000
GATE (TY 1)
EA 1.000 $2,500.000 $834.710 $2,500.000 $1,500.000 $1,700.000 $2,000.000 $2,060.000
MAILBOX INSTALL-M (TWG-POST) TY 1
EA 1.000 $500.000 $719.940 $840.000 $350.000 $853.000 $730.000 $790.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 1.000 $500.000 $626.030 $1,070.000 $500.000 $643.000 $550.000 $690.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 14.000 $30.000 $26.080 $19.000 $20.000 $29.000 $25.000 $29.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 8.000 $35.000 $36.520 $26.000 $50.000 $32.000 $27.000 $40.000
TMA (STATIONARY)
DAY 20.000 $300.000 $417.360 $360.000 $250.000 $260.000 $235.000 $400.000
Totals: $2,225,645.500 $2,292,072.105 $2,318,279.273 $2,464,030.900 $2,546,114.700 $2,559,469.500 $3,697,116.030