WHARTON SH 71 (0266-06-050)
Items: 40
County: WHARTON
Length: N/A
Highway: SH 71
District: YOAKUM
Control Number: 0266-06-050
DBE Goal: N/A
Project: F 2B23(080)
Guaranty: N/A
Time: 180 WORKING DAYS
Engineer's Estimate: $3,361,293.50
Date: 08/03/2023 (2 years ago)
Contract Number: N/A
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Mail/Deliver Bids To: N/A
RYAN SIMPER
PAUL RODRIGUEZ
Bidders (3)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$3,361,293.50 | |||
| $3,057,574.82 |
-9.04%
-$303,718.68
|
|||
| $3,377,740.00 |
0.49%
$16,446.50
|
10.47%
$320,165.18
|
||
| $4,014,115.00 |
19.42%
$652,821.50
|
31.28%
$956,540.18
|
-18.84%
-$636,375.00
|
E
Engineer's Estimate
$3,361,293.50
1
Awarded
$3,057,574.82
Over/Under Est:
-9.04%
-$303,718.68
$3,377,740.00
Over/Under Est:
0.49%
$16,446.50
Amt Left:
10.47%
$320,165.18
$4,014,115.00
Over/Under Est:
19.42%
$652,821.50
Amt Left:
31.28%
$956,540.18
Delta:
-18.84%
-$636,375.00
| Subcontractor | Percentage | Amount |
|---|---|---|
| PBJ CONSTRUCTION | 5.13% | $156,853.59 |
| ROBIN STEEL LLC | 0.89% | $27,212.42 |
| AWP SAFETY | 0.65% | $19,874.24 |
| HIGHWAY BARRICADES AND SERVICES, LLC | 0.63% | $19,262.72 |
| ASPHALT MAINTENANCE, INC. | 0.41% | $12,536.06 |
| Total: | 7.71% | $235,739.03 |
Bid Items & Bid Tabulations
40
Total
0 of 40