Show Job Controls
Bid Cobra

WHARTON US 59 (0089-06-092)

Items: 38

County: WHARTON
Length: N/A
Highway: US 59
District: YOAKUM
Control Number: 0089-06-092
DBE Goal: N/A
Project: STP 2023(977)HES
Guaranty: N/A
Time: 270 WORKING DAYS
Engineer's Estimate: $7,398,163.30
Date: 06/28/2023 (2 years ago)
Contract Number: N/A
Type: INSTALL RAISED MEDIAN
Mail/Deliver Bids To: N/A
RYAN SIMPER
PAUL RODRIGUEZ
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$7,398,163.30
1
$7,119,900.00
Over/Under Est: -3.76% -$278,263.30
$7,780,332.55
Over/Under Est: 5.17% $382,169.25
Amt Left: 9.28% $660,432.55
Over/Under Est: 5.35% $396,033.47
Amt Left: 9.47% $674,296.77
Delta: -0.18% -$13,864.22
$8,769,717.50
Over/Under Est: 18.54% $1,371,554.20
Amt Left: 23.17% $1,649,817.50
Delta: -12.52% -$975,520.73
$10,102,548.96
Over/Under Est: 36.55% $2,704,385.66
Amt Left: 41.89% $2,982,648.96
Delta: -15.20% -$1,332,831.46
Subcontractor Percentage Amount
MTAM CORPORATION 1.17% $83,302.83
ROADWAY SPECIALTIES, INC. 0.77% $54,823.23
QUALITY TURF FARMS, L.C. 0.66% $46,991.34
TEXAS STEEL INDUSTRIAL PLACING, LLC 0.55% $39,159.45
KASKO, LLC 0.51% $36,311.49
LONESTAR TRAFFIC SAFETY, LLC 0.27% $19,223.73
Total: 3.93% $279,812.07

Bid Items & Bid Tabulations

38 Total 0 of 38
WHARTON  |  US 59  |  YOAKUM  |  0089-06-092  |  06/28/2023  |  $7,398,163.30  |  STP 2023(977)HES  |  INSTL RAISED MEDIAN  |  270 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
WEBBER, LLC
ISI CONTRACTING, INC.
JAMES CONSTRUCTION GROUP, LLC
FNH CONSTRUCTION, LLC
ALTUS CONSTRUCTION LLC
REMOVING CONCRETE(MOW STRIP)
LF 2,563.000 $8.500 $9.000 $12.000 $6.680 $20.000 $18.630
EXCAVATION (ROADWAY)
CY 1,427.000 $20.000 $20.000 $16.500 $120.160 $20.000 $31.040
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 4,526.000 $25.000 $25.000 $54.000 $12.490 $30.000 $31.040
BLADING
HR 150.000 $100.000 $170.000 $275.000 $109.490 $150.000 $186.260
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 35,639.000 $0.200 $0.300 $2.750 $0.300 $1.000 $3.100
BROADCAST SEED (TEMP) (WARM)
SY 8,912.000 $0.200 $0.250 $1.250 $0.250 $1.000 $1.430
BROADCAST SEED (TEMP) (COOL)
SY 8,912.000 $0.200 $0.250 $1.250 $0.250 $1.000 $0.370
VEGETATIVE WATERING
MG 300.400 $14.000 $21.000 $125.000 $38.990 $50.000 $37.250
FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS)
CY 66.000 $85.000 $130.000 $200.000 $177.090 $150.000 $248.350
CONC PVMT (CONT REINF - CRCP) (8")
SY 15,379.000 $75.000 $90.000 $115.000 $150.000 $95.000 $128.380
RETROFIT RAIL (TY SSTR)
LF 2,529.340 $190.000 $100.000 $220.000 $81.120 $75.000 $178.580
MOBILIZATION
LS 1.000 $660,000.000 $706,500.000 $750,000.000 $760,000.000 $800,000.000 $993,407.500
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 18.000 $5,000.000 $19,000.000 $5,000.000 $10,602.550 $8,500.000 $18,626.390
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 400.000 $45.000 $35.000 $40.000 $35.000 $30.000 $62.090
ROCK FILTER DAMS (REMOVE)
LF 400.000 $10.000 $15.000 $23.000 $15.000 $15.000 $10.240
TEMP SEDMT CONT FENCE (INSTALL)
LF 750.000 $5.000 $3.500 $5.500 $3.500 $4.000 $3.730
TEMP SEDMT CONT FENCE (REMOVE)
LF 750.000 $2.000 $1.000 $2.000 $1.000 $2.000 $0.930
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 9,810.000 $65.000 $50.000 $72.000 $70.000 $95.000 $86.920
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 33,300.000 $10.000 $9.600 $8.000 $4.970 $20.000 $18.630
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 9,810.000 $7.500 $15.000 $11.000 $8.420 $30.000 $24.840
PERM CTB (SGL SLOPE) (TY 1) (42 )
LF 29,873.000 $95.000 $83.000 $77.000 $77.700 $90.000 $114.440
PERM CTB(SS)(42")(HEB)(RGD PVM)
LF 2,200.000 $200.000 $142.000 $185.000 $152.790 $320.000 $169.740
MTL W-BEAM GD FEN (TIM POST)
LF 575.000 $28.000 $25.300 $27.000 $27.000 $30.000 $27.010
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 3.000 $2,500.000 $2,275.000 $3,750.000 $1,881.000 $1,850.000 $2,142.030
REMOVE METAL BEAM GUARD FENCE
LF 2,943.000 $5.000 $6.000 $8.000 $3.000 $3.000 $2.790
REMOVE TERMINAL ANCHOR SECTION
EA 1.000 $200.000 $830.000 $400.000 $200.000 $500.000 $216.070
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 2.000 $350.000 $420.200 $450.000 $200.000 $500.000 $246.800
GUARDRAIL END TREATMENT (INSTALL)
EA 3.000 $3,400.000 $3,850.000 $6,000.000 $3,165.000 $3,250.000 $3,161.830
GUARDRAIL END TREATMENT (REMOVE)
EA 12.000 $300.000 $500.000 $5,050.000 $350.000 $800.000 $256.110
CRASH CUSH ATTEN (MOVE & RESET)
EA 9.000 $3,500.000 $2,000.000 $1,500.000 $1,515.000 $5,000.000 $1,629.810
CRASH CUSH ATTEN (REMOVE)
EA 6.000 $1,000.000 $1,100.000 $350.000 $1,456.000 $2,500.000 $931.320
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 8.000 $25,000.000 $25,000.000 $4,900.000 $27,600.000 $25,000.000 $25,657.850
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 3.000 $10,000.000 $9,000.000 $4,250.000 $8,800.000 $21,000.000 $8,991.900
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 26.000 $35.000 $16.000 $25.000 $20.000 $100.000 $23.280
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
EA 1,429.000 $20.000 $18.000 $25.000 $20.000 $50.000 $18.630
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 17.000 $45.000 $30.000 $40.000 $40.000 $100.000 $31.030
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $15,000.000 $17,500.000 $200.000 $10,510.970 $16,500.000 $9,313.200
TMA (STATIONARY)
DAY 100.000 $550.000 $350.000 $500.000 $300.970 $250.000 $310.440
Totals: $7,398,163.300 $7,119,900.000 $7,780,332.550 $7,794,196.777 $8,769,717.500 $10,102,548.967