WALKER SH0030 (6376-15-001)

Items: 33

County: WALKER
Length: N/A
Highway: SH0030
District: BRYAN
Control Number: 6376-15-001
DBE Goal: N/A
Project: RMC - 637615001
Guaranty: N/A
Time: 730 CALENDAR DAYS
Engineer's Estimate: $556,640.00
Date: 02/04/2021 (5 years ago)
Contract Number: N/A
Type: METAL BEAM GUARD FENCE REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (4)
E
Engineer's Estimate
$556,640.00
$489,000.00
Over/Under Est: -12.15% -$67,640.00
Over/Under Est: -7.43% -$41,350.00
Amt Left: 5.38% $26,290.00
Over/Under Est: 11.58% $64,460.00
Amt Left: 27.01% $132,100.00
Delta: -20.53% -$105,810.00
Over/Under Est: 20.31% $113,050.00
Amt Left: 36.95% $180,690.00
Delta: -7.82% -$48,590.00

Bid Items & Bid Tabulations

33 Total 0 of 33
WALKER  |  SH0030  |  BRYAN  |  6376-15-001  |  02/04/2021  |  $556,640.00  |  RMC - 637615001  |  METAL BEAM GUARD FENCE REPAIR  |  730 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ROY JORGENSEN ASSOCIATES, INC.
T&L CLEANING SERVICES LLC
P-VILLE, INCORPORATED
ISI CONTRACTING, INC.
RIPRAP (MOW STRIP)(4 IN)
CY 20.000 $400.000 $425.000 $200.000 $120.000 $575.000
MOBILIZATION (CALLOUT)
EA 40.000 $550.000 $400.000 $100.000 $1,800.000 $1,800.000
REPAIR RAIL ELEMENT (W - BEAM)
LF 5,000.000 $21.250 $15.000 $21.000 $14.000 $19.000
REPAIR RAIL ELEMENT (THRIE - BEAM)
LF 50.000 $24.000 $10.000 $20.000 $15.000 $30.000
REP RAIL ELMNT(THRIE-BM TRANS TO W -BM)
LF 425.000 $25.000 $25.000 $20.000 $35.000 $30.000
REPAIR RAIL ELEMENT (CURVED RAIL)
LF 50.000 $26.500 $25.000 $25.000 $25.000 $35.000
REM / REPL TIMBER POST W / O CONC FND
EA 250.000 $34.000 $30.000 $30.000 $55.000 $45.000
REM / REPL STEEL POST W / O CONC FND
EA 150.000 $49.000 $45.000 $40.000 $80.000 $75.000
REM / REPL TIMBER POST W / CONC FND
EA 80.000 $53.000 $30.000 $50.000 $60.000 $50.000
REM / REPL STEEL POST W / CONC FND
EA 40.000 $64.000 $45.000 $100.000 $90.000 $80.000
REPAIR STEEL POST WITH BASE PLATE
EA 10.000 $155.000 $150.000 $250.000 $200.000 $250.000
REALIGN POSTS
EA 250.000 $12.500 $10.000 $10.000 $25.000 $10.000
REMOVE & REPLACE BLOCKOUT
EA 450.000 $19.000 $15.000 $10.000 $20.000 $10.000
REPLACE STL BLOCKOUTS W /WOOD BLOCKOUTS
EA 10.000 $10.000 $15.000 $10.000 $20.000 $7.000
REPLACE SINGLE GDRAIL TERMINAL RAIL
LF 200.000 $21.000 $30.000 $25.000 $25.000 $35.000
REPLACE SINGLE GDRAIL TERMINAL POST
EA 40.000 $50.000 $65.000 $60.000 $75.000 $65.000
REMOVE GDRAIL END TRT / REPL WITH SGT
EA 80.000 $3,000.000 $2,900.000 $3,000.000 $3,400.000 $3,400.000
REPL SINGLE GDRAIL TERM IMPACT HEAD
EA 10.000 $900.000 $850.000 $1,000.000 $1,400.000 $1,400.000
REM & RESET SGT IMPACT HEAD
EA 10.000 $110.000 $150.000 $100.000 $200.000 $250.000
REPLACE SGT CABLE ASSEMBLY
EA 6.000 $60.000 $100.000 $70.000 $70.000 $120.000
REPLACE SGT CABLE ANCHOR
EA 6.000 $80.000 $75.000 $70.000 $70.000 $100.000
REPLACE SGT STRUT
EA 10.000 $70.000 $75.000 $70.000 $50.000 $100.000
REPLACE SGT OBJECT MARKER
EA 15.000 $25.000 $25.000 $30.000 $20.000 $35.000
REMOVE AND REPLACE DAT
EA 20.000 $1,350.000 $1,250.000 $900.000 $1,400.000 $1,200.000
REPLACE POSTS (TL-4)
EA 300.000 $130.000 $130.000 $160.000 $180.000 $200.000
CABLE SPLICE / TURNBUCKLE (TL-4)
EA 10.000 $210.000 $165.000 $150.000 $200.000 $375.000
REPAIR CONCRETE FOUNDATION (TL-4)
EA 10.000 $275.000 $75.000 $50.000 $30.000 $45.000
REPR OR REPLC CABLE BARR TERM SEC(TL-4)
EA 10.000 $1,400.000 $1,350.000 $1,500.000 $1,000.000 $1,000.000
REPLACE CABLE (TL-4)
LF 300.000 $4.000 $2.000 $1.000 $3.000 $3.000
CHECK / RE-TENSION CABLE
EA 10.000 $200.000 $250.000 $100.000 $100.000 $200.000
REPLACE POST HARDWARE (TL-4)
EA 125.000 $30.000 $20.000 $30.000 $35.000 $35.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 10.000 $125.000 $50.000 $200.000 $1.000 $100.000
TMA (STATIONARY)
DAY 100.000 $200.000 $90.000 $100.000 $100.000 $285.000
Totals: $556,640.000 $489,000.000 $515,290.000 $621,100.000 $669,690.000