Show Job Controls
Bid Cobra

VICTORIA SH 185 (0432-02-096)

Items: 29

County: VICTORIA
Length: N/A
Highway: SH 185
District: YOAKUM
Control Number: 0432-02-096
DBE Goal: N/A
Project: STP 2020(915)HES
Guaranty: N/A
Time: 90 WORKING DAYS
Engineer's Estimate: $509,918.00
Date: 06/04/2020 (6 years ago)
Contract Number: N/A
Type: INSTALL SIDEWALKS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$509,918.00
$469,930.70
Over/Under Est: -7.84% -$39,987.30
Over/Under Est: -4.75% -$24,235.67
Amt Left: 3.35% $15,751.63
Over/Under Est: 18.44% $94,043.00
Amt Left: 28.52% $134,030.30
Delta: -24.35% -$118,278.67
Over/Under Est: 18.97% $96,722.15
Amt Left: 29.09% $136,709.45
Delta: -0.44% -$2,679.15
$649,490.45
Over/Under Est: 27.37% $139,572.45
Amt Left: 38.21% $179,559.75
Delta: -7.06% -$42,850.30

Bid Items & Bid Tabulations

29 Total 0 of 29
VICTORIA  |  SH 185  |  YOAKUM  |  0432-02-096  |  06/04/2020  |  $509,918.00  |  STP 2020(915)HES  |  INSTL SIDEWALKS  |  90 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TI-ZACK CONCRETE, INC.
REXCO CONSTRUCTION SERVICES, INC.
FNH CONSTRUCTION, LLC
LESTER CONTRACTING, INC.
SB CONTRACTORS LLC
PREPARING ROW
STA 4.100 $7,000.000 $1,000.000 $2,400.000 $7,500.000 $1,500.000 $4,000.000
REMOVING CONC (RIPRAP)
SY 7.000 $15.000 $25.000 $80.000 $100.000 $59.700 $79.180
REMOVING CONC (SIDEWALKS)
SY 156.000 $25.000 $25.000 $6.500 $50.000 $25.000 $28.410
REMOVING CONC (DRIVEWAYS)
SY 557.000 $20.000 $25.000 $16.700 $35.000 $17.500 $19.900
REMOVING CONC (CURB AND GUTTER)
LF 144.000 $8.000 $25.000 $4.550 $20.000 $16.250 $19.910
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 19.000 $20.000 $85.000 $68.030 $35.000 $34.500 $145.980
BLADING
HR 100.000 $100.000 $25.000 $75.000 $150.000 $218.000 $95.730
COMPOST MANUF TOPSOIL (2")
SY 2,813.000 $2.000 $5.000 $3.250 $6.000 $2.750 $9.170
BLOCK SODDING
SY 2,813.000 $6.500 $5.000 $6.220 $6.000 $5.500 $5.000
VEGETATIVE WATERING
MG 23.700 $75.000 $1.000 $86.700 $50.000 $205.000 $55.280
FLEX PAVEMENT STRUCTURE REPAIR (2-8")
SY 284.000 $100.000 $80.000 $69.920 $85.000 $83.000 $153.520
RETAINING WALL (CAST - IN - PLACE)
SF 95.000 $125.000 $50.000 $61.470 $85.000 $17.750 $75.820
RIPRAP (CONC)(5 IN)
CY 4.000 $500.000 $650.000 $459.400 $650.000 $650.000 $921.600
RC PIPE (CL III)(18 IN)
LF 35.000 $85.000 $150.000 $85.700 $85.000 $151.750 $156.930
SET (TY II) (18 IN) (RCP) (6: 1) (C)
EA 2.000 $1,300.000 $1,500.000 $1,346.900 $1,850.000 $1,830.000 $2,322.470
ADJUSTING MANHOLES
EA 1.000 $1,500.000 $500.000 $1,500.000 $2,500.000 $1,600.000 $1,701.630
MOBILIZATION
LS 1.000 $46,000.000 $35,000.000 $68,450.000 $60,000.000 $23,260.000 $62,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $4,000.000 $1,500.000 $1,448.400 $8,500.000 $5,140.000 $4,500.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 910.000 $5.000 $1.000 $4.180 $4.000 $3.750 $6.150
TEMP SEDMT CONT FENCE (REMOVE)
LF 910.000 $1.000 $1.000 $1.790 $2.000 $1.000 $2.460
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 360.000 $6.000 $1.000 $5.360 $18.000 $4.100 $12.280
BIODEG EROSN CONT LOGS (REMOVE)
LF 360.000 $1.500 $1.000 $2.550 $9.000 $2.250 $2.460
CONC CURB & GUTTER (TY II)
LF 144.000 $45.000 $40.000 $30.500 $40.000 $44.000 $37.340
DRIVEWAYS (CONC)
SY 1,420.000 $90.000 $95.000 $85.830 $85.000 $112.000 $108.290
CONC SIDEWALKS (5")
SY 1,677.000 $60.000 $95.000 $76.370 $65.000 $102.500 $100.190
CURB RAMPS
SY 215.000 $145.000 $95.000 $107.100 $285.000 $238.000 $231.090
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 4.000 $500.000 $450.000 $402.900 $850.000 $410.000 $245.630
PREFAB PAV MRK TY C (W) (4") (SLD)
LF 192.000 $4.000 $6.000 $6.120 $10.000 $16.000 $12.280
TMA (STATIONARY)
DAY 65.000 $500.000 $50.000 $408.000 $300.000 $635.000 $184.220
Totals: $509,918.000 $469,930.700 $485,682.330 $603,961.000 $606,640.150 $649,490.446