WASHINGTON US0290 (6477-41-001)

Items: 22

County: WASHINGTON
Length: 0.0100 MILES
Highway: US0290
District: BRYAN
Control Number: 6477-41-001
DBE Goal: N/A
Project: RMC - A00213021
Guaranty: $29,000.00
Time: 25 WORKING DAYS
Engineer's Estimate: $1,454,685.33
Date: 03/05/2025 (1 year ago)
Contract Number: 3254209
Type: MILL AND INLAY
Project ID: A00213021
Project Description: MILL AND INLAY FOR US 290 MAIN LANES EAST OF BRENHAM IN WASHINGTON COUNTY.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JAMES KREAMER
RENE PEQUENO
MICHAEL ESTILLETTE
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (9)
E
Engineer's Estimate
$1,454,685.33
Over/Under Est: -10.67% -$155,279.13
Over/Under Est: -6.32% -$91,888.33
Amt Left: 4.88% $63,390.80
Over/Under Est: -5.9% -$85,787.33
Amt Left: 5.35% $69,491.80
Delta: -0.45% -$6,101.00
Over/Under Est: -2.91% -$42,326.08
Amt Left: 8.69% $112,953.05
Delta: -3.17% -$43,461.25
Over/Under Est: 11.05% $160,742.67
Amt Left: 24.32% $316,021.80
Delta: -14.38% -$203,068.75
Over/Under Est: 15.5% $225,416.17
Amt Left: 29.3% $380,695.30
Delta: -4.00% -$64,673.50
Over/Under Est: 23.18% $337,148.67
Amt Left: 37.9% $492,427.80
Delta: -6.65% -$111,732.50
Over/Under Est: 24.48% $356,095.87
Amt Left: 39.35% $511,375.00
Delta: -1.06% -$18,947.20
$1,898,545.75
Over/Under Est: 30.51% $443,860.42
Amt Left: 46.11% $599,139.55
Delta: -4.85% -$87,764.55
Subcontractor Percentage Amount
PROFESSIONAL TRAFFIC CONTROL LLC 0.00% $0.00
TRAFFIC SIGNS & LINES, LLC 0.00% $0.00
Total: 0.00% $0.00

Bid Items & Bid Tabulations

22 Total 0 of 22
WASHINGTON  |  US0290  |  BRYAN  |  6477-41-001  |  03/05/2025  |  $1,454,685.33  |  RMC - A00213021  |  MILL AND INLAY  |  25 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
BIG CREEK CONSTRUCTION, LTD.
ELITE KINGS CONSTRUCTION, LLC
KNIFE RIVER CORPORATION - SOUTH
TEXAS MATERIALS GROUP, INC.
ENVIRONMENTAL ALLIES, INC.
FORDE CONSTRUCTION COMPANY, INC.
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC
BRAZOS PAVING, INC.
BACKFILL (TY A OR B)
STA 73.000 $200.000 $400.000 $350.000 $100.000 $278.000 $400.000 $600.000 $500.000 $242.000 $765.000
PFC-C PG76-22 SAC-A
TON 3,887.000 $150.000 $174.000 $165.000 $150.000 $172.850 $182.000 $206.000 $208.000 $178.000 $203.300
TACK COAT
GAL 6,688.000 $6.260 $3.400 $3.500 $3.000 $4.250 $4.000 $5.500 $4.000 $3.500 $7.450
TOM-C PG76-22 SAC-B
TON 2,759.000 $144.350 $150.000 $145.000 $130.000 $161.900 $232.000 $165.500 $200.000 $212.000 $185.750
TACK COAT
GAL 6,688.000 $6.260 $3.400 $3.500 $3.000 $4.250 $4.000 $5.500 $4.000 $3.500 $7.450
PLANE & TEXT ASPH CONC PAV(0" TO 2")
SY 66,880.000 $3.000 $0.500 $1.500 $3.000 $0.940 $1.000 $2.250 $2.650 $3.040 $3.700
MOBILIZATION
LS 1.000 $55,115.720 $45,000.000 $65,000.000 $10,000.000 $56,980.000 $58,000.000 $75,000.000 $50,000.000 $165,000.000 $86,700.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $4,000.000 $3,000.000 $5,000.000 $12,500.000 $5,750.000 $1,100.000 $2,500.000 $24,000.000 $23,400.000 $6,480.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 28.000 $100.000 $75.000 $200.000 $350.000 $280.000 $95.000 $110.000 $170.000 $56.000 $590.000
TMA (STATIONARY)
DAY 12.000 $200.000 $125.000 $250.000 $325.000 $580.000 $200.000 $375.000 $200.000 $336.000 $650.000
TMA (MOBILE OPERATION)
DAY 6.000 $200.000 $125.000 $500.000 $450.000 $940.000 $400.000 $500.000 $200.000 $336.000 $1,000.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 27,100.000 $1.050 $0.100 $0.550 $1.500 $0.320 $0.100 $0.350 $0.300 $0.130 $0.300
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 3,960.000 $0.420 $0.500 $0.400 $2.300 $0.420 $0.450 $0.450 $0.400 $0.500 $0.520
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 15,840.000 $0.650 $0.390 $0.400 $1.000 $0.420 $0.450 $0.400 $0.350 $0.390 $0.520
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 720.000 $0.620 $0.800 $1.000 $1.200 $1.100 $0.900 $0.750 $0.450 $0.800 $1.040
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 15,840.000 $0.750 $0.390 $0.400 $1.200 $0.420 $0.450 $0.450 $0.350 $0.390 $0.520
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,980.000 $1.000 $1.450 $1.500 $1.000 $2.200 $0.850 $2.000 $2.700 $0.450 $1.150
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 720.000 $1.650 $1.450 $1.000 $1.000 $1.420 $1.150 $1.550 $1.450 $0.850 $1.300
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 3,960.000 $1.000 $0.700 $0.750 $1.000 $0.920 $0.750 $0.950 $0.850 $1.450 $0.840
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 15,840.000 $1.310 $0.620 $0.750 $1.000 $0.920 $0.750 $0.850 $0.750 $0.700 $0.840
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 15,840.000 $1.430 $0.620 $0.750 $1.000 $0.920 $0.750 $0.850 $0.750 $0.620 $0.840
REFL PAV MRKR TY II-C-R
EA 300.000 $5.380 $6.000 $6.000 $13.000 $7.600 $6.750 $11.000 $11.000 $0.620 $7.800
Totals: $1,454,685.330 $1,299,406.200 $1,362,797.000 $1,368,898.000 $1,412,359.250 $1,615,428.000 $1,680,101.500 $1,791,834.000 $1,810,781.200 $1,898,545.750