Bid Cobra

WHARTON CR (0913-09-060)

Items: 44

County: WHARTON
Length: N/A
Highway: CR
District: YOAKUM
Control Number: 0913-09-060
DBE Goal: N/A
Project: BR 1502(637)
Guaranty: N/A
Time: 100 WORKING DAYS
Engineer's Estimate: $991,998.75
Date: 01/05/2017 (9 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$991,998.75
$902,792.10
Over/Under Est: -8.99% -$89,206.65
Over/Under Est: -6.19% -$61,438.95
Amt Left: 3.08% $27,767.70
$976,539.54
Over/Under Est: -1.56% -$15,459.21
Amt Left: 8.17% $73,747.44
Delta: -4.94% -$45,979.74
Over/Under Est: 0.27% $2,710.60
Amt Left: 10.18% $91,917.25
Delta: -1.86% -$18,169.81
Over/Under Est: 36.46% $361,679.21
Amt Left: 49.94% $450,885.86
Delta: -36.09% -$358,968.61
Over/Under Est: 56.84% $563,881.93
Amt Left: 72.34% $653,088.58
Delta: -14.94% -$202,202.72

Bid Items & Bid Tabulations

44 Total 0 of 44
WHARTON  |  CR  |  YOAKUM  |  0913-09-060  |  01/05/2017  |  $991,998.75  |  BR 1502(637)  |  REPLACE BRIDGE AND APPROACHES  |  100 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
JOHN REED AND COMPANY, LLC
CONSTAR CONSTRUCTION
TREVWAY, INC.
ISI CONTRACTING, INC.
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
JAY-REESE CONTRACTORS, INC.
PREPARING ROW(TREE)(5" TO 12" DIA)
EA 13.000 $500.000 $200.000 $300.000 $300.000 $500.000 $1,000.000 $400.000
PREPARING ROW(TREE)(12" TO 24" DIA)
EA 4.000 $800.000 $600.000 $600.000 $300.000 $850.000 $2,200.000 $600.000
EXCAVATION (ROADWAY)
CY 130.000 $25.000 $30.000 $24.000 $17.000 $23.000 $50.000 $35.000
EXCAVATION (CHANNEL)
CY 67.000 $20.000 $40.000 $23.000 $22.190 $36.000 $150.000 $50.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 2,147.000 $25.000 $15.000 $14.000 $18.120 $24.000 $40.000 $47.000
BLADING
HR 20.000 $150.000 $20.000 $100.000 $50.000 $98.000 $115.000 $125.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 2,821.000 $0.750 $0.100 $1.000 $0.500 $0.550 $0.560 $0.580
BROADCAST SEED (TEMP) (WARM)
SY 705.000 $0.750 $0.100 $1.000 $1.000 $1.600 $1.700 $1.750
BROADCAST SEED (TEMP) (COOL)
SY 705.000 $0.750 $0.100 $1.000 $1.000 $1.600 $1.700 $1.750
VEGETATIVE WATERING
MG 15.700 $60.000 $20.000 $120.000 $80.000 $20.000 $220.000 $85.000
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)
CY 379.000 $125.000 $94.000 $120.000 $160.000 $98.000 $190.000 $155.000
CEM STABIL BKFL
CY 121.700 $150.000 $46.000 $70.000 $150.000 $78.000 $84.000 $285.000
TRENCH EXCAVATION PROTECTION
LF 205.000 $25.000 $2.000 $10.000 $7.000 $1.000 $11.000 $30.000
SHEET PILING (PZ - 27)
SF 4,865.000 $37.000 $36.000 $46.000 $42.780 $34.000 $39.500 $70.000
PRESTR CONC PIL (18 IN SQ)
LF 864.000 $110.000 $110.000 $86.000 $87.190 $80.000 $80.000 $110.000
CL C CONC (ABUT)
CY 44.800 $1,000.000 $1,000.000 $900.000 $475.000 $840.000 $1,100.000 $1,600.000
REINF CONC SLAB
SF 2,560.000 $20.000 $14.000 $25.000 $25.410 $17.000 $25.000 $38.000
PRESTR CONC BOX BEAM (5XB28)
LF 317.680 $200.000 $180.000 $210.000 $232.000 $190.000 $230.000 $250.000
RIPRAP (CONC)(5 IN)
CY 8.500 $425.000 $450.000 $250.000 $300.000 $310.000 $780.000 $1,100.000
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 98.000 $180.000 $180.000 $130.000 $175.000 $150.000 $200.000 $140.000
RAIL (TY T631)
LF 200.000 $100.000 $90.000 $80.000 $86.000 $110.000 $80.000 $100.000
CMP (GAL STL 24 IN)
LF 475.000 $50.000 $26.000 $27.000 $33.560 $43.000 $72.000 $100.000
CMP (GAL STL 48 IN)
LF 150.000 $90.000 $58.000 $47.000 $80.890 $120.000 $150.000 $140.000
CONC BOX CULV (9 FT X 8 FT)
LF 124.200 $800.000 $460.000 $600.000 $537.000 $680.000 $1,445.000 $525.000
WINGWALL (PW - 1) (HW=9 FT)
EA 2.000 $25,000.000 $25,000.000 $20,000.000 $15,000.000 $30,000.000 $45,700.000 $60,000.000
SET (TY II) (24 IN) (CMP) (6: 1) (P)
EA 5.000 $1,600.000 $500.000 $1,200.000 $676.340 $1,600.000 $2,100.000 $1,900.000
SET (TY II) (48 IN) (CMP) (6: 1) (P)
EA 1.000 $6,000.000 $4,500.000 $4,000.000 $3,307.850 $8,300.000 $8,000.000 $2,900.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $10,000.000 $20,000.000 $10,000.000 $15,000.000 $19,000.000 $20,000.000 $18,000.000
REMOV STR (PIPE)
EA 2.000 $500.000 $500.000 $500.000 $700.000 $100.000 $560.000 $1,500.000
MOBILIZATION
LS 1.000 $50,000.000 $90,000.000 $50,000.000 $100,000.000 $98,000.000 $135,000.000 $145,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $2,500.000 $1,600.000 $1,000.000 $900.000 $1,800.000 $2,500.000 $450.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 100.000 $35.000 $50.000 $50.000 $10.000 $42.000 $41.500 $45.000
ROCK FILTER DAMS (REMOVE)
LF 100.000 $10.000 $20.000 $25.000 $1.000 $15.000 $15.000 $15.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 860.000 $4.500 $3.000 $6.000 $3.000 $5.000 $5.000 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 860.000 $2.000 $1.000 $2.000 $0.300 $1.500 $1.400 $1.400
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 240.000 $40.000 $52.830 $80.000 $70.000 $85.000 $41.000 $160.000
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 240.000 $12.000 $13.130 $35.000 $10.000 $35.000 $12.500 $50.000
MTL W-BEAM GD FEN (TIM POST)
LF 75.000 $20.000 $20.000 $30.000 $35.000 $15.000 $23.500 $35.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 75.000 $50.000 $56.000 $80.000 $90.000 $42.000 $68.000 $98.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $2,200.000 $2,000.000 $2,000.000 $2,500.000 $1,900.000 $2,400.000 $2,450.000
CRASH CUSH ATTEN (INSTL)
EA 4.000 $8,000.000 $10,000.000 $8,000.000 $10,000.000 $12,000.000 $12,800.000 $13,500.000
CRASH CUSH ATTEN (REMOVE)
EA 4.000 $800.000 $750.000 $1,000.000 $200.000 $950.000 $990.000 $1,380.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
EA 12.000 $30.000 $19.000 $50.000 $26.000 $3.000 $21.000 $30.000
INSTL OM ASSM (OM-2Y)(WC)GND(BI)
EA 4.000 $60.000 $47.000 $40.000 $65.000 $50.000 $52.000 $75.000
Totals: $991,998.750 $902,792.100 $930,559.800 $976,539.540 $994,709.350 $1,353,677.960 $1,555,880.680