WALLER FM 362 (0523-02-051)
Items: 79
County: WALLER
Length: N/A
Highway: FM 362
District: HOUSTON
Control Number: 0523-02-051
DBE Goal: 0.0%
Project: C 523-2-51
Guaranty: N/A
Time: 76 WORKING DAYS
Engineer's Estimate: $4,339,194.89
Date: 01/05/2024 (2 years ago)
Contract Number: N/A
Type: BASE REPAIR, 1.5" PLANING, 1.5" ACP OVERLAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$4,339,194.89 | |||
| $4,087,471.73 |
-5.8%
-$251,723.16
|
|||
| $4,110,723.87 |
-5.27%
-$228,471.02
|
0.57%
$23,252.14
|
||
| $4,168,872.92 |
-3.93%
-$170,321.97
|
1.99%
$81,401.19
|
-1.41%
-$58,149.05
|
|
| $4,210,289.71 |
-2.97%
-$128,905.18
|
3%
$122,817.98
|
-0.99%
-$41,416.79
|
|
| $4,983,973.59 |
14.86%
$644,778.70
|
21.93%
$896,501.86
|
-18.38%
-$773,683.88
|
E
Engineer's Estimate
$4,339,194.89
1
Awarded
$4,087,471.73
Over/Under Est:
-5.8%
-$251,723.16
$4,110,723.87
Over/Under Est:
-5.27%
-$228,471.02
Amt Left:
0.57%
$23,252.14
$4,168,872.92
Over/Under Est:
-3.93%
-$170,321.97
Amt Left:
1.99%
$81,401.19
Delta:
-1.41%
-$58,149.05
$4,210,289.71
Over/Under Est:
-2.97%
-$128,905.18
Amt Left:
3%
$122,817.98
Delta:
-0.99%
-$41,416.79
$4,983,973.59
Over/Under Est:
14.86%
$644,778.70
Amt Left:
21.93%
$896,501.86
Delta:
-18.38%
-$773,683.88
| Subcontractor | Percentage | Amount |
|---|---|---|
| TRAFFIC SIGNS & LINES, LLC | 7.69% | $331,437.25 |
| BATTERSON, LLP | 3.78% | $162,917.14 |
| CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. | 2.71% | $116,800.38 |
| TRAFFIC SYSTEMS CONSTRUCTION, INC. | 1.34% | $57,753.70 |
| INTERSTATE BARRICADES & MARKINGS, INC. | 0.35% | $15,084.92 |
| PROFESSIONAL TRAFFIC CONTROL LLC | 0.32% | $13,791.93 |
| Total: | 16.19% | $697,785.32 |
Bid Items & Bid Tabulations
79
Total
0 of 79