WEBB SH 255 (3586-02-007)

Items: 118

County: WEBB
Length: 7.4150 MILES
Highway: SH 255
District: LAREDO
Control Number: 3586-02-007
DBE Goal: 3.0%
Project: F 2025(886)
Guaranty: $100,000.00
Time: 479 WORKING DAYS
Engineer's Estimate: $30,716,266.51
Date: 07/02/2025 (11 months ago)
Contract Number: 7253203
Type: REHABILITATE EXISTING ROADWAY
Project ID: A00180424
Contract Type: Federal
Project Description: REHABILITATION OF EXISTING ROADWAY TREAT FLEXBASE, HMA TY-B, SMA-C, MBGF, & PAVEMENT MARKING, & UPGRADE DRAINAGE STRUCTURES
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JOSE VARGAS
MISAEL AGUILAR
ANGEL MARTINEZ
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$30,716,266.51
$26,042,349.50
Over/Under Est: -15.22% -$4,673,917.01
Over/Under Est: -9.84% -$3,022,674.36
Amt Left: 6.34% $1,651,242.65
Over/Under Est: -5.62% -$1,727,459.26
Amt Left: 11.31% $2,946,457.75
Delta: -4.68% -$1,295,215.10
Subcontractor Percentage Amount
ACEE CONSTRUCTION LLC. 16.98% $4,455,815.25
HIGHWAY BARRICADES AND SERVICES, LLC 1.10% $288,657.05
SOIL TECH ADVANCE INC. 0.65% $170,570.08
DEPENDABLE FENCE 0.49% $128,583.60
D&G ENERGY CORPORATION 0.43% $112,838.67
PENHALL COMPANY 0.41% $107,590.36
MURRAY CONSTRUCTION 0.39% $102,342.05
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. 0.35% $91,845.43
4E TREE WORX LLC 0.21% $55,107.26
Total: 21.01% $5,513,349.75

Bid Items & Bid Tabulations

118 Total 0 of 118
WEBB  |  SH 255  |  LAREDO  |  3586-02-007  |  07/02/2025  |  $30,716,266.51  |  F 2025(886)  |  REHAB EXIST ROADWAY  |  479 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CK NEWBERRY, LLC
ANDERSON COLUMBIA CO., INC.
TEXAS MATERIALS GROUP, INC.
PREPARING ROW
STA 96.000 $2,500.000 $500.000 $1,000.000 $1,000.000
REMOV CONC (MOWSTRIP)
SY 20.000 $27.500 $50.000 $70.000 $42.000
REMOV CONC (CURB & GUTTER)
LF 5,880.000 $14.000 $7.000 $4.000 $8.300
RMV (20") TRT/UNTRT BASE & ASPH PAV
CY 2,481.000 $55.000 $20.000 $16.000 $28.000
EXCAV (ROADWAY)
CY 8,982.400 $17.000 $10.000 $20.000 $20.550
EMBANK (FNL)(OC)(TY C)
CY 10,026.500 $23.330 $17.000 $14.000 $27.000
BACKFILL (TY B)
STA 96.000 $115.000 $500.000 $220.000 $150.000
DRILL SEED (PERM_RURAL_CLAY)
AC 82.300 $567.500 $550.000 $1,400.000 $1,200.000
DRILL SEED (TEMP_WARM)
AC 82.300 $567.500 $550.000 $500.000 $400.000
FL BS (RDWY DEL)(TY E GR 1-2)(FNL POS)
CY 3,889.000 $120.000 $70.000 $64.000 $72.000
CEMENT
TON 130.000 $293.000 $200.000 $265.000 $230.000
CEMENT TRT (NEW BASE)(6")
SY 24,414.000 $6.500 $1.500 $3.500 $2.450
CEMENT
TON 1,392.000 $300.000 $200.000 $262.000 $230.000
ASPHALT BINDER (PG 64-22)
TON 3,479.000 $600.000 $550.000 $620.000 $689.000
FOAM ASPH TRT (EXIST MATL) (12")
SY 241,153.000 $6.500 $3.000 $5.000 $5.850
PRIME COAT (RC-250)
GAL 50,440.000 $6.000 $4.250 $6.000 $4.550
AGGR (TY-PB, GR-5)(SAC-B)
CY 1,802.000 $110.000 $115.000 $180.000 $189.000
D-GR HMA TY-B SAC-B PG70-22
TON 71,079.000 $120.000 $105.000 $104.000 $110.000
STONE-MTRX-ASPH SMA-C SAC-A PG76-22
TON 35,344.000 $150.000 $135.000 $168.000 $169.000
PLANE ASPH CONC PAV(4")
SY 233,897.000 $4.500 $1.250 $2.400 $2.150
PLAN ASPH CONC PAV (4"-7.5")
SY 3,912.000 $5.000 $4.500 $5.000 $6.300
CONC PVMT (CRCP) (12")
SY 24,735.000 $110.000 $125.000 $120.000 $116.000
FLOWABLE BACKFILL
CY 209.200 $265.000 $350.000 $150.000 $145.000
TEMPORARY SPL SHORING
SF 4,644.000 $25.000 $20.000 $14.000 $13.000
DRILL SHAFT (36 IN)
LF 52.800 $482.000 $425.000 $440.000 $400.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 10.000 $358.000 $300.000 $270.000 $300.000
RIPRAP (CONC)(4 IN)
CY 412.000 $707.000 $500.000 $520.000 $485.000
RIPRAP (CONC)(5 IN)
CY 141.000 $650.000 $550.000 $620.000 $515.000
RIPRAP (MOW STRIP)(4 IN)
CY 92.000 $800.000 $700.000 $680.000 $495.000
RC PIPE (CL III)(18 IN)
LF 100.000 $117.500 $100.000 $110.000 $100.000
RC PIPE (CL III)(24 IN)
LF 100.000 $102.000 $125.000 $144.000 $132.000
INLET (COMPL)(POD)(SFG)(3FTX3FT)
EA 6.000 $5,500.000 $7,000.000 $4,000.000 $3,750.000
SET (TY I)(S= 8 FT)(HW= 5 FT)(4:1)(C)
EA 16.000 $12,000.000 $12,000.000 $15,000.000 $14,750.000
SET (TY I)(S= 8 FT)(HW= 6 FT)(4:1)(C)
EA 26.000 $16,000.000 $8,000.000 $18,000.000 $16,750.000
SET (TY II) (18 IN) (RCP) (4: 1) (C)
EA 1.000 $1,155.000 $4,000.000 $1,500.000 $1,381.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 1.000 $2,560.000 $5,000.000 $1,600.000 $1,392.000
ADJUSTING INLETS
EA 6.000 $500.000 $2,500.000 $1,000.000 $1,000.000
ADJUSTING MANHOLES (CAP)
EA 2.000 $3,000.000 $3,000.000 $2,500.000 $2,500.000
CLEAN EXIST CULVERTS
EA 10.000 $1,500.000 $3,000.000 $4,000.000 $3,500.000
REMOV STR (INLET)
EA 12.000 $1,095.000 $1,500.000 $2,000.000 $1,850.000
REMOV STR (WINGWALL)
EA 13.000 $3,500.000 $2,000.000 $2,500.000 $2,250.000
REMOV STR (PIPE)
LF 20.000 $30.000 $50.000 $46.000 $43.000
MOBILIZATION
LS 1.000 $2,674,908.400 $2,500,000.000 $1,380,000.000 $2,100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 24.000 $4,000.000 $10,000.000 $2,500.000 $8,200.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $11,000.000 $25,000.000 $34,000.000 $20,000.000
TMA (STATIONARY)
DAY 453.000 $270.000 $100.000 $280.000 $165.000
TMA (MOBILE OPERATION)
HR 136.000 $205.000 $100.000 $70.000 $60.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 873.000 $50.000 $120.000 $160.000 $150.000
ROCK FILTER DAMS (REMOVE)
LF 873.000 $25.000 $22.000 $16.000 $15.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 156.000 $20.000 $20.000 $50.000 $45.000
CONSTRUCTION EXITS (REMOVE)
SY 156.000 $20.000 $10.000 $17.000 $15.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 56.000 $100.000 $75.000 $170.000 $146.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,242.000 $3.000 $7.000 $5.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,242.000 $3.000 $2.000 $2.000 $1.500
ONE-WAY TRAF CONT (PILOT CAR)
HR 944.000 $105.000 $150.000 $180.000 $153.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 7.000 $6,504.000 $3,500.000 $7,000.000 $5,100.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 9,120.000 $60.000 $35.000 $28.000 $37.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 5,160.000 $15.000 $18.000 $26.000 $24.500
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 9,120.000 $12.500 $28.000 $17.000 $24.000
CONC CURB & GUTTER (TY II)
LF 3,787.000 $40.000 $35.000 $46.000 $42.500
DRIVEWAYS (ACP)
SY 1,383.000 $66.000 $80.000 $115.000 $108.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 114,189.000 $0.150 $0.100 $0.150 $0.090
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 13,200.000 $0.450 $0.250 $0.150 $0.170
MTL W-BEAM GD FEN (TIM POST)
LF 925.000 $30.000 $24.000 $25.000 $26.500
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 16.000 $2,500.000 $1,900.000 $3,160.000 $2,200.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 3.000 $1,750.000 $1,400.000 $1,500.000 $1,250.000
REMOVE METAL BEAM GUARD FENCE
LF 850.000 $3.500 $3.000 $3.300 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 3.000 $250.000 $275.000 $300.000 $220.000
GUARDRAIL END TREATMENT (INSTALL)
EA 19.000 $2,650.000 $3,300.000 $3,610.000 $3,050.000
GUARDRAIL END TREATMENT (REMOVE)
EA 19.000 $325.000 $300.000 $320.000 $335.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 60.000 $1,400.000 $700.000 $1,020.000 $1,100.000
CRASH CUSH ATTEN (REMOVE)
EA 6.000 $1,000.000 $600.000 $820.000 $700.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 6.000 $14,000.000 $10,000.000 $7,080.000 $8,300.000
RELOCATE RD IL ASM (TRANS-BASE)
EA 1.000 $3,085.000 $4,500.000 $4,940.000 $4,500.000
CONDT (PVC) (SCH 40) (2")
LF 357.000 $22.000 $21.000 $20.000 $21.000
CONDT (PVC) (SCH 80) (2") (BORE)
LF 245.000 $25.000 $50.000 $6.500 $50.000
ELEC CONDR (NO.6) BARE
LF 122.000 $2.630 $2.000 $2.200 $1.850
ELEC CONDR (NO.6) INSULATED
LF 244.000 $2.630 $2.250 $3.000 $2.200
TRAY CABLE (3 CONDR) (12 AWG)
LF 1,040.000 $5.750 $2.750 $3.300 $2.650
GROUND BOX TY A (122311)W/APRON
EA 4.000 $2,005.000 $1,400.000 $1,400.000 $1,300.000
GROUND BOX TY C (162911)W/APRON
EA 3.000 $2,166.000 $1,600.000 $1,460.000 $1,500.000
REMOVE GROUND BOX
EA 3.000 $692.000 $450.000 $550.000 $450.000
RELOCATE ELECTRICAL SERVICES
EA 1.000 $3,800.000 $3,000.000 $2,760.000 $2,800.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 110.000 $600.000 $700.000 $845.000 $675.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 15.000 $950.000 $775.000 $1,030.000 $775.000
REMOVE SM RD SN SUP&AM
EA 118.000 $118.000 $100.000 $98.000 $100.000
REMOVE OVERHD SIGN SUP
EA 2.000 $9,148.000 $7,500.000 $8,170.000 $13,000.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 43.000 $22.000 $32.000 $49.000 $32.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 24.000 $45.000 $75.000 $98.000 $75.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 43.000 $15.500 $15.000 $27.000 $15.000
WK ZN PAV MRK REMOV (TRAF BTN) TY W
LF 8,448.000 $1.200 $1.000 $1.000 $0.800
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 5,606.000 $0.500 $1.000 $2.000 $1.600
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 4,138.000 $2.250 $1.000 $2.000 $1.600
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 1,382.000 $2.000 $1.000 $1.000 $0.960
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 2,692.000 $2.500 $1.000 $1.000 $0.960
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 144.000 $9.500 $16.000 $18.000 $16.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 14.000 $198.000 $175.000 $190.000 $175.000
REFL PAV MRK TY I(W)(UTURN ARW)(100MIL)
EA 6.000 $215.000 $325.000 $350.000 $325.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 20.000 $291.000 $250.000 $270.000 $250.000
PAVEMENT SLER 6"
LF 204,614.000 $0.750 $0.250 $0.300 $0.260
PAVEMENT SLER 24"
LF 144.000 $1.650 $1.100 $1.200 $1.100
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 9,241.000 $0.650 $0.900 $1.000 $0.880
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 84,727.000 $0.500 $0.650 $0.700 $0.630
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 83,580.000 $0.500 $0.650 $0.700 $0.630
REFL PAV MRKR TY I-C
EA 762.000 $5.500 $7.500 $8.000 $7.500
REFL PAV MRKR TY II-A-A
EA 1,630.000 $4.700 $5.500 $6.000 $5.500
ELIM EXT PM & MRKS (4")
LF 12,444.000 $0.600 $1.000 $0.300 $0.250
ELIM EXT PM & MRKS (ARROW)
EA 5.000 $92.000 $35.000 $38.000 $35.000
ELIM EXT PM & MRKS (WORD)
EA 4.000 $150.000 $35.000 $38.000 $35.000
REMOVING TRAFFIC SIGNALS
EA 1.000 $5,200.000 $6,000.000 $7,030.000 $7,200.000
INS HY TRF SIG (DPT SUP CNT & CAB)(FLA)
EA 1.000 $8,920.000 $12,500.000 $3,600.000 $12,600.000
TRF SIG CBL (TY A)(12 AWG)(4 CONDR)
LF 534.000 $2.670 $2.500 $3.000 $2.450
TREE TRIMMING / BRUSH REMOVAL
MI 1.140 $14,000.000 $25,000.000 $22,000.000 $20,176.000
BONDING COURSE
GAL 49,175.000 $5.000 $4.000 $4.700 $0.100
CONTINUOUS GRINDING-CONCRETE PAVEMENT
SY 18,967.000 $12.000 $5.500 $6.500 $8.830
ITS RADIO(SNGL)(5 GHZ)-I-U
EA 1.000 $10,800.000 $6,000.000 $5,400.000 $5,800.000
REMOVE ITS RADIO
EA 2.000 $3,127.000 $600.000 $1,050.000 $580.000
TMSP RADAR SPEED CONTROL MONITOR
EA 2.000 $9,500.000 $5,000.000 $18,000.000 $9,200.000
Totals: $30,716,266.505 $26,042,349.500 $27,693,592.150 $28,988,807.250
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $50,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,332,654.20
Total: $1,383,654.20