WALKER SH 75 (0110-01-052)
Items: 88
County: WALKER
Length: 0.0000 MILES
Highway: SH 75
District: BRYAN
Control Number: 0110-01-052
DBE Goal: 0.0%
Project: STP 2026(528)HES
Guaranty: $49,000.00
Time: 94 WORKING DAYS
Engineer's Estimate: $2,628,064.50
Date: 05/07/2026 (4 weeks ago) Changed
Contract Number: 5263026
Type: INSTALL SAFETY LIGHTING AND TURN BAY
Project ID: A00184443
Contract Type: Federal
Project Description: INSTALL SAFETY LIGHTING AND TURN BAY
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DELMY REYES
MATT HENSARLING
WALKER SH 75 (0110-01-052)
Project Name: N/A
Project: STP 2026(528)HES
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: 0.5 MILES NORTH OF FM 2296
Limits To: 0.5 MILES SOUTH OF FM 2296
Project Description: INSTALL SAFETY LIGHTING AND TURN BAY
WALKER SH 30 (0212-02-044)
Project Name: SH 30 AT FM 1791 - ILLUMINATION FY 26
Project: STP 2026(528)HES
Length: 0.0000 MILES
Project Type: SAFETY IMPROVEMENT PROJECTS
Limits From: 0.43 MI W OF FM 1791
Limits To: 0.47 MI E OF FM 1791
Project Description: INSTALL ILLUMINATION
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,628,064.50 | |||
| $2,980,128.53 |
13.4%
$352,064.03
|
|||
| $3,123,380.25 |
18.85%
$495,315.75
|
4.81%
$143,251.72
|
||
| $3,343,417.74 |
27.22%
$715,353.24
|
12.19%
$363,289.21
|
-7.04%
-$220,037.49
|
|
| $3,481,775.52 |
32.48%
$853,711.02
|
16.83%
$501,646.99
|
-4.14%
-$138,357.78
|
|
| $3,711,878.32 |
41.24%
$1,083,813.82
|
24.55%
$731,749.79
|
-6.61%
-$230,102.80
|
E
Engineer's Estimate
$2,628,064.50
1
Awarded
$2,980,128.53
Over/Under Est:
13.4%
$352,064.03
$3,123,380.25
Over/Under Est:
18.85%
$495,315.75
Amt Left:
4.81%
$143,251.72
$3,343,417.74
Over/Under Est:
27.22%
$715,353.24
Amt Left:
12.19%
$363,289.21
Delta:
-7.04%
-$220,037.49
$3,481,775.52
Over/Under Est:
32.48%
$853,711.02
Amt Left:
16.83%
$501,646.99
Delta:
-4.14%
-$138,357.78
$3,711,878.32
Over/Under Est:
41.24%
$1,083,813.82
Amt Left:
24.55%
$731,749.79
Delta:
-6.61%
-$230,102.80
Bid Items & Bid Tabulations
88
Total
0 of 88
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $50,000.00 |
| Total: | $60,000.00 |