WALLER US 290 (0114-11-079)

Items: 27

County: WALLER
Length: N/A
Highway: US 290
District: HOUSTON
Control Number: 0114-11-079
DBE Goal: N/A
Project: F 1702(164)
Guaranty: N/A
Time: 51 WORKING DAYS
Engineer's Estimate: $1,034,394.25
Date: 06/01/2022 (4 years ago)
Contract Number: N/A
Type: EMERGENCY RELIEF
Mail/Deliver Bids To: N/A
CARLOS ZEPEDA
DANIEL DVORAK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (2)
E
Engineer's Estimate
$1,034,394.25
$1,227,770.00
Over/Under Est: 18.69% $193,375.75
Over/Under Est: 102.27% $1,057,885.75
Amt Left: 70.41% $864,510.00

Bid Items & Bid Tabulations

27 Total 0 of 27
WALLER  |  US 290  |  HOUSTON  |  0114-11-079  |  06/01/2022  |  $1,034,394.25  |  F 1702(164)  |  EMERGENCY RELIEF  |  51 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
EARTH BUILDERS, L.P.
FORDE CONSTRUCTION COMPANY, INC.
PREPARING ROW
AC 0.300 $10,000.000 $200,000.000 $350,000.000
REMOVING CONC (RIPRAP)
SY 38.000 $10.000 $20.000 $120.000
EXCAVATION (CHANNEL)
CY 370.000 $10.000 $25.000 $93.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 1,270.000 $20.000 $35.000 $73.000
BACKFILL (TY A OR B)
CY 7.000 $20.000 $50.000 $250.000
BLOCK SODDING
SY 100.000 $3.100 $10.000 $10.000
STRAW OR HAY MULCH
SY 100.000 $0.200 $6.000 $10.000
DRILL SEED (TEMP)(WARM OR COOL)
SY 100.000 $0.150 $6.000 $10.000
DRILL SEEDING (PERM)(WARM OR COOL)
SY 100.000 $0.200 $6.000 $10.000
FERTILIZER
AC 0.100 $500.000 $6,000.000 $1,800.000
VEGETATIVE WATERING
MG 10.000 $8.000 $100.000 $300.000
TEMPORARY SPL SHORING
SF 5,680.000 $20.000 $4.000 $74.000
CONC STR REPAIR (EPOXY MORTAR)
SF 104.000 $70.000 $250.000 $215.000
CONC STR REPAIR(RAPID DECK REP(PRT DPT)
SF 10.000 $250.000 $500.000 $400.000
RIPRAP (CONC)(5 IN)
CY 11.000 $450.000 $500.000 $1,000.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 3,050.000 $215.000 $264.000 $298.000
REMOVE STR (PILING)
LF 26.000 $150.000 $120.000 $2,000.000
MOBILIZATION
LS 1.000 $80,000.000 $125,000.000 $205,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $3,000.000 $2,500.000 $7,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 100.000 $2.500 $6.000 $3.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 100.000 $0.600 $1.000 $2.000
TREE TRIMMING / BRUSH REMOVAL(CHANNELS)
AC 3.500 $5,000.000 $4,500.000 $13,000.000
REP (CONC PARAPETW/ALUMPOST/RAIL-T4(A))
LF 25.000 $28.570 $500.000 $900.000
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 101.000 $75.000 $120.000 $90.000
REMOVE AND RE-LAY EXISTING STONE RIPRAP
CY 600.000 $150.000 $100.000 $175.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 12.000 $100.000 $100.000 $250.000
TMA (STATIONARY)
DAY 5.000 $200.000 $250.000 $500.000
Totals: $1,034,394.250 $1,227,770.000 $2,092,280.000