VAN ZANDT SH 64 (0245-02-031)

Items: 125

County: VAN ZANDT
Length: N/A
Highway: SH 64
District: TYLER
Control Number: 0245-02-031
DBE Goal: N/A
Project: C 245-2-31
Guaranty: N/A
Time: 340 WORKING DAYS
Engineer's Estimate: $11,101,486.00
Date: 04/03/2018 (8 years ago)
Contract Number: N/A
Type: FLX BS,LVL-UP,OCST,HMAC,STRS,PV MRK
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (14)
E
Engineer's Estimate
$11,101,486.00
$9,587,787.65
Over/Under Est: -13.64% -$1,513,698.35
$10,324,210.47
Over/Under Est: -7% -$777,275.53
Amt Left: 7.68% $736,422.82
Over/Under Est: -5.61% -$622,861.64
Amt Left: 9.29% $890,836.71
Delta: -1.50% -$154,413.89
Over/Under Est: -0.41% -$45,534.48
Amt Left: 15.31% $1,468,163.87
Delta: -5.51% -$577,327.16
$11,331,648.73
Over/Under Est: 2.07% $230,162.73
Amt Left: 18.19% $1,743,861.08
Delta: -2.49% -$275,697.21
$11,639,302.32
Over/Under Est: 4.84% $537,816.32
Amt Left: 21.4% $2,051,514.67
Delta: -2.71% -$307,653.59
Over/Under Est: 5.54% $614,854.52
Amt Left: 22.2% $2,128,552.87
Delta: -0.66% -$77,038.20
Over/Under Est: 5.9% $655,466.19
Amt Left: 22.62% $2,169,164.54
Delta: -0.35% -$40,611.67
$11,809,299.44
Over/Under Est: 6.38% $707,813.44
Amt Left: 23.17% $2,221,511.79
Delta: -0.45% -$52,347.25
Over/Under Est: 10.76% $1,194,042.12
Amt Left: 28.24% $2,707,740.47
Delta: -4.12% -$486,228.68
Over/Under Est: 12.22% $1,356,321.53
Amt Left: 29.93% $2,870,019.88
Delta: -1.32% -$162,279.41
Over/Under Est: 16.69% $1,853,135.71
Amt Left: 35.12% $3,366,834.06
Delta: -3.99% -$496,814.18
$13,594,166.56
Over/Under Est: 22.45% $2,492,680.56
Amt Left: 41.79% $4,006,378.91
Delta: -4.94% -$639,544.85
Over/Under Est: 25.24% $2,801,685.54
Amt Left: 45.01% $4,315,383.89
Delta: -2.27% -$309,004.98

Bid Items & Bid Tabulations

125 Total 0 of 125
VAN ZANDT  |  SH 64  |  TYLER  |  0245-02-031  |  04/03/2018  |  $11,101,486.00  |  C 245-2-31  |  FLX BS,LVL-UP,OCST,HMAC,STRS,PV MRK  |  340 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BIG CREEK CONSTRUCTION, LTD.
A. L. HELMCAMP, INC.
LONGVIEW BRIDGE AND ROAD, LTD.
SOUTH TEXAS ILLUMINATION, LLC
EAST TEXAS BRIDGE, INC.
H. V. CAVER, INC.
D. L. LENNON INCORPORATED - CONTRACTOR
A. K. GILLIS & SONS, INC.
REYNOLDS & KAY, LTD.
ED BELL CONSTRUCTION COMPANY
OLDCASTLE MATERIALS TEXAS, INC.
DREWERY CONSTRUCTION COMPANY, INCORPORATED
L. S. EQUIPMENT CO., INC.
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
PREPARING ROW
AC 3.660 $8,000.000 $7,500.000 $15,000.000 $10,000.000 $16,275.000 $10,000.000 $4,500.000 $7,490.000 $4,000.000 $8,000.000 $15,750.000 $6,000.000 $10,000.000 $5,000.000 $15,000.000
PREPARING ROW
STA 61.000 $800.000 $700.000 $1,500.000 $730.000 $1,425.000 $1,500.000 $800.000 $2,132.000 $150.000 $1,050.000 $6,300.000 $3,500.000 $2,300.000 $1,000.000 $2,000.000
REMOVING CONC (DRIVEWAYS)
SY 432.000 $20.000 $12.000 $22.000 $26.000 $11.250 $20.000 $12.000 $12.000 $12.000 $15.000 $21.000 $16.000 $17.000 $10.000 $17.000
EXCAVATION (ROADWAY)
CY 38,232.000 $7.000 $9.000 $7.500 $6.250 $4.460 $8.000 $8.900 $8.150 $12.780 $8.400 $7.350 $7.500 $17.000 $5.000 $17.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 14,182.000 $9.000 $9.000 $17.000 $6.450 $4.460 $10.000 $14.000 $10.350 $14.100 $8.400 $7.350 $16.000 $22.000 $10.000 $10.000
BACKFILL (TY C)
STA 87.370 $200.000 $250.000 $310.000 $200.000 $420.140 $425.000 $255.000 $340.000 $736.450 $350.000 $630.000 $325.000 $450.000 $250.000 $200.000
FURNISHING AND PLACING TOPSOIL (4")
SY 292,354.000 $0.500 $0.500 $0.500 $0.950 $0.920 $1.650 $2.350 $2.300 $1.750 $1.050 $1.000 $1.850 $1.350 $1.000 $2.000
STRAW/HAY MLCH SEED(PERM)(RURAL)(SANDY)
SY 265,200.000 $0.200 $0.230 $0.200 $0.280 $0.230 $0.280 $0.220 $0.200 $0.200 $0.300 $0.230 $0.200 $0.260 $0.340 $0.220
STRAW/HAY MLCH SEED(TEMP)(WARM)
SY 132,607.000 $0.200 $0.200 $0.200 $0.270 $0.210 $0.270 $0.210 $0.170 $0.170 $0.270 $0.210 $0.170 $0.260 $0.270 $0.200
STRAW/HAY MLCH SEED(TEMP)(COOL)
SY 132,607.000 $0.200 $0.200 $0.200 $0.250 $0.210 $0.260 $0.200 $0.170 $0.170 $0.270 $0.210 $0.170 $0.240 $0.250 $0.200
BONDED FBR MTRX SEED (TEMP)(WARM)
SY 300.000 $1.500 $2.500 $4.000 $1.700 $2.100 $1.750 $1.500 $5.000 $5.000 $1.750 $4.000 $5.250 $5.000 $7.000 $2.000
BONDED FBR MTRX SEED (TEMP)(COOL)
SY 300.000 $1.500 $2.500 $4.000 $1.700 $2.100 $1.750 $1.500 $5.000 $5.000 $1.750 $4.000 $5.250 $5.000 $7.000 $2.000
VEGETATIVE WATERING
MG 6,133.000 $12.000 $1.000 $8.000 $1.000 $9.600 $6.000 $1.000 $0.010 $10.780 $17.000 $25.000 $22.000 $2.000 $0.010 $20.000
FL BS (CMP IN PLACE)(TY A GR 1-2)(12")
SY 67,408.000 $25.000 $23.500 $23.000 $25.000 $27.000 $23.000 $26.400 $29.250 $28.120 $23.000 $21.000 $22.000 $30.000 $22.000 $27.000
LIME (HYDRATED LIME (DRY))
TON 577.000 $180.000 $180.000 $155.000 $165.000 $168.540 $185.000 $161.000 $165.000 $155.000 $180.000 $189.000 $157.810 $150.000 $200.000 $151.340
LIME TRT (EXST MATL)(8")
SY 35,769.000 $3.000 $3.500 $2.000 $2.000 $6.050 $2.650 $3.000 $3.100 $2.740 $5.250 $1.000 $5.490 $4.000 $3.000 $5.100
CEMENT
TON 643.000 $160.000 $180.000 $155.000 $180.000 $154.120 $165.000 $143.000 $134.000 $143.000 $155.000 $147.000 $152.860 $140.000 $150.000 $145.000
CEMENT TREAT(EXIST MATL)(8")
SY 35,779.000 $3.000 $3.500 $2.600 $1.750 $3.170 $2.150 $3.000 $3.100 $2.740 $3.500 $1.000 $4.450 $3.250 $3.000 $8.000
PRIME COAT & BLOTTER (MC-30)
GAL 13,482.000 $4.000 $4.000 $5.000 $3.200 $5.150 $5.000 $4.800 $4.300 $4.490 $4.000 $7.830 $4.300 $5.500 $4.000 $7.000
EMULS ASPH (EROSN CONT)(SS-1)
GAL 6,782.000 $3.000 $3.000 $3.000 $3.000 $4.200 $3.500 $4.800 $4.450 $4.110 $3.250 $3.000 $3.800 $3.000 $3.000 $3.600
ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR)
GAL 95,534.000 $3.000 $2.700 $3.500 $2.800 $3.940 $3.500 $4.000 $3.600 $3.670 $3.400 $3.500 $3.600 $2.500 $3.000 $3.300
AGGR (TY-PD GR-3 OR TY-PL GR-3)
CY 2,268.000 $120.000 $100.000 $100.000 $130.000 $152.250 $100.000 $110.000 $145.000 $202.290 $115.000 $120.000 $190.000 $118.000 $100.000 $156.000
D-GR HMA(SQ) TY-D PG64-22
TON 414.000 $130.000 $100.000 $100.000 $140.000 $131.250 $150.000 $175.000 $99.000 $135.000 $175.000 $135.000 $145.000 $225.000 $200.000 $118.000
SUPERPAVE MIXTURES SP-C SAC-A PG70-22
TON 25,019.000 $83.000 $75.000 $82.000 $88.000 $85.050 $102.000 $100.000 $89.060 $82.500 $99.000 $90.000 $85.000 $96.000 $100.000 $84.000
SUPERPAVE MIXTURES SP-D PG64-22(LEV-UP)
TON 12,634.000 $95.000 $70.000 $78.000 $96.000 $81.900 $102.000 $95.000 $87.350 $83.000 $97.000 $86.000 $87.000 $105.000 $100.000 $83.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 4,000.000 $60.000 $30.000 $45.000 $55.000 $50.400 $50.000 $20.000 $41.000 $55.750 $40.000 $57.750 $54.000 $45.000 $50.000 $80.000
PLANE ASPH CONC PAV(0" TO 2")
SY 9,587.000 $5.000 $2.500 $4.000 $4.750 $4.390 $4.500 $6.000 $5.250 $2.250 $5.750 $6.300 $5.000 $4.500 $5.000 $3.600
CUT & RESTORING PAV
SY 12.000 $180.000 $150.000 $110.000 $200.000 $110.000 $100.000 $125.000 $125.000 $125.000 $85.000 $315.000 $150.000 $150.000 $150.000 $45.000
FLOWABLE BACKFILL
CY 25.000 $350.000 $200.000 $220.000 $220.000 $186.000 $300.000 $200.000 $200.000 $200.000 $155.000 $315.000 $165.000 $200.000 $250.000 $150.000
TEMPORARY SPL SHORING
SF 260.000 $35.000 $40.000 $55.000 $35.000 $18.900 $50.000 $26.000 $75.000 $150.000 $50.000 $73.500 $25.000 $50.000 $60.000 $45.000
CL A CONC (COLLAR)
EA 20.000 $900.000 $800.000 $1,250.000 $500.000 $792.000 $1,100.000 $450.000 $450.000 $450.000 $900.000 $450.000 $800.000 $1,200.000 $600.000 $500.000
CL E CONC (SEAL SLAB)
CY 23.700 $400.000 $400.000 $400.000 $390.000 $315.000 $450.000 $250.000 $250.000 $250.000 $600.000 $350.000 $800.000 $500.000 $300.000 $550.000
RIPRAP (CONC)(CL B)(5 IN)
CY 66.000 $400.000 $450.000 $540.000 $455.000 $467.400 $500.000 $390.000 $390.000 $390.000 $525.000 $525.000 $600.000 $1,000.000 $700.000 $420.000
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 197.000 $140.000 $120.000 $125.000 $170.000 $186.000 $145.000 $167.000 $135.000 $169.560 $180.000 $168.000 $80.000 $150.000 $250.000 $250.000
RIPRAP (MOW STRIP)(4 IN)
CY 17.000 $500.000 $400.000 $630.000 $525.000 $417.600 $500.000 $400.000 $400.000 $400.000 $715.000 $525.000 $550.000 $550.000 $450.000 $450.000
CONC BOX CULV (3 FT X 3 FT)(EXTEND)
LF 90.000 $300.000 $500.000 $500.000 $275.000 $351.000 $400.000 $300.000 $300.000 $300.000 $450.000 $525.000 $800.000 $425.000 $450.000 $300.000
CONC BOX CULV (6 FT X 4 FT)(EXTEND)
LF 13.000 $500.000 $850.000 $685.000 $830.000 $561.000 $700.000 $410.000 $410.000 $410.000 $555.000 $875.000 $600.000 $525.000 $525.000 $580.000
CONC BOX CULV (6 FT X 6 FT)(EXTEND)
LF 18.000 $550.000 $900.000 $625.000 $675.000 $753.000 $750.000 $500.000 $500.000 $500.000 $600.000 $900.000 $600.000 $550.000 $600.000 $680.000
CONC BOX CULV (7 FT X 4 FT)(EXTEND)
LF 24.000 $600.000 $1,100.000 $700.000 $565.000 $789.000 $650.000 $490.000 $490.000 $490.000 $685.000 $945.000 $700.000 $650.000 $650.000 $630.000
CONC BOX CULV (6 FT X 2.5 FT) (EXTEND)
LF 38.000 $600.000 $700.000 $650.000 $625.000 $792.000 $600.000 $325.000 $325.000 $325.000 $515.000 $875.000 $575.000 $500.000 $550.000 $580.000
CONC BOX CULVERT (10 FT X 2.5 FT)
LF 26.000 $700.000 $2,000.000 $750.000 $800.000 $810.000 $800.000 $425.000 $425.000 $425.000 $685.000 $1,050.000 $850.000 $650.000 $750.000 $1,050.000
RC PIPE (CL III)(18 IN)
LF 5,044.000 $50.000 $48.000 $48.000 $32.250 $30.630 $38.000 $40.000 $35.000 $35.000 $51.000 $63.000 $44.000 $46.000 $35.000 $60.000
RC PIPE (CL III)(24 IN)
LF 413.000 $60.000 $75.000 $90.000 $55.000 $49.960 $50.000 $50.000 $50.000 $50.000 $56.000 $73.500 $56.000 $95.000 $50.000 $90.000
RC PIPE (CL III)(30 IN)
LF 188.000 $70.000 $85.000 $130.000 $80.000 $66.900 $70.000 $70.000 $70.000 $70.000 $72.000 $94.500 $97.000 $145.000 $80.000 $125.000
RC PIPE (CL III)(36 IN)
LF 84.000 $120.000 $100.000 $190.000 $100.000 $96.280 $100.000 $80.000 $80.000 $80.000 $103.000 $189.000 $125.000 $200.000 $110.000 $180.000
RC PIPE (CL III)(42 IN)
LF 20.000 $180.000 $150.000 $225.000 $125.000 $140.190 $150.000 $100.000 $100.000 $100.000 $116.000 $240.000 $180.000 $400.000 $150.000 $240.000
RC PIPE (CL III)(48 IN)
LF 18.000 $160.000 $215.000 $260.000 $150.000 $190.760 $200.000 $130.000 $130.000 $130.000 $123.000 $630.000 $275.000 $400.000 $200.000 $305.000
HEADWALL (CH - PW - 0) (DIA= 30 IN)
EA 1.000 $6,000.000 $6,900.000 $4,500.000 $5,000.000 $4,590.000 $6,500.000 $3,000.000 $3,000.000 $3,000.000 $4,000.000 $9,000.000 $5,600.000 $3,700.000 $5,000.000 $6,240.000
HEADWALL (CH - PW - 0) (DIA= 48 IN)
EA 2.000 $11,000.000 $9,600.000 $7,800.000 $7,350.000 $4,650.000 $8,500.000 $6,000.000 $6,000.000 $6,000.000 $8,000.000 $14,700.000 $8,500.000 $7,200.000 $7,500.000 $7,260.000
WINGWALL (FW - 0) (HW=4 FT)
EA 7.000 $6,000.000 $6,500.000 $4,000.000 $5,000.000 $5,325.000 $7,000.000 $4,000.000 $4,000.000 $4,000.000 $3,500.000 $10,500.000 $9,800.000 $3,250.000 $4,500.000 $4,500.000
WINGWALL (FW - 0) (HW=5 FT)
EA 1.000 $6,000.000 $9,700.000 $6,500.000 $6,000.000 $7,002.000 $8,500.000 $5,000.000 $5,000.000 $5,000.000 $5,500.000 $12,600.000 $11,000.000 $5,100.000 $6,000.000 $5,200.000
WINGWALL (FW - 0) (HW=6 FT)
EA 1.000 $8,000.000 $10,000.000 $11,000.000 $6,000.000 $7,440.000 $10,000.000 $6,000.000 $6,000.000 $6,000.000 $6,000.000 $13,650.000 $11,500.000 $5,500.000 $6,300.000 $6,000.000
WINGWALL (FW - 0) (HW=8 FT)
EA 2.000 $14,000.000 $13,500.000 $9,500.000 $8,000.000 $11,640.000 $14,000.000 $10,000.000 $10,000.000 $10,000.000 $29,000.000 $15,750.000 $19,800.000 $9,500.000 $11,500.000 $10,000.000
WINGWALL (PW - 2) (HW=4 FT)
EA 1.000 $11,000.000 $9,300.000 $8,500.000 $8,000.000 $7,800.000 $8,500.000 $6,000.000 $6,000.000 $6,000.000 $7,500.000 $13,650.000 $9,600.000 $6,900.000 $7,500.000 $7,200.000
WINGWALL (PW - 2) (HW=5 FT)
EA 1.000 $13,000.000 $11,000.000 $9,000.000 $9,000.000 $7,815.000 $10,000.000 $7,000.000 $7,000.000 $7,000.000 $9,200.000 $14,700.000 $12,000.000 $8,500.000 $10,000.000 $8,880.000
WINGWALL (PW - 2) (HW=6 FT)
EA 1.000 $14,000.000 $12,700.000 $10,000.000 $9,500.000 $10,575.000 $12,000.000 $12,000.000 $12,000.000 $12,000.000 $10,300.000 $15,750.000 $15,000.000 $9,500.000 $10,000.000 $10,200.000
SET (TY I) (42 IN) (3: 1) (C)
EA 2.000 $9,000.000 $9,500.000 $3,500.000 $7,000.000 $7,740.000 $6,500.000 $3,800.000 $3,800.000 $3,800.000 $7,000.000 $8,400.000 $9,000.000 $4,500.000 $6,000.000 $2,500.000
SET (TY II) (18 IN) (CMP) (6: 1) (P)
EA 4.000 $1,200.000 $675.000 $650.000 $565.000 $609.000 $525.000 $450.000 $500.000 $500.000 $750.000 $735.000 $875.000 $650.000 $650.000 $800.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 354.000 $700.000 $675.000 $650.000 $515.000 $639.000 $525.000 $600.000 $500.000 $500.000 $750.000 $735.000 $800.000 $650.000 $650.000 $800.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 12.000 $800.000 $850.000 $750.000 $690.000 $852.000 $665.000 $600.000 $600.000 $600.000 $850.000 $735.000 $875.000 $725.000 $850.000 $850.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 20.000 $1,000.000 $1,000.000 $850.000 $880.000 $1,122.000 $900.000 $630.000 $800.000 $800.000 $1,000.000 $945.000 $925.000 $800.000 $1,000.000 $900.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 4.000 $1,600.000 $1,300.000 $1,400.000 $1,050.000 $1,674.000 $1,400.000 $1,100.000 $1,100.000 $1,100.000 $1,700.000 $1,050.000 $1,350.000 $1,325.000 $1,325.000 $950.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 4.000 $1,800.000 $1,650.000 $2,200.000 $1,525.000 $1,974.000 $1,900.000 $2,000.000 $2,000.000 $2,000.000 $2,100.000 $1,470.000 $1,920.000 $2,100.000 $1,900.000 $2,000.000
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 6.000 $4,000.000 $3,450.000 $3,300.000 $3,300.000 $4,068.000 $3,750.000 $3,800.000 $3,800.000 $3,800.000 $4,400.000 $3,150.000 $4,950.000 $3,250.000 $4,500.000 $3,500.000
SET (TY II) (42 IN) (RCP) (4: 1) (C)
EA 2.000 $3,300.000 $3,500.000 $4,400.000 $2,925.000 $4,170.000 $3,200.000 $3,100.000 $3,100.000 $3,100.000 $4,600.000 $4,200.000 $5,000.000 $4,250.000 $3,500.000 $4,500.000
REMOV STR (PIPE)
LF 4,916.000 $18.000 $12.000 $18.000 $8.000 $8.100 $10.000 $8.000 $8.000 $8.000 $24.000 $10.500 $5.500 $18.000 $10.000 $10.000
MOBILIZATION
LS 1.000 $700,000.000 $925,000.000 $940,000.000 $750,000.000 $1,096,273.950 $760,000.000 $500,000.000 $1,163,000.000 $1,303,190.000 $1,192,000.000 $1,300,000.000 $1,241,062.000 $1,290,000.000 $1,100,000.000 $1,255,900.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 21.000 $7,000.000 $2,500.000 $13,000.000 $3,400.000 $7,642.500 $3,500.000 $2,900.000 $6,000.000 $15,009.520 $8,000.000 $42,000.000 $26,000.000 $3,500.000 $10,000.000 $46,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 6,013.000 $30.000 $23.000 $22.000 $26.000 $21.150 $26.000 $34.000 $24.000 $24.000 $27.000 $21.000 $26.000 $25.000 $35.000 $21.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 2,130.000 $30.000 $25.000 $28.000 $30.000 $23.400 $30.000 $40.000 $28.000 $28.000 $30.000 $25.000 $30.000 $28.000 $42.000 $25.000
ROCK FILTER DAMS (REMOVE)
LF 8,143.000 $8.000 $2.000 $2.000 $9.500 $4.050 $7.000 $10.000 $5.000 $5.000 $8.000 $7.500 $5.200 $10.000 $10.000 $7.500
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 544.000 $20.000 $22.000 $12.000 $29.750 $28.650 $30.000 $35.000 $20.000 $20.000 $30.000 $21.000 $21.000 $28.000 $50.000 $28.000
CONSTRUCTION EXITS (REMOVE)
SY 544.000 $8.000 $5.000 $2.000 $9.400 $9.000 $5.000 $11.000 $5.000 $5.000 $8.000 $10.500 $5.500 $9.000 $10.000 $8.600
EARTHWORK (EROSN & SEDMT CONT, IN VEH)
CY 2,000.000 $40.000 $15.000 $10.000 $11.250 $26.100 $20.000 $20.000 $10.000 $35.000 $8.000 $13.650 $24.000 $15.000 $25.000 $23.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 200.000 $120.000 $100.000 $65.000 $225.000 $105.750 $65.000 $85.000 $50.000 $122.360 $46.000 $168.000 $105.000 $125.000 $100.000 $548.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 8,040.000 $2.750 $3.000 $3.500 $2.900 $2.370 $3.000 $6.000 $2.500 $2.500 $3.000 $2.360 $2.650 $3.000 $3.000 $2.250
TEMP SEDMT CONT FENCE (REMOVE)
LF 8,040.000 $1.000 $0.500 $0.750 $1.100 $0.630 $0.750 $0.700 $1.000 $1.000 $1.000 $0.630 $1.050 $0.500 $1.000 $0.600
TRACKHOE WORK (EROSION & SEDMT CONT)
HR 60.000 $100.000 $150.000 $88.000 $225.000 $180.000 $85.000 $95.000 $50.000 $242.760 $80.000 $262.500 $145.000 $130.000 $75.000 $191.000
DRIVEWAYS (ACP)
SY 18,503.000 $45.000 $17.000 $22.000 $25.000 $28.500 $23.000 $49.000 $32.800 $18.200 $24.000 $14.840 $22.000 $33.000 $100.000 $32.000
TURNOUTS (ACP)
SY 559.000 $60.000 $25.000 $22.000 $44.000 $28.500 $30.000 $49.000 $33.000 $20.800 $28.000 $19.670 $26.000 $50.000 $100.000 $52.000
DRIVEWAYS (CONC) (HES)
SY 425.000 $100.000 $92.000 $140.000 $105.000 $101.250 $80.000 $80.000 $95.000 $80.000 $100.000 $126.000 $180.000 $110.000 $125.000 $262.000
MTL W-BEAM GD FEN (TIM POST)
LF 140.000 $22.000 $25.000 $24.000 $25.000 $19.850 $25.000 $23.000 $23.000 $23.000 $21.000 $19.850 $38.000 $40.000 $25.000 $20.000
MTL BM GD FEN (LONG SPAN SYSTEM)
LF 33.000 $22.000 $30.000 $27.000 $28.000 $25.200 $30.000 $26.000 $26.000 $26.000 $27.000 $25.200 $40.000 $40.000 $50.000 $25.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $2,600.000 $2,500.000 $2,800.000 $2,890.000 $2,520.000 $2,900.000 $2,625.000 $2,625.000 $2,625.000 $2,700.000 $2,520.000 $2,700.000 $2,500.000 $2,500.000 $2,200.000
PIPE UNDERDRAINS (TY 8) (6")
LF 500.000 $40.000 $33.000 $35.000 $46.000 $33.000 $30.000 $30.000 $45.000 $35.000 $35.000 $21.000 $30.000 $45.000 $100.000 $35.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 99.000 $220.000 $200.000 $200.000 $265.000 $183.580 $195.000 $185.000 $155.000 $185.000 $275.000 $236.250 $200.000 $255.000 $200.000 $185.000
MAILBOX INSTALL-M (TWG-POST) TY 2
EA 11.000 $320.000 $400.000 $400.000 $425.000 $300.000 $425.000 $255.000 $350.000 $375.000 $440.000 $472.500 $400.000 $405.000 $450.000 $375.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 4.000 $800.000 $510.000 $530.000 $635.000 $483.000 $760.000 $550.000 $505.000 $505.000 $650.000 $598.500 $545.000 $610.000 $800.000 $185.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 11.000 $700.000 $600.000 $620.000 $720.000 $526.220 $1,000.000 $600.000 $580.000 $585.000 $750.000 $656.250 $600.000 $700.000 $1,000.000 $375.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 1.000 $620.000 $700.000 $730.000 $825.000 $672.000 $750.000 $670.000 $825.000 $690.000 $850.000 $735.000 $720.000 $800.000 $850.000 $505.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $640.000 $800.000 $800.000 $915.000 $655.630 $1,000.000 $725.000 $795.000 $760.000 $950.000 $803.250 $800.000 $900.000 $1,000.000 $585.000
IN SM RD SN SUP&AM TYS80(1)SA(U-WC)
EA 7.000 $750.000 $900.000 $940.000 $1,020.000 $761.680 $1,100.000 $800.000 $970.000 $890.000 $1,000.000 $876.750 $900.000 $1,000.000 $1,000.000 $690.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 77.000 $400.000 $300.000 $300.000 $400.000 $296.400 $380.000 $400.000 $170.000 $285.000 $400.000 $420.000 $300.000 $400.000 $510.000 $760.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 1.000 $450.000 $400.000 $400.000 $485.000 $341.020 $480.000 $450.000 $300.000 $365.000 $500.000 $488.250 $400.000 $475.000 $510.000 $900.000
REMOVE SM RD SN SUP&AM
EA 101.000 $100.000 $65.000 $70.000 $88.000 $1.440 $90.000 $90.000 $75.000 $65.000 $90.000 $105.000 $70.000 $90.000 $100.000 $115.000
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND
EA 8.000 $95.000 $40.000 $45.000 $75.000 $59.750 $55.000 $50.000 $68.000 $40.000 $75.000 $47.250 $43.000 $72.000 $50.000 $75.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
EA 4.000 $23.000 $50.000 $30.000 $26.000 $48.600 $30.000 $30.000 $24.000 $24.000 $60.000 $29.400 $62.000 $60.000 $50.000 $75.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 36.000 $65.000 $50.000 $55.000 $75.000 $63.400 $55.000 $50.000 $68.000 $50.000 $80.000 $57.750 $52.000 $57.750 $75.000 $75.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 156,191.000 $0.200 $0.100 $0.110 $0.110 $0.140 $0.110 $0.200 $0.120 $0.100 $0.110 $0.130 $0.120 $0.110 $0.120 $0.100
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 2,020.000 $0.350 $0.250 $0.260 $0.280 $0.570 $0.280 $0.650 $0.550 $0.250 $0.300 $0.580 $0.270 $0.260 $0.300 $0.250
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 1,010.000 $5.000 $2.000 $2.100 $2.200 $4.760 $2.200 $4.500 $4.500 $2.000 $2.300 $4.730 $2.200 $2.100 $2.250 $2.000
WK ZN PAV MRK NON-REMOV (W)(ARROW)
EA 8.000 $50.000 $35.000 $37.000 $38.500 $68.250 $38.500 $80.000 $65.000 $35.000 $40.000 $68.250 $37.000 $36.750 $40.000 $35.000
WK ZN PAV MRK NON-REMOV(W)(WORD)
EA 14.000 $160.000 $55.000 $58.000 $60.000 $78.750 $60.000 $128.000 $75.000 $55.000 $63.000 $78.750 $58.000 $57.750 $75.000 $55.000
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 156,191.000 $0.200 $0.100 $0.110 $0.110 $0.130 $0.110 $0.200 $0.120 $0.100 $0.110 $0.130 $0.110 $0.110 $0.120 $0.100
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 664.000 $3.500 $3.250 $3.300 $3.400 $3.020 $3.400 $3.500 $2.800 $3.100 $3.550 $2.940 $3.200 $3.260 $3.500 $3.100
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 45,491.000 $0.700 $0.500 $0.200 $1.050 $0.650 $1.250 $0.750 $0.640 $0.600 $1.240 $0.670 $1.050 $1.000 $3.000 $0.840
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 156,191.000 $0.700 $0.500 $0.200 $1.050 $0.650 $1.250 $0.600 $0.640 $0.600 $0.750 $0.670 $1.050 $0.960 $3.000 $0.840
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,758.000 $1.250 $2.000 $0.400 $1.250 $1.050 $1.250 $1.200 $2.000 $2.170 $0.900 $2.000 $1.030 $0.900 $1.000 $5.600
WK ZN PAV MRK SHT TERM RMV (Y)(4")
LF 35,143.000 $1.500 $0.500 $0.400 $1.250 $1.060 $1.250 $0.750 $1.000 $2.500 $1.250 $2.000 $1.050 $1.000 $3.000 $4.300
REFL PAV MRK TY I (W)4"(LNDP)(100MIL)
LF 414.000 $1.000 $1.000 $1.100 $1.100 $0.440 $1.100 $1.100 $1.000 $1.000 $1.150 $1.050 $1.080 $1.050 $1.250 $0.420
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,010.000 $1.000 $1.000 $0.900 $0.950 $0.390 $0.930 $0.700 $1.000 $0.840 $0.950 $1.050 $1.000 $0.880 $1.000 $0.400
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 4,030.000 $0.500 $0.420 $0.440 $0.460 $0.440 $0.460 $0.380 $0.410 $0.420 $0.500 $0.430 $0.450 $0.440 $0.500 $0.420
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 87,565.000 $0.400 $0.370 $0.390 $0.400 $0.380 $0.410 $0.280 $0.360 $0.370 $0.400 $0.380 $0.390 $0.390 $0.450 $0.400
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 2,955.000 $0.500 $0.420 $0.440 $0.460 $0.440 $0.460 $0.420 $0.410 $0.420 $0.500 $0.430 $0.440 $0.440 $0.500 $0.420
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 75,030.000 $0.400 $0.370 $0.390 $0.400 $0.380 $0.410 $0.280 $0.360 $0.370 $0.400 $0.380 $0.390 $0.390 $0.400 $0.370
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 505.000 $13.000 $12.000 $12.000 $12.650 $12.870 $12.650 $10.000 $12.250 $11.500 $13.000 $12.860 $12.100 $12.080 $15.000 $11.500
PREFAB PAV MRK TY C (W) (ARROW)
EA 15.000 $160.000 $170.000 $180.000 $190.000 $268.800 $190.000 $150.000 $255.000 $170.000 $195.000 $267.750 $180.000 $178.500 $170.000 $170.000
PREFAB PAV MRK TY C (W) (WORD)
EA 7.000 $215.000 $225.000 $240.000 $250.000 $393.860 $250.000 $225.000 $375.000 $225.000 $250.000 $393.750 $235.000 $236.250 $250.000 $225.000
REFL PAV MRKR TY I-A
EA 332.000 $4.000 $3.500 $3.500 $3.500 $4.010 $3.500 $4.000 $3.800 $3.200 $3.600 $3.990 $3.400 $3.360 $3.500 $3.200
REFL PAV MRKR TY I-C
EA 260.000 $3.700 $3.500 $3.500 $3.500 $4.000 $3.500 $4.000 $3.800 $3.200 $3.600 $3.990 $3.400 $3.360 $3.500 $3.200
REFL PAV MRKR TY II-A-A
EA 1,347.000 $3.700 $3.500 $3.500 $3.500 $4.000 $3.500 $3.200 $3.800 $3.200 $3.600 $3.990 $3.400 $3.360 $3.500 $3.200
FLOATING TURBIDITY BARRIER
LF 850.000 $100.000 $40.000 $28.000 $30.000 $14.830 $30.000 $27.000 $30.000 $35.000 $28.000 $25.000 $25.000 $30.000 $300.000 $12.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $6,000.000 $12,500.000 $18,000.000 $16,000.000 $6,600.000 $25,000.000 $15,000.000 $19,000.000 $13,000.000 $8,500.000 $15,000.000 $29,000.000 $225.000 $21,000.000 $16,000.000
TMA (STATIONARY)
EA 1.000 $8,000.000 $3,500.000 $22,000.000 $8,000.000 $10,200.000 $25,000.000 $30,000.000 $25,000.000 $5,000.000 $24,500.000 $20,000.000 $55,220.000 $20,000.000 $21,000.000 $65,000.000
TMA (STATIONARY)
DAY 100.000 $200.000 $100.000 $250.000 $150.000 $360.000 $250.000 $200.000 $300.000 $150.000 $100.000 $315.000 $285.000 $500.000 $150.000 $400.000
Totals: $11,101,486.000 $9,587,787.650 $10,324,210.470 $10,478,624.360 $11,055,951.522 $11,331,648.730 $11,639,302.320 $11,716,340.520 $11,756,952.196 $11,809,299.440 $12,295,528.120 $12,457,807.530 $12,954,621.710 $13,594,166.560 $13,903,171.540