Show Job Controls
Bid Cobra

WHARTON CR (0913-09-089)

Items: 65

County: WHARTON
Length: N/A
Highway: CR
District: YOAKUM
Control Number: 0913-09-089
DBE Goal: N/A
Project: BR 1702(587)
Guaranty: N/A
Time: 352 WORKING DAYS
Engineer's Estimate: $3,424,358.20
Date: 02/07/2020 (6 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$3,424,358.20
1
$3,985,642.29
Over/Under Est: 16.39% $561,284.09
Over/Under Est: 24.11% $825,459.85
Amt Left: 6.63% $264,175.76
Over/Under Est: 59.66% $2,042,894.97
Amt Left: 37.17% $1,481,610.88
Delta: -28.65% -$1,217,435.12
Subcontractor Percentage Amount
HEMPHILL WBE PILE DRIVING CO. 7.67% $305,698.76
WEBER-BALKE FOUNDATION COMPANY, INC 5.76% $229,573.00
LONE STAR PAVING COMPANY 1.83% $72,937.25
LONESTAR TRAFFIC SAFETY, LLC 0.36% $14,348.31
Total: 15.62% $622,557.32

Bid Items & Bid Tabulations

65 Total 0 of 65
WHARTON  |  CR  |  YOAKUM  |  0913-09-089  |  02/07/2020  |  $3,424,358.20  |  BR 1702(587)  |  REPLACE BRIDGE AND APPROACHES  |  352 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TREVWAY, INC.
STATELINE CONSTRUCTION, LLC
ANGEL BROTHERS HOLDINGS CORP.
PREPARING ROW
STA 15.400 $3,000.000 $4,500.000 $2,200.000 $27,000.000
EXCAVATION (ROADWAY)
CY 508.000 $25.000 $12.000 $16.000 $80.000
EXCAVATION (CHANNEL)
CY 256.000 $25.000 $12.000 $45.000 $80.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 1,911.000 $30.000 $13.000 $18.000 $80.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 319.000 $30.000 $13.000 $24.000 $80.000
BLADING
HR 78.000 $100.000 $25.000 $145.000 $100.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 4,695.000 $2.000 $0.550 $1.000 $0.500
BROADCAST SEED (TEMP) (WARM)
SY 1,174.000 $2.000 $0.550 $0.900 $0.400
BROADCAST SEED (TEMP) (COOL)
SY 1,174.000 $2.000 $0.550 $0.900 $0.400
VEGETATIVE WATERING
MG 40.500 $50.000 $25.000 $25.000 $100.000
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)
CY 1,134.000 $110.000 $110.000 $85.000 $148.000
ASPH (RC-250)
GAL 692.000 $20.000 $15.000 $16.000 $19.000
AGGR(TY-E GR-5 SAC-B)
CY 28.000 $400.000 $900.000 $800.000 $730.000
AGGR(TY-PE GR-4 SAC-B)
CY 31.700 $400.000 $850.000 $800.000 $730.000
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
GAL 1,174.000 $20.000 $16.000 $26.000 $19.000
CEM STABIL BKFL
CY 400.000 $100.000 $100.000 $345.000 $230.000
SHEET PILING (PZ - 40)
SF 14,892.000 $55.000 $60.260 $66.000 $60.000
PRESTR CONC PIL (18 IN SQ)
LF 1,921.000 $100.000 $148.740 $146.000 $200.000
DRILL SHAFT (18 IN)
LF 116.000 $100.000 $518.000 $225.000 $170.000
DRILL SHAFT (36 IN)
LF 431.000 $200.000 $981.000 $795.000 $700.000
CL C CONC (ABUT)
CY 148.200 $1,100.000 $650.000 $1,150.000 $2,000.000
CL C CONC (CAP)
CY 50.100 $1,200.000 $1,500.000 $1,475.000 $2,000.000
CL C CONC (COLUMN)(HPC)
CY 7.100 $1,500.000 $2,800.000 $1,550.000 $4,000.000
REINF CONC SLAB
SF 3,360.000 $20.000 $18.000 $28.000 $34.000
REINF CONC SLAB (SLAB BEAM)
SF 10,223.000 $20.000 $18.000 $19.000 $30.000
PRESTR CONC SLAB BEAM (4SB12)
LF 788.000 $170.000 $163.000 $145.000 $190.000
PRESTR CONC SLAB BEAM (5SB12)
LF 742.500 $140.000 $164.550 $145.000 $193.000
PRESTR CONC SLAB BEAM (4SB15)
LF 395.860 $170.000 $188.000 $145.000 $198.000
PRESTR CONC SLAB BEAM (5SB15)
LF 296.890 $170.000 $203.000 $145.000 $221.000
PRESTR CONC GIRDER (TX28)
LF 415.180 $140.000 $250.000 $145.000 $200.000
RIPRAP (CONC)(CL B)(5 IN)
CY 26.000 $500.000 $490.000 $485.000 $750.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 677.000 $140.000 $150.000 $168.000 $180.000
RIPRAP (CONC) (CHANNEL) (4IN)
CY 8.000 $150.000 $600.000 $1,000.000 $700.000
RAIL (TY T223)
LF 610.000 $100.000 $145.000 $118.000 $170.000
RAIL (TY T631)
LF 448.000 $100.000 $81.000 $95.000 $94.000
ARMOR JOINT (SEALED)
LF 274.000 $85.000 $55.000 $95.000 $115.000
CONC BOX CULV (6 FT X 3 FT)
LF 130.000 $360.000 $495.000 $695.000 $550.000
RC PIPE (CL III)(18 IN)
LF 40.000 $65.000 $78.860 $48.000 $60.000
RC PIPE (CL III)(24 IN)
LF 272.000 $70.000 $101.980 $65.000 $130.000
RC PIPE (CL III)(30 IN)
LF 120.000 $100.000 $100.000 $90.000 $160.000
RC PIPE (CL IV)(36 IN)
LF 44.000 $100.000 $187.000 $125.000 $200.000
SET (TY I)(S= 6 FT)(HW= 4 FT)(6:1) (P)
EA 1.000 $7,800.000 $15,000.000 $8,500.000 $14,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 2.000 $2,100.000 $1,500.000 $750.000 $1,000.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 2.000 $2,200.000 $2,778.000 $900.000 $1,300.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 1.000 $2,200.000 $4,444.000 $1,400.000 $2,700.000
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 1.000 $2,600.000 $4,500.000 $1,950.000 $3,700.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 5.000 $35,000.000 $20,000.000 $36,000.000 $30,000.000
REMOV STR (RET WALL)
LF 183.000 $55.000 $25.000 $63.000 $300.000
REMOV STR (SMALL)
EA 2.000 $500.000 $500.000 $1,500.000 $1,700.000
MOBILIZATION
LS 1.000 $300,000.000 $400,000.000 $400,000.000 $500,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 24.000 $3,000.000 $800.000 $5,500.000 $7,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 112.000 $30.000 $18.000 $30.000 $42.000
ROCK FILTER DAMS (REMOVE)
LF 112.000 $11.000 $10.000 $5.000 $20.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 3,050.000 $3.000 $3.000 $3.000 $3.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 3,050.000 $1.000 $0.500 $1.000 $1.700
MTL W-BEAM GD FEN (TIM POST)
LF 337.500 $25.000 $32.000 $23.000 $30.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 12.000 $1,800.000 $1,619.000 $1,500.000 $2,400.000
SHORT RADIUS
LF 16.000 $30.000 $122.000 $65.000 $37.000
DRIVEWAY TERMINAL ANCHOR SECTION
EA 1.000 $1,000.000 $2,017.000 $1,800.000 $1,000.000
GUARDRAIL END TREATMENT (INSTALL)
EA 19.000 $2,800.000 $2,497.000 $2,795.000 $3,000.000
WIRE FENCE (TY A)
LF 456.000 $20.000 $12.000 $17.000 $20.000
MAILBOX INSTALL-S (WC-POST) TY 3
EA 1.000 $200.000 $200.000 $600.000 $260.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 20.000 $11.000 $25.000 $65.000 $25.000
INSTL DEL ASSM (D-SY)SZ 2(WC)GND
EA 1.000 $50.000 $25.000 $65.000 $60.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 41.000 $20.000 $25.000 $65.000 $30.000
Totals: $3,424,358.200 $3,985,642.295 $4,249,818.050 $5,467,253.170