WEBB CR (0922-33-194)
Items: 40
County: WEBB
Length: N/A
Highway: CR
District: LAREDO
Control Number: 0922-33-194
DBE Goal: N/A
Project: BR 2022(261)
Guaranty: N/A
Time: 78 WORKING DAYS
Engineer's Estimate: $882,559.00
Date: 01/05/2023 (3 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
ANTONIO REYNA1
ALBERTO CHAVEZ
Bidders (3)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$882,559.00 | |||
| $1,492,184.00 |
69.07%
$609,625.00
|
|||
| $1,558,207.00 |
76.56%
$675,648.00
|
4.42%
$66,023.00
|
||
| $1,628,308.85 |
84.5%
$745,749.85
|
9.12%
$136,124.85
|
-4.50%
-$70,101.85
|
E
Engineer's Estimate
$882,559.00
1
Awarded
$1,492,184.00
Over/Under Est:
69.07%
$609,625.00
$1,558,207.00
Over/Under Est:
76.56%
$675,648.00
Amt Left:
4.42%
$66,023.00
$1,628,308.85
Over/Under Est:
84.5%
$745,749.85
Amt Left:
9.12%
$136,124.85
Delta:
-4.50%
-$70,101.85