WASHINGTON US0290 (6323-02-001)

Items: 11

County: WASHINGTON
Length: N/A
Highway: US0290
District: BRYAN
Control Number: 6323-02-001
DBE Goal: N/A
Project: RMC - 632302001
Guaranty: N/A
Time: 731 CALENDAR DAYS
Engineer's Estimate: $2,495,037.00
Date: 11/02/2017 (8 years ago)
Contract Number: N/A
Type: FLAGGING AND TRAFFIC CONTROL
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$2,495,037.00
$1,969,791.50
Over/Under Est: -21.05% -$525,245.50
$2,014,750.00
Over/Under Est: -19.25% -$480,287.00
Amt Left: 2.28% $44,958.50
Over/Under Est: -16.94% -$422,569.00
Amt Left: 5.21% $102,676.50
Delta: -2.86% -$57,718.00
Over/Under Est: 27.64% $689,713.00
Amt Left: 61.68% $1,214,958.50
Delta: -53.67% -$1,112,282.00

Bid Items & Bid Tabulations

11 Total 0 of 11
WASHINGTON  |  US0290  |  BRYAN  |  6323-02-001  |  11/02/2017  |  $2,495,037.00  |  RMC - 632302001  |  FLAGGING AND TRAF CONTROL  |  731 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ALTUS TRAFFIC MANAGEMENT LLC
NIXON ENGINEERING
AREA WIDE PROTECTIVE, INC.
TOTAL HIGHWAY MAINTENANCE, LLC
MOBILIZATION
LS 1.000 $117,537.000 $12,820.000 $200,000.000 $32,632.000 $309,000.000
TMA (MOBILE OPERATION)
HR 3,000.000 $85.000 $74.550 $60.000 $73.750 $80.000
LANE CLOSURE (MAINTENANCE) (TY 1)
HR 9,000.000 $155.000 $134.940 $110.000 $144.100 $185.000
LANE CLOSURE (MAINTENANCE) (TY 2)
HR 500.000 $160.000 $121.540 $35.000 $144.170 $175.000
LANE CLOSURE (MAINTENANCE) (TY 3)
HR 500.000 $170.000 $145.920 $100.000 $129.370 $200.000
LANE CLOSURE (MAINTENANCE) (TY 4)
HR 250.000 $170.000 $145.920 $15.000 $129.730 $325.000
LANE CLOSURE (MAINTENANCE) (TY 5)
HR 150.000 $225.000 $146.230 $30.000 $109.890 $325.000
LANE CLOSURE (MAINTENANCE) (TY 6)
HR 50.000 $225.000 $186.340 $20.000 $125.000 $325.000
LANE CLOSURE (SETUP AND REMOV)(TY 21)
HR 4,000.000 $20.000 $5.000 $25.000 $5.850 $13.000
LANE CLOSURE (SETUP AND REMOV)(TY 22)
HR 1,000.000 $35.000 $27.040 $18.000 $27.620 $45.000
LANE CLOSURE (SETUP AND REMOV)(TY 23)
HR 9,000.000 $40.000 $30.040 $50.000 $30.970 $60.000
Totals: $2,495,037.000 $1,969,791.500 $2,014,750.000 $2,072,468.000 $3,184,750.000