Bid Cobra

WHARTON CR (0913-09-073)

Items: 56

County: WHARTON
Length: N/A
Highway: CR
District: YOAKUM
Control Number: 0913-09-073
DBE Goal: N/A
Project: BR 2017(100)
Guaranty: N/A
Time: 144 WORKING DAYS
Engineer's Estimate: $1,098,938.40
Date: 05/01/2018 (8 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$1,098,938.40
$980,970.40
Over/Under Est: -10.73% -$117,968.00
$1,041,288.90
Over/Under Est: -5.25% -$57,649.50
Amt Left: 6.15% $60,318.50
Over/Under Est: 2.04% $22,431.25
Amt Left: 14.31% $140,399.25
Delta: -7.69% -$80,080.75
$1,248,170.48
Over/Under Est: 13.58% $149,232.08
Amt Left: 27.24% $267,200.08
Delta: -11.31% -$126,800.83
Over/Under Est: 22.19% $243,822.26
Amt Left: 36.88% $361,790.26
Delta: -7.58% -$94,590.18
$1,344,054.20
Over/Under Est: 22.3% $245,115.80
Amt Left: 37.01% $363,083.80
Delta: -0.10% -$1,293.54
Over/Under Est: 41% $450,601.30
Amt Left: 57.96% $568,569.30
Delta: -15.29% -$205,485.50

Bid Items & Bid Tabulations

56 Total 0 of 56
WHARTON  |  CR  |  YOAKUM  |  0913-09-073  |  05/01/2018  |  $1,098,938.40  |  BR 2017(100)  |  REPLACE BRIDGE AND APPROACHES  |  144 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
JOHN REED AND COMPANY, LLC
TREVWAY, INC.
HILL COUNTRY BRIDGE, INC.
ISI CONTRACTING, INC.
REXCO CONSTRUCTION SERVICES, INC.
CONSTAR CONSTRUCTION
A GREATER AUSTIN DEVELOPMENT COMPANY, LTD.
PREPARING ROW
STA 9.060 $3,000.000 $2,000.000 $900.000 $4,500.000 $6,000.000 $7,620.000 $2,000.000 $1,500.000
EXCAVATION (ROADWAY AND CHANNEL)
CY 875.000 $20.000 $20.000 $5.000 $16.300 $20.000 $40.000 $20.000 $42.100
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 990.000 $25.000 $20.000 $9.000 $22.600 $31.000 $40.600 $30.000 $49.750
BLADING
HR 50.000 $100.000 $20.000 $50.000 $89.300 $57.000 $100.000 $100.000 $125.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 3,120.000 $2.000 $0.300 $0.250 $1.250 $0.450 $1.250 $2.000 $1.000
BROADCAST SEED (TEMP) (WARM)
SY 780.000 $2.000 $0.300 $0.250 $1.500 $1.700 $1.560 $2.000 $1.000
BROADCAST SEED (TEMP) (COOL)
SY 780.000 $2.000 $0.300 $0.250 $1.500 $1.700 $1.560 $2.000 $1.000
VEGETATIVE WATERING
MG 26.200 $80.000 $20.000 $50.000 $160.000 $20.000 $78.000 $150.000 $100.000
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)
CY 549.000 $120.000 $140.000 $125.000 $135.900 $130.000 $146.440 $120.000 $145.000
PRIME COAT (MC-30)
GAL 389.000 $20.000 $10.000 $22.000 $8.150 $5.000 $8.900 $18.000 $13.000
AGGR(TY-PB GR-4 SAC-B)
CY 28.000 $200.000 $160.000 $378.000 $281.000 $250.000 $583.000 $400.000 $390.000
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
GAL 1,326.000 $10.000 $6.000 $14.000 $6.650 $4.000 $6.050 $20.000 $13.650
CEM STABIL BKFL
CY 298.000 $90.000 $50.000 $130.000 $130.400 $50.000 $120.640 $100.000 $210.000
TEMPORARY SPL SHORING
SF 560.000 $20.000 $1.000 $9.000 $17.100 $10.000 $10.200 $25.000 $35.000
PRESTR CONC PIL (16 IN SQ)
LF 480.000 $120.000 $140.000 $129.000 $88.500 $120.000 $140.520 $120.000 $100.000
DRILL SHAFT (36 IN)
LF 234.000 $220.000 $250.000 $266.000 $222.750 $235.000 $259.480 $300.000 $230.000
CL C CONC (ABUT)
CY 62.600 $850.000 $1,000.000 $458.220 $815.000 $900.000 $1,153.000 $1,000.000 $1,000.000
CL C CONC (CAP)
CY 16.600 $850.000 $1,000.000 $417.280 $1,060.000 $1,350.000 $2,275.320 $1,600.000 $1,600.000
REINF CONC SLAB
SF 1,950.000 $20.000 $10.000 $21.000 $26.600 $23.000 $30.430 $36.000 $27.000
REINF CONC SLAB (SLAB BEAM)
SF 2,892.000 $20.000 $5.000 $21.000 $15.450 $16.000 $20.990 $20.000 $18.000
PRESTR CONC SLAB BEAM (4SB12)
LF 707.860 $140.000 $160.000 $139.000 $124.600 $148.000 $121.670 $170.000 $150.000
PRESTR CONC GIRDER (TX28)
LF 297.930 $200.000 $160.000 $174.000 $197.500 $210.000 $207.450 $200.000 $170.000
RIPRAP (CONC)(5 IN)
CY 8.800 $450.000 $300.000 $500.000 $763.000 $490.000 $529.600 $460.000 $520.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 450.000 $120.000 $100.000 $136.810 $149.600 $180.000 $121.320 $175.000 $200.000
RAIL (TY T223)
LF 402.000 $100.000 $85.000 $85.280 $99.300 $90.000 $122.260 $150.000 $180.000
ARMOR JOINT (SEALED)
LF 104.000 $80.000 $54.000 $65.000 $61.300 $80.000 $70.850 $65.000 $140.000
CONC BOX CULV (8 FT X 5 FT)
LF 96.000 $800.000 $600.000 $560.870 $598.000 $560.000 $600.940 $800.000 $1,800.000
RC PIPE (CL III)(18 IN)
LF 32.000 $80.000 $90.000 $78.600 $65.000 $72.000 $70.960 $55.000 $170.000
RC PIPE (CL III)(24 IN)
LF 20.000 $60.000 $100.000 $117.420 $98.700 $84.000 $85.160 $75.000 $150.000
RC PIPE (CL III)(42 IN)
LF 152.000 $180.000 $140.000 $174.500 $126.600 $164.000 $142.500 $190.000 $370.000
WINGWALL (SW - 0) (HW=6 FT)
EA 2.000 $9,000.000 $4,000.000 $5,048.000 $5,720.000 $17,000.000 $23,928.000 $15,000.000 $9,100.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 2.000 $1,500.000 $1,200.000 $2,000.000 $940.000 $1,600.000 $2,244.480 $1,400.000 $2,200.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 2.000 $1,800.000 $1,400.000 $4,400.000 $1,355.000 $2,000.000 $2,376.560 $1,600.000 $2,800.000
SET (TY II) (42 IN) (RCP) (6: 1) (P)
EA 1.000 $4,500.000 $3,000.000 $6,400.000 $5,490.000 $3,100.000 $6,111.520 $4,000.000 $8,700.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 3.000 $12,000.000 $20,000.000 $20,000.000 $15,500.000 $32,000.000 $13,000.000 $12,000.000 $21,300.000
REMOV STR (SMALL)
EA 1.000 $500.000 $300.000 $5,000.000 $1,550.000 $600.000 $1,500.000 $1,000.000 $1,600.000
MOBILIZATION
LS 1.000 $95,000.000 $96,000.000 $100,000.000 $110,000.000 $125,000.000 $140,000.000 $140,000.000 $154,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $2,500.000 $1,200.000 $800.000 $3,000.000 $3,000.000 $2,246.400 $1,500.000 $4,500.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 150.000 $30.000 $30.000 $12.000 $40.700 $55.000 $51.480 $50.000 $48.000
ROCK FILTER DAMS (REMOVE)
LF 150.000 $5.000 $10.000 $3.000 $15.500 $11.000 $9.670 $25.000 $26.500
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,514.000 $3.000 $3.000 $3.500 $2.720 $4.250 $3.980 $6.000 $3.200
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,514.000 $1.000 $1.000 $1.000 $1.250 $1.100 $0.970 $2.000 $1.100
DRIVEWAYS (SURF TREAT)
SY 147.000 $30.000 $40.000 $53.000 $81.800 $90.000 $31.000 $90.000 $48.000
MTL W-BEAM GD FEN (TIM POST)
LF 50.000 $25.000 $37.000 $39.340 $37.350 $25.000 $38.060 $50.000 $22.500
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 6.000 $1,200.000 $1,868.000 $1,726.210 $2,030.000 $2,200.000 $2,064.400 $2,700.000 $2,500.000
SHORT RADIUS
LF 24.000 $50.000 $40.000 $82.690 $52.000 $50.000 $52.990 $60.000 $42.500
DRIVEWAY TERMINAL ANCHOR SECTION
EA 2.000 $1,000.000 $900.000 $1,180.520 $740.000 $680.000 $754.000 $1,000.000 $960.000
MTL BEAM GD FEN TRANS(THRIE BEAM)28"
EA 2.000 $2,500.000 $1,625.000 $1,673.160 $2,030.000 $2,200.000 $2,064.400 $2,700.000 $1,700.000
GUARDRAIL END TREATMENT (INSTALL)
EA 6.000 $2,200.000 $2,200.000 $2,505.580 $2,785.000 $2,600.000 $2,836.080 $2,700.000 $2,300.000
WIRE FENCE (TY A)
LF 144.000 $15.000 $30.000 $22.000 $15.300 $17.000 $20.800 $40.000 $16.000
GATE (TY 1)
EA 1.000 $1,200.000 $2,500.000 $1,500.000 $1,000.000 $1,000.000 $364.000 $600.000 $2,700.000
RELOCATE SM RD SN SUP&AM TY TWT
EA 1.000 $450.000 $600.000 $781.540 $510.000 $800.000 $260.000 $400.000 $450.000
REMOVE SM RD SN SUP&AM
EA 6.000 $50.000 $50.000 $50.000 $80.000 $80.000 $52.000 $200.000 $80.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 8.000 $25.000 $10.000 $53.900 $15.300 $23.000 $15.600 $50.000 $10.500
INSTL OM ASSM (OM-2Z)(FLX)GND(BI)
EA 4.000 $65.000 $50.000 $70.000 $49.000 $70.000 $49.920 $70.000 $53.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 15.000 $30.000 $20.000 $11.370 $15.300 $31.000 $15.600 $90.000 $21.500
Totals: $1,098,938.400 $980,970.400 $1,041,288.910 $1,121,369.661 $1,248,170.480 $1,342,760.677 $1,344,054.200 $1,549,539.700