WEBB VARIOUS (0922-00-078)

Items: 48

County: WEBB
Length: 0.0000 MILES
Highway: VARIOUS
District: LAREDO
Control Number: 0922-00-078
DBE Goal: 0.0%
Project: C 922-00-78
Guaranty: $62,000.00
Time: 400 WORKING DAYS
Engineer's Estimate: $3,082,511.60
Date: 03/04/2025 (1 year ago)
Contract Number: 3253022
Type: REMOVE/REPLACE BRIDGE RAIL
Project ID: A00196689
Project Description: DISTRICTWIDE REMOVAL AND REPLACEMENT OF EXISTING BRIDGE RAIL AT VAL VERDE, MAVERICK, ZAVALA.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JOSE VARGAS
GERARDO M GONZALEZ
ANGEL MARTINEZ
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$3,082,511.60
$3,111,940.00
Over/Under Est: 0.95% $29,428.40
$3,147,250.00
Over/Under Est: 2.1% $64,738.40
Amt Left: 1.13% $35,310.00
$3,298,801.76
Over/Under Est: 7.02% $216,290.16
Amt Left: 6% $186,861.76
Delta: -4.82% -$151,551.76
$3,323,094.29
Over/Under Est: 7.8% $240,582.69
Amt Left: 6.79% $211,154.29
Delta: -0.74% -$24,292.53
$4,074,753.00
Over/Under Est: 32.19% $992,241.40
Amt Left: 30.94% $962,813.00
Delta: -22.62% -$751,658.71
Over/Under Est: 75.95% $2,341,048.40
Amt Left: 74.28% $2,311,620.00
Delta: -33.10% -$1,348,807.00
Subcontractor Percentage Amount
FLASHER EQUIPMENT COMPANY 0.00% $0.00
HIGHWAY BARRICADES AND SERVICES, LLC 0.00% $0.00
RPV CONSTRUCTION, LLC 0.00% $0.00
USA AMTECH, INC. 0.00% $0.00
Total: 0.00% $0.00

Bid Items & Bid Tabulations

48 Total 0 of 48
WEBB  |  VARIOUS  |  LAREDO  |  0922-00-078  |  03/04/2025  |  $3,082,511.60  |  C 922-00-78  |  REMOVE/REPLACE BRIDGE RAIL  |  400 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DELGADO'S CONTRACTORS, LLC
ICOS MANAGEMENT, LLC
3LW CIVIL LLC
RELMCO, INC.
STX CIVIL
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
REMOV CONC (MOWSTRIP)
LF 3,020.000 $15.000 $6.000 $15.000 $17.240 $25.000 $22.000 $50.000
EMBANK (FNL)(OC)(TY A)
CY 72.000 $100.000 $100.000 $120.000 $331.970 $200.000 $75.000 $300.000
BACKFILL (TY B)
STA 125.000 $300.000 $125.000 $80.000 $373.520 $1,500.000 $263.000 $500.000
SPEC EXCAV WORK (BACKHOE)
HR 28.000 $125.000 $125.000 $500.000 $78.310 $100.000 $196.000 $200.000
RIPRAP (CONC)(4 IN)
CY 72.000 $500.000 $625.000 $800.000 $699.740 $525.000 $714.000 $1,700.000
RIPRAP (MOW STRIP)(4 IN)
CY 466.000 $600.000 $625.000 $700.000 $798.190 $525.000 $777.000 $1,300.000
RETROFIT RAIL (TY T402)
LF 3,062.000 $220.000 $180.000 $260.000 $166.810 $150.000 $281.000 $350.000
RETROFIT RAIL (TY T631)
LF 3,950.000 $100.000 $115.000 $160.000 $98.950 $104.500 $139.000 $225.000
RETROFIT RAIL (ADD HSS)
LF 170.000 $100.000 $125.000 $500.000 $159.770 $187.000 $139.000 $300.000
CLEAN EXIST CULVERTS
EA 9.000 $2,500.000 $4,000.000 $7,000.000 $16,662.940 $3,500.000 $4,500.000 $5,000.000
MOBILIZATION
LS 1.000 $227,075.600 $155,000.000 $47,000.000 $311,943.910 $300,000.000 $336,000.000 $500,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 20.000 $5,000.000 $5,000.000 $1.000 $2,101.670 $6,500.000 $5,500.000 $2,500.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $9,500.000 $10,000.000 $8,453.190 $17,500.000 $12,500.000 $20,000.000
TMA (STATIONARY)
DAY 388.000 $150.000 $300.000 $1.000 $183.500 $250.000 $260.000 $325.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 273.000 $50.000 $75.000 $10.000 $46.800 $50.000 $110.000 $125.000
ROCK FILTER DAMS (REMOVE)
LF 273.000 $15.000 $7.000 $5.000 $21.600 $25.000 $25.000 $35.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 156.000 $15.000 $35.000 $20.000 $33.600 $30.000 $45.000 $55.000
CONSTRUCTION EXITS (REMOVE)
SY 156.000 $10.000 $7.000 $5.000 $18.000 $15.000 $20.000 $25.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 4.000 $100.000 $150.000 $600.000 $97.880 $100.000 $116.000 $200.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 160.000 $3.000 $7.000 $5.000 $5.700 $6.000 $8.000 $7.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 160.000 $1.000 $1.000 $2.000 $2.400 $4.000 $2.000 $5.000
ONE-WAY TRAF CONT (FLAGGER CONT)
HR 848.000 $100.000 $75.000 $1.000 $113.720 $100.000 $132.000 $35.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 6.000 $5,000.000 $6,000.000 $10,000.000 $4,200.000 $5,500.000 $7,630.000 $6,000.000
PTB (FUR&INST)(SSCB OR CSB)(TY1)OR(STL)
LF 1,170.000 $60.000 $90.000 $90.000 $38.260 $60.000 $75.000 $105.000
PTB (MOVE)(SSCB OR CSB)(TY1)OR(STL)
LF 5,670.000 $15.000 $12.000 $25.000 $8.620 $30.000 $25.000 $25.000
PTB (REMOVE)(SSCB OR CSB)(TY1)OR(STL)
LF 1,170.000 $20.000 $17.000 $25.000 $25.460 $30.000 $30.000 $40.000
MTL W-BEAM GD FEN (TIM POST)
LF 9,975.000 $28.000 $27.500 $19.000 $28.640 $30.800 $33.000 $33.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 12.000 $2,500.000 $2,500.000 $3,800.000 $3,242.160 $2,420.000 $3,200.000 $5,500.000
TRANSITION ADJUSTMENT
EA 1.000 $500.000 $1,250.000 $5,000.000 $2,184.650 $1,210.000 $128.000 $1,500.000
REMOVE METAL BEAM GUARD FENCE
LF 7,625.000 $3.000 $2.500 $2.000 $9.180 $2.750 $4.000 $5.000
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $200.000 $250.000 $500.000 $1,143.940 $275.000 $422.000 $300.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 12.000 $250.000 $325.000 $500.000 $762.630 $275.000 $469.000 $300.000
RM MTL BM GD FEN TRANS (T101)
EA 33.000 $200.000 $250.000 $500.000 $1,109.280 $275.000 $426.000 $300.000
GUARDRAIL END TREATMENT (INSTALL)
EA 47.000 $3,000.000 $3,150.000 $3,500.000 $3,791.800 $3,520.000 $3,500.000 $4,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 43.000 $200.000 $250.000 $500.000 $744.890 $275.000 $523.000 $300.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 42.000 $1,500.000 $2,000.000 $2,000.000 $1,089.470 $800.000 $2,272.000 $3,500.000
CRASH CUSH ATTEN (REMOVE)
EA 6.000 $1,000.000 $2,000.000 $2,000.000 $1,162.630 $600.000 $1,136.000 $1,500.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 6.000 $15,000.000 $9,000.000 $10,000.000 $8,417.940 $9,000.000 $11,135.000 $13,000.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 267.000 $50.000 $40.000 $40.000 $60.410 $40.700 $45.000 $65.000
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
EA 56.000 $100.000 $100.000 $100.000 $71.980 $40.700 $127.000 $25.000
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 16,920.000 $2.000 $3.000 $0.500 $1.800 $1.650 $2.000 $3.500
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 288.000 $10.000 $20.000 $0.500 $24.000 $22.000 $28.000 $25.000
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 32,080.000 $2.000 $3.000 $0.500 $1.100 $1.210 $2.000 $3.250
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,692.000 $2.000 $2.000 $0.500 $4.660 $5.000 $3.000 $0.500
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 3,208.000 $2.000 $2.000 $0.500 $4.630 $5.000 $3.000 $0.500
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 8,020.000 $1.000 $3.000 $0.500 $3.000 $3.300 $4.000 $3.250
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 32,080.000 $1.500 $3.000 $0.500 $1.280 $1.408 $2.000 $3.250
REFL PAV MRKR TY II-A-A
EA 802.000 $8.000 $11.000 $10.000 $20.000 $22.000 $28.000 $20.000
Totals: $3,082,511.600 $3,111,940.000 $3,147,250.000 $3,298,801.760 $3,323,094.290 $4,074,753.000 $5,423,560.000
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $1,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $50,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $100,000.00
Total: $151,000.00