Show Job Controls
Bid Cobra

VICTORIA COLOGNE RD (0913-27-097)

Items: 50

County: VICTORIA
Length: 0.2190 MILES
Highway: COLOGNE RD
District: YOAKUM
Control Number: 0913-27-097
DBE Goal: 5.0%
Project: BR 2B23(253)
Guaranty: $45,000.00
Time: 205 WORKING DAYS
Engineer's Estimate: $2,250,729.84
Date: 05/01/2025 (1 year ago)
Contract Number: 5253022
Type: BRIDGE REPLACEMENT
Project ID: A00194194
Contract Type: Federal
Project Description: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
CLAYTON HARRIS
JAMES JANAK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$2,250,729.84
1
Awarded
$1,925,463.00
Over/Under Est: -14.45% -$325,266.84
Over/Under Est: -9.27% -$208,666.40
Amt Left: 6.06% $116,600.44
Over/Under Est: -2.48% -$55,862.84
Amt Left: 13.99% $269,404.00
Delta: -7.48% -$152,803.56
Over/Under Est: -2.34% -$52,682.68
Amt Left: 14.16% $272,584.16
Delta: -0.14% -$3,180.16
Over/Under Est: -1.09% -$24,526.61
Amt Left: 15.62% $300,740.23
Delta: -1.28% -$28,156.07
Over/Under Est: 6.59% $148,328.10
Amt Left: 24.6% $473,594.94
Delta: -7.76% -$172,854.71
$2,965,231.40
Over/Under Est: 31.75% $714,501.56
Amt Left: 54% $1,039,768.40
Delta: -23.60% -$566,173.46
Subcontractor Percentage Amount
JH CONTRACT FIELD SERVICES, LLC 6.47% $124,577.46
HIGHWAY BARRICADES AND SERVICES, LLC 0.84% $16,173.89
TORO BRAVO CONSTRUCTION, LLC 0.72% $13,863.33
HOUSTON SAWING & DRILLING 0.50% $9,627.32
Total: 8.53% $164,242.00

Bid Items & Bid Tabulations

50 Total 0 of 50
VICTORIA  |  COLOGNE RD  |  YOAKUM  |  0913-27-097  |  05/01/2025  |  $2,250,729.84  |  BR 2B23(253)  |  BRIDGE REPL  |  205 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
STX CIVIL
ACME BRIDGE COMPANY, INC.
E-Z BEL CONSTRUCTION, LLC
TEXAS STEEL INDUSTRIAL PLACING, LLC
PRESIDIO CONTRACTING, LLC
DEAN WORD COMPANY, LTD.
CK NEWBERRY, LLC
PREPARING ROW
STA 11.600 $3,500.000 $2,200.000 $2,910.000 $2,100.000 $3,000.000 $5,000.000 $7,900.000 $13,000.000
EXCAV (ROADWAY)
CY 697.000 $32.500 $12.000 $24.000 $18.000 $25.000 $58.050 $63.000 $60.000
EXCAV (CHANNEL)
CY 1,334.000 $26.000 $15.000 $23.100 $29.000 $25.000 $46.900 $40.000 $75.000
EMBANK (FNL)(OC)(TY C)
CY 341.000 $60.000 $32.000 $28.800 $35.000 $30.000 $30.800 $74.500 $55.000
BLADING
HR 48.000 $120.000 $110.000 $70.600 $175.000 $100.000 $50.000 $31.000 $200.000
BROADCAST SEED (PERM_RURAL_SAND)
SY 4,368.000 $1.000 $1.000 $1.500 $2.000 $1.430 $1.000 $2.000 $1.000
BROADCAST SEED (TEMP_WARM)
SY 1,092.000 $2.000 $1.000 $3.550 $2.000 $3.330 $1.950 $4.500 $2.000
BROADCAST SEED (TEMP_COOL)
SY 1,092.000 $2.000 $1.000 $3.550 $2.000 $3.330 $1.950 $4.500 $2.000
VEGETATIVE WATERING
TGL 56.200 $90.000 $50.000 $38.300 $25.000 $50.000 $85.000 $142.000 $60.000
FL BS (CMP IN PLC)(TY E GR 5)(FNAL POS)
CY 698.000 $140.000 $120.000 $168.000 $116.000 $145.000 $171.400 $169.500 $150.000
ASPH (RC-250)
GAL 599.000 $15.000 $11.000 $14.800 $18.000 $12.000 $18.900 $15.000 $10.000
AGGR (TY-E, GR-5)(SAC-B)
CY 24.200 $1,250.000 $800.000 $1,420.000 $1,127.000 $1,100.000 $1,185.000 $1,025.000 $815.000
AGGR (TY-PE, GR-4)(SAC-B)
CY 25.300 $1,250.000 $800.000 $1,350.000 $1,090.000 $1,100.000 $1,145.000 $1,025.000 $800.000
ASPH (AC 20-5TR OR AC-20XP OR CRS-2P)
GAL 1,015.000 $15.000 $12.000 $11.600 $16.000 $12.000 $16.450 $9.000 $8.000
CEM STABIL BKFL
CY 75.000 $240.000 $180.000 $302.000 $425.000 $250.000 $380.000 $311.000 $325.000
DRILL SHAFT (24 IN)
LF 1,083.000 $265.000 $280.000 $229.000 $250.000 $315.000 $255.350 $245.500 $275.000
CL C CONC (ABUT)
CY 57.400 $1,500.000 $1,800.000 $1,330.000 $2,200.000 $1,625.000 $1,528.000 $1,789.500 $2,200.000
CL C CONC (CAP)
CY 21.100 $1,600.000 $2,120.000 $1,890.000 $2,300.000 $1,750.000 $1,885.000 $2,574.500 $2,650.000
CL C CONC (COLUMN)
CY 8.900 $1,800.000 $2,000.000 $1,760.000 $3,300.000 $1,750.000 $2,125.000 $4,121.500 $2,000.000
REINF CONC SLAB (SLAB BEAM)
SF 6,437.000 $30.000 $28.000 $24.900 $29.000 $33.000 $29.100 $38.500 $45.000
PRESTR CONC SLAB BEAM (5SB12)
LF 818.920 $252.000 $245.000 $279.000 $280.000 $260.000 $249.600 $294.500 $220.000
PRESTR CONC SLAB BEAM (5SB15)
LF 420.000 $265.000 $245.000 $277.000 $280.000 $275.000 $249.600 $293.000 $225.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 583.000 $220.000 $160.000 $212.000 $241.000 $220.000 $197.100 $160.000 $225.000
RIPRAP (STONE PROTECTION)(21 IN)
CY 640.000 $260.000 $175.000 $217.000 $261.000 $190.000 $197.100 $140.500 $205.000
RAIL (TY T223)
LF 546.000 $168.000 $160.000 $126.000 $200.000 $150.000 $167.550 $230.000 $245.000
ARMOR JOINT (SEALED)
LF 162.000 $155.000 $150.000 $169.000 $126.000 $100.000 $115.500 $169.000 $175.000
RC PIPE (CL III)(18 IN)
LF 157.000 $105.000 $90.000 $94.300 $81.000 $100.000 $54.100 $100.500 $100.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 1.000 $2,425.000 $2,000.000 $2,380.000 $2,800.000 $3,000.000 $3,455.000 $4,232.000 $6,500.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 3.000 $37,500.000 $25,000.000 $17,000.000 $23,133.000 $30,000.000 $35,100.000 $25,500.000 $125,000.000
REMOV STR (SMALL)
EA 1.000 $1,500.000 $100.000 $3,190.000 $501.000 $2,500.000 $1,250.000 $355.000 $2,000.000
MOBILIZATION
LS 1.000 $200,000.000 $152,500.000 $163,000.000 $170,000.000 $220,000.000 $200,000.000 $200,000.000 $285,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 15.000 $3,500.000 $1,500.000 $4,180.000 $1,500.000 $1,315.000 $3,260.000 $1,223.000 $5,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
CY 18.000 $320.000 $220.000 $417.000 $180.000 $150.000 $413.000 $524.500 $100.000
ROCK FILTER DAMS (REMOVE)
CY 18.000 $70.000 $30.000 $53.000 $24.000 $30.000 $50.000 $66.500 $85.000
SANDBAGS FOR EROSION CONTROL
EA 90.000 $25.000 $1.000 $4.250 $20.000 $10.000 $4.200 $5.500 $50.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,766.000 $4.500 $6.000 $5.000 $4.000 $4.000 $5.000 $6.500 $6.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,766.000 $1.500 $1.000 $1.050 $2.000 $1.000 $1.000 $1.500 $2.000
MTL W-BEAM GD FEN (TIM POST)
LF 225.000 $38.500 $30.000 $29.700 $27.000 $30.000 $27.850 $40.000 $30.000
MTL BEAM GD FEN TRANS (TL2)
EA 10.000 $1,875.000 $1,500.000 $1,270.000 $1,570.000 $1,650.000 $1,660.000 $1,468.000 $1,800.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,750.000 $1,500.000 $1,490.000 $1,682.000 $1,500.000 $1,280.000 $2,185.000 $1,900.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $3,500.000 $3,200.000 $3,290.000 $3,420.000 $3,250.000 $3,125.000 $4,670.500 $3,500.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 2.000 $32,500.000 $30,500.000 $31,300.000 $29,500.000 $30,000.000 $32,000.000 $40,030.500 $35,000.000
WIRE FENCE (TY A)
LF 540.000 $25.000 $20.000 $21.200 $34.000 $30.000 $25.750 $45.500 $35.000
WIRE FENCE (TY C)
LF 106.000 $30.000 $20.000 $21.200 $35.000 $35.000 $35.200 $46.500 $35.000
WIRE FENCE (WATER GAP)
LF 80.000 $75.000 $30.000 $53.000 $60.000 $50.000 $48.850 $80.000 $65.000
WIRE FENCE (REMOVE)
LF 106.000 $15.000 $0.100 $5.300 $13.000 $10.000 $9.500 $16.500 $15.000
IN SM RD SN SUP&AM TYTWT(1)UA(T)
EA 4.000 $775.000 $600.000 $1,050.000 $740.000 $800.000 $783.000 $1,201.000 $2,000.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 1.000 $565.000 $600.000 $700.000 $450.000 $500.000 $489.000 $800.500 $2,000.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
EA 18.000 $75.000 $20.000 $29.200 $25.000 $50.000 $25.750 $33.500 $200.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 18.000 $75.000 $20.000 $29.200 $26.000 $50.000 $31.500 $33.500 $200.000
Totals: $2,250,729.840 $1,925,463.000 $2,042,063.440 $2,194,867.000 $2,198,047.160 $2,226,203.232 $2,399,057.940 $2,965,231.400
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $500.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
Total: $1,500.00