WHARTON BU 59-R (0089-10-030)

Items: 47

County: WHARTON
Length: N/A
Highway: BU 59-R
District: YOAKUM
Control Number: 0089-10-030
DBE Goal: 450.0%
Project: BR 2024(812)
Guaranty: N/A
Time: 60 WORKING DAYS
Engineer's Estimate: $976,185.00
Date: 03/06/2024 (2 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
RYAN SIMPER
PAUL RODRIGUEZ
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$976,185.00
$1,257,172.30
Over/Under Est: 28.78% $280,987.30
$1,283,819.48
Over/Under Est: 31.51% $307,634.48
Amt Left: 2.12% $26,647.18
$1,394,908.00
Over/Under Est: 42.89% $418,723.00
Amt Left: 10.96% $137,735.70
Delta: -8.65% -$111,088.52
$1,675,560.79
Over/Under Est: 71.64% $699,375.79
Amt Left: 33.28% $418,388.49
Delta: -20.12% -$280,652.79
$1,850,573.00
Over/Under Est: 89.57% $874,388.00
Amt Left: 47.2% $593,400.70
Delta: -10.44% -$175,012.21
Over/Under Est: 92.56% $903,566.10
Amt Left: 49.52% $622,578.80
Delta: -1.58% -$29,178.10
Subcontractor Percentage Amount
LARRY YOUNG PAVING, INC. 23.50% $295,435.49
HIGHWAY 1 LLC 2.51% $31,555.02
WILLOW CITY SIGN & RAIL, INC. 2.10% $26,400.62
SEMARCK LANDSCAPE SERVICES, INC. 0.53% $6,663.01
A K FUQUAY CONSTRUCTION 0.44% $5,531.56
BUYERS BARRICADES HOUSTON, LLC 0.20% $2,514.34
Total: 29.28% $368,100.04

Bid Items & Bid Tabulations

47 Total 0 of 47
WHARTON  |  BU 59-R  |  YOAKUM  |  0089-10-030  |  03/06/2024  |  $976,185.00  |  BR 2024(812)  |  BRIDGE REPL  |  60 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
R CONSTRUCTION CIVIL, LLC
C. E. BARKER, LTD.
ICOS MANAGEMENT, LLC
TREVWAY, INC.
EARTH BUILDERS, L.P.
ARANDA BROTHERS CONSTRUCTION CO., INC.
REMOVING CONC (PAV)
SY 112.000 $20.000 $50.000 $37.750 $165.000 $211.000 $100.000 $20.000
EXCAVATION (ROADWAY)
CY 51.000 $35.000 $35.000 $44.690 $115.000 $220.000 $50.000 $20.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 251.000 $40.000 $30.000 $56.770 $67.000 $178.720 $50.000 $25.000
BLADING
HR 16.000 $175.000 $120.000 $120.790 $550.000 $100.000 $125.000 $100.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 6,115.000 $1.000 $0.600 $0.530 $1.000 $1.000 $1.000 $0.500
BROADCAST SEED (TEMP) (WARM)
SY 1,529.000 $1.000 $1.100 $0.440 $1.000 $1.000 $1.000 $0.750
BROADCAST SEED (TEMP) (COOL)
SY 1,529.000 $1.000 $1.100 $0.440 $1.000 $1.000 $1.000 $0.650
VEGETATIVE WATERING
MG 52.000 $40.000 $140.000 $46.970 $1.000 $99.170 $50.000 $100.000
AGGR(TY-PE GR-4 SAC-B)
CY 22.000 $175.000 $615.000 $362.360 $660.000 $1,677.000 $500.000 $120.000
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
GAL 940.000 $7.500 $6.750 $7.250 $22.000 $13.270 $25.000 $12.000
FLEX PAVEMENT STRUCTURE REPAIR (8"-15")
SY 375.000 $100.000 $150.000 $157.020 $132.000 $35.550 $150.000 $65.000
PLANE ASPH CONC PAV (0" TO 1 1/2")
SY 958.000 $6.000 $6.000 $7.250 $45.000 $12.960 $30.000 $85.000
CEM STABIL BKFL
CY 242.000 $200.000 $80.000 $265.730 $275.000 $150.000 $350.000 $90.000
CUT & RESTORING PAV
SY 270.000 $90.000 $70.000 $144.940 $330.000 $175.000 $150.000 $55.000
TRENCH EXCAVATION PROTECTION
LF 268.000 $12.000 $2.000 $15.770 $1.000 $61.000 $10.000 $1.000
TEMPORARY SPL SHORING
SF 2,532.000 $25.000 $25.000 $30.200 $1.000 $22.000 $30.000 $65.000
RIPRAP (CONC)(5 IN)
CY 31.200 $550.000 $870.000 $641.370 $880.000 $769.000 $650.000 $700.000
CONC BOX CULV (6 FT X 5 FT)
LF 536.000 $600.000 $700.000 $670.720 $880.000 $1,200.000 $1,400.000 $1,600.000
RC PIPE (CL III)(18 IN)
LF 16.000 $150.000 $275.000 $86.780 $550.000 $181.000 $100.000 $100.000
WINGWALL (FW - 0) (HW=6 FT)
EA 2.000 $16,500.000 $10,000.000 $15,098.130 $33,000.000 $23,153.000 $30,000.000 $25,000.000
SET (TY II) (18 IN) (RCP) (4: 1) (P)
EA 2.000 $1,750.000 $2,850.000 $2,584.800 $5,500.000 $3,876.000 $1,500.000 $2,100.000
REMOV STR (BOX CULVERT)
EA 1.000 $30,000.000 $20,000.000 $65,767.430 $2,200.000 $200,000.000 $120,000.000 $50,000.000
MOBILIZATION
LS 1.000 $85,000.000 $200,000.000 $120,000.000 $96,000.000 $100,000.000 $150,000.000 $100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $7,000.000 $2,700.000 $11,051.830 $500.000 $1,000.000 $2,500.000 $12,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 120.000 $40.000 $40.000 $102.670 $22.000 $15.900 $50.000 $40.000
ROCK FILTER DAMS (REMOVE)
LF 120.000 $12.000 $5.000 $24.160 $1.000 $10.740 $10.000 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 80.000 $4.000 $4.000 $7.000 $22.000 $22.860 $12.000 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 80.000 $1.000 $1.000 $1.820 $1.000 $19.000 $6.000 $2.000
MTL W-BEAM GD FEN (TIM POST)
LF 375.000 $27.000 $67.000 $25.670 $44.000 $33.000 $35.000 $30.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 25.000 $75.000 $140.000 $108.710 $88.000 $142.500 $100.000 $130.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,500.000 $4,150.000 $3,454.450 $5,500.000 $3,442.000 $3,600.000 $4,000.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 1.000 $500.000 $950.000 $483.140 $1,100.000 $1,000.000 $1,200.000 $700.000
REMOVE SM RD SN SUP&AM
EA 1.000 $100.000 $200.000 $90.590 $550.000 $300.000 $200.000 $250.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 4.000 $75.000 $95.000 $102.670 $55.000 $42.000 $100.000 $70.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 10.000 $40.000 $40.000 $72.470 $55.000 $14.000 $30.000 $50.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 4,460.000 $1.200 $1.500 $0.740 $2.000 $1.550 $1.500 $3.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 3,480.000 $1.200 $1.500 $0.740 $2.000 $1.550 $1.500 $3.000
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
LF 1,740.000 $3.000 $2.800 $1.990 $2.000 $3.230 $2.900 $6.000
REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL)
LF 2,230.000 $3.000 $2.800 $1.990 $2.000 $3.230 $2.900 $6.000
ELIM EXT PAV MRK & MRKS (4")
LF 3,970.000 $0.500 $0.550 $0.610 $2.000 $0.650 $0.600 $1.500
D-GR HMA TY-B PG64-22
TON 191.000 $115.000 $272.000 $258.480 $275.000 $250.000 $300.000 $220.000
D-GR HMA TY-D SAC-A PG70-22
TON 349.000 $150.000 $345.000 $271.770 $220.000 $325.000 $320.000 $280.000
D-GR HMA TY-D PG70-22 (LEVEL-UP)
TON 242.000 $145.000 $345.000 $271.770 $220.000 $110.000 $320.000 $275.000
TACK COAT
GAL 500.000 $5.750 $6.000 $9.060 $55.000 $22.000 $25.000 $15.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $9,500.000 $2,150.000 $8,496.770 $11,000.000 $7,225.000 $7,000.000 $10,000.000
TMA (STATIONARY)
DAY 80.000 $250.000 $225.000 $326.950 $275.000 $270.000 $200.000 $550.000
TMA (MOBILE OPERATION)
DAY 16.000 $400.000 $950.000 $528.440 $550.000 $387.000 $150.000 $850.000
Totals: $976,185.000 $1,257,172.300 $1,283,819.484 $1,394,908.000 $1,675,560.790 $1,850,573.000 $1,879,751.100