VAN ZANDT VA (0910-12-141)
Items: 8
County: VAN ZANDT
Length: N/A
Highway: VA
District: TYLER
Control Number: 0910-12-141
DBE Goal: 0.0%
Project: STP 2024(855)HES
Guaranty: N/A
Time: 72 WORKING DAYS
Engineer's Estimate: $472,400.00
Date: 04/04/2024 (2 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
JUANITA DANIELSWEST
STEVEN SWINDELL
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$472,400.00 | |||
| $450,860.00 |
-4.56%
-$21,540.00
|
|||
| $569,200.00 |
20.49%
$96,800.00
|
26.25%
$118,340.00
|
||
| $570,750.00 |
20.82%
$98,350.00
|
26.59%
$119,890.00
|
-0.27%
-$1,550.00
|
|
| $700,290.00 |
48.24%
$227,890.00
|
55.32%
$249,430.00
|
-22.70%
-$129,540.00
|
|
| $794,305.00 |
68.14%
$321,905.00
|
76.18%
$343,445.00
|
-13.43%
-$94,015.00
|
E
Engineer's Estimate
$472,400.00
1
Awarded
$450,860.00
Over/Under Est:
-4.56%
-$21,540.00
$569,200.00
Over/Under Est:
20.49%
$96,800.00
Amt Left:
26.25%
$118,340.00
$570,750.00
Over/Under Est:
20.82%
$98,350.00
Amt Left:
26.59%
$119,890.00
Delta:
-0.27%
-$1,550.00
$700,290.00
Over/Under Est:
48.24%
$227,890.00
Amt Left:
55.32%
$249,430.00
Delta:
-22.70%
-$129,540.00
$794,305.00
Over/Under Est:
68.14%
$321,905.00
Amt Left:
76.18%
$343,445.00
Delta:
-13.43%
-$94,015.00
| Subcontractor | Percentage | Amount |
|---|---|---|
| SCHUSTER MULCH & CONSTRUCTION, LLC | 10.37% | $46,754.18 |
| AWP SAFETY | 1.46% | $6,582.56 |
| Total: | 11.83% | $53,336.74 |
Bid Items & Bid Tabulations
8
Total
0 of 8