VAN ZANDT US0080 (6354-30-001)

Items: 12

County: VAN ZANDT
Length: N/A
Highway: US0080
District: TYLER
Control Number: 6354-30-001
DBE Goal: N/A
Project: MMC - 635430001
Guaranty: N/A
Time: 120 CALENDAR DAYS
Engineer's Estimate: $298,175.00
Date: 02/11/2020 (6 years ago)
Contract Number: N/A
Type: HOT MIX MATERIALS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (2)
E
Engineer's Estimate
$298,175.00
$262,400.00
Over/Under Est: -12% -$35,775.00
Over/Under Est: -4.2% -$12,525.00
Amt Left: 8.86% $23,250.00

Bid Items & Bid Tabulations

12 Total 0 of 12
VAN ZANDT  |  US0080  |  TYLER  |  6354-30-001  |  02/11/2020  |  $298,175.00  |  MMC - 635430001  |  HOT MIX MATERIALS  |  120 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS MATERIALS GROUP, INC.
AUSTIN ASPHALT, INC.
D-GR HMA(SQ) TY F PG 64_22 (PICKUP)
TON 100.000 $76.250 $64.000 $75.000
D-GR HMA(SQ) TY F PG 64_22 (DELIVERY)
TON 100.000 $81.500 $73.000 $93.000
D-GR HMA(SQ) TY F PG 70_22 (PICKUP)
TON 100.000 $76.250 $66.000 $82.000
D-GR HMA(SQ) TY F PG 70_22 (DELIVERY)
TON 100.000 $81.500 $75.000 $100.000
SP MIXTURES SP-C PG64-22 (PICKUP)
TON 1,000.000 $76.250 $66.000 $66.000
SP MIXTURES SP-C PG64-22 (DELIVERY)
TON 500.000 $81.500 $75.000 $84.000
SP MIXTURES SP-C PG70-22 (PICKUP)
TON 100.000 $76.250 $64.000 $72.500
SP MIXTURES SP-C PG70-22 (DELIVERY)
TON 100.000 $81.500 $73.000 $90.500
SP MIXTURES SP-D PG64-22 (PICKUP)
TON 1,000.000 $77.000 $66.000 $67.000
SP MIXTURES SP-D PG64-22 (DELIVERY)
TON 500.000 $82.000 $75.000 $85.000
SP MIXTURES SP-D PG70-22 (PICKUP)
TON 100.000 $77.000 $65.000 $75.250
SP MIXTURES SP-D PG70-22 (DELIVERY)
TON 100.000 $81.500 $74.000 $93.250
Totals: $298,175.000 $262,400.000 $285,650.000