VAN ZANDT SH 19 (0108-12-018)

Items: 125

County: VAN ZANDT
Length: N/A
Highway: SH 19
District: TYLER
Control Number: 0108-12-018
DBE Goal: N/A
Project: F 2022(423)
Guaranty: N/A
Time: 225 WORKING DAYS
Engineer's Estimate: $8,429,563.20
Date: 04/06/2022 (4 years ago)
Contract Number: N/A
Type: HIGHWAY IMPROVEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (5)
E
Engineer's Estimate
$8,429,563.20
$8,769,308.82
Over/Under Est: 4.03% $339,745.62
Over/Under Est: 4.32% $364,426.93
Amt Left: 0.28% $24,681.31
Over/Under Est: 7.97% $671,786.36
Amt Left: 3.79% $332,040.74
Delta: -3.50% -$307,359.43
$9,671,130.90
Over/Under Est: 14.73% $1,241,567.70
Amt Left: 10.28% $901,822.08
Delta: -6.26% -$569,781.34
Over/Under Est: 18.38% $1,549,008.92
Amt Left: 13.79% $1,209,263.30
Delta: -3.18% -$307,441.22
Subcontractor Percentage Amount
MISSOURI PETROLEUM PRODUCTS COMPANY LLC 6.96% $642,497.11
J & M CONTRACTING, COMPANY 4.24% $391,406.29
J. H. ODEN CONTRACTING COMPANY 1.91% $176,317.46
STRIPE-A-ZONE, LLC 1.17% $108,005.98
FORTSON CONTRACTING, INC. 1.17% $108,005.98
MARCOM'S MOWING SERVICE, LLC 0.72% $66,465.22
WOLFE CONSTRUCTION GROUP, INCORPORATED 0.30% $27,693.84
TEXAS TRAFFIC AND BARRICADE, LLC 0.24% $22,155.07
CHEROKEE SERVICES 0.16% $14,770.05
WEST TEXAS ROCK RESOURCES, LLC 0.11% $10,154.41
Total: 16.98% $1,567,471.41

Bid Items & Bid Tabulations

125 Total 0 of 125
VAN ZANDT  |  SH 19  |  TYLER  |  0108-12-018  |  04/06/2022  |  $8,429,563.20  |  F 2022(423)  |  HWY IMPRV  |  225 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
A. L. HELMCAMP, INC.
LONGVIEW BRIDGE AND ROAD, LTD.
D. L. LENNON INCORPORATED - CONTRACTOR
REYNOLDS & KAY, LTD.
EAST TEXAS BRIDGE, INC.
PREPARING ROW
STA 19.990 $1,500.000 $3,000.000 $7,000.000 $2,770.000 $2,500.000 $5,000.000
REMOVING CONC (DRIVEWAYS)
SY 55.000 $20.000 $75.000 $50.000 $22.000 $25.000 $35.000
EXCAVATION (ROADWAY)
CY 9,828.600 $10.000 $7.500 $11.250 $6.500 $10.000 $15.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 10,065.000 $15.000 $5.500 $15.000 $13.000 $15.000 $20.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 46.000 $20.000 $50.000 $65.000 $45.000 $30.000 $20.000
BACKFILL (TY A)
STA 131.890 $225.000 $295.000 $250.000 $273.000 $325.000 $325.000
BACKFILL (TY A)
LF 17,646.000 $2.250 $3.500 $1.500 $2.730 $2.000 $2.000
BLADING
STA 6.000 $200.000 $250.000 $600.000 $1,000.000 $400.000 $500.000
FURNISHING AND PLACING TOPSOIL (4")
SY 53,762.000 $1.500 $0.500 $1.750 $1.350 $2.500 $2.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 46,448.000 $0.150 $0.160 $0.130 $0.068 $0.100 $0.090
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 92,895.000 $0.800 $0.680 $0.850 $0.633 $0.750 $0.750
BONDED FBR MTRX SEED (TEMP)(WARM)
SY 46,448.000 $0.800 $0.660 $0.850 $0.568 $0.650 $0.660
BONDED FBR MTRX SEED (TEMP)(COOL)
SY 46,448.000 $0.800 $0.660 $0.850 $0.547 $0.650 $0.640
VEGETATIVE WATERING
MG 2,044.000 $12.000 $5.000 $12.000 $0.010 $15.000 $5.000
FL BS (CMP IN PLACE)(TY A GR 1-2)(8")
SY 24,200.000 $18.000 $17.000 $14.750 $23.400 $20.000 $21.000
LIME (HYDRATED LIME (DRY))
TON 188.000 $180.000 $200.000 $270.000 $270.000 $245.000 $235.000
LIME TRT (EXST MATL)(8")
SY 12,540.000 $4.000 $4.000 $2.250 $4.000 $5.500 $5.000
CEMENT
TON 213.000 $175.000 $205.000 $245.000 $263.000 $215.000 $225.000
CEMENT TREAT(EXIST MATL)(8")
SY 12,540.000 $4.000 $6.000 $2.250 $4.000 $3.500 $3.000
PRIME COAT (MC-30)
GAL 6,996.000 $4.000 $6.000 $5.250 $6.350 $5.000 $6.000
EMULS ASPH (EROSN CONT)(CSS-1)
GAL 1,461.000 $4.300 $8.000 $5.000 $8.350 $4.500 $6.000
ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR)
GAL 94,600.000 $4.000 $4.500 $5.250 $7.220 $4.750 $4.500
AGGR (TY-PD GR-3 OR TY-PL GR-3)
CY 2,252.000 $125.000 $160.000 $135.000 $165.000 $145.000 $110.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 2,000.000 $55.000 $90.000 $55.000 $117.000 $60.000 $60.000
PLANE ASPH CONC PAV(0" TO 2")
SY 5,868.000 $2.500 $4.000 $2.750 $3.580 $3.750 $3.750
PLANE ASPH CONC PAV (1.5")
SY 2,886.000 $2.500 $4.000 $3.000 $3.600 $4.000 $3.500
PLANE ASPH CONC PAV (2")
SY 10,242.000 $2.500 $2.650 $3.000 $3.250 $3.500 $2.900
PLANE ASPH CONC PAV (6")
SY 12,170.000 $4.500 $3.350 $4.500 $5.500 $7.000 $7.000
PLANE ASPH CONC PAV (0" TO 1 1/2")
SY 13,172.000 $2.500 $2.650 $3.000 $2.650 $3.000 $2.150
TEMPORARY SPL SHORING
SF 120.000 $25.000 $79.000 $100.000 $15.000 $60.000 $70.000
CL C CONC (COLLAR)
EA 12.000 $1,000.000 $499.000 $1,650.000 $475.000 $800.000 $2,000.000
CL E CONC (SEAL SLAB)(NON-REINF)
CY 5.400 $425.000 $447.000 $570.000 $425.000 $840.000 $600.000
RIPRAP (CONC) (CL B) (4")
CY 16.000 $500.000 $499.000 $585.000 $475.000 $700.000 $750.000
RIPRAP (STONE COMMON)(DRY)(18 IN)
CY 153.000 $160.000 $237.000 $175.000 $172.000 $200.000 $170.000
RIPRAP (MOW STRIP)(4 IN)
CY 171.000 $500.000 $525.000 $555.000 $500.000 $625.000 $550.000
CLEANING AND SEALING JOINTS (CL 3)
LF 572.000 $35.000 $30.000 $35.000 $36.000 $25.000 $33.000
CONC BOX CULV (4 FT X 3 FT)(EXTEND)
LF 18.000 $500.000 $685.000 $1,100.000 $650.000 $670.000 $1,000.000
CONC BOX CULV (5 FT X 3 FT)(EXTEND)
LF 8.000 $550.000 $710.000 $1,350.000 $675.000 $930.000 $1,000.000
CONC BOX CULV (7 FT X 5 FT)(EXTEND)
LF 11.000 $700.000 $790.000 $1,450.000 $750.000 $835.000 $1,000.000
RC PIPE (CL III)(18 IN)
LF 936.000 $50.000 $45.500 $49.000 $43.000 $50.000 $65.000
RC PIPE (CL III)(24 IN)
LF 92.000 $70.000 $73.500 $68.000 $70.000 $85.000 $90.000
RC PIPE (CL III)(30 IN)
LF 36.000 $90.000 $94.500 $120.000 $90.000 $95.000 $115.000
RC PIPE (CL III)(36 IN)
LF 18.000 $110.000 $126.000 $200.000 $120.000 $130.000 $150.000
WINGWALL (PW - 1) (HW=7 FT)
EA 3.000 $15,000.000 $22,050.000 $15,500.000 $21,000.000 $18,000.000 $24,000.000
SET (TY I)(S= 7 FT)(HW= 6 FT)(3:1) (C)
EA 1.000 $10,000.000 $10,500.000 $4,000.000 $10,000.000 $15,000.000 $10,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 50.000 $650.000 $682.500 $850.000 $650.000 $900.000 $750.000
SET (TY II) (24 IN) (RCP) (3: 1) (C)
EA 4.000 $800.000 $761.250 $1,050.000 $725.000 $900.000 $850.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 2.000 $850.000 $840.000 $1,600.000 $800.000 $1,000.000 $950.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 2.000 $900.000 $1,155.000 $1,800.000 $1,100.000 $1,200.000 $1,200.000
SET (TY II) (30 IN) (RCP) (3: 1) (C)
EA 1.000 $1,400.000 $1,260.000 $2,800.000 $1,200.000 $1,250.000 $1,800.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 2.000 $1,600.000 $1,470.000 $2,000.000 $1,400.000 $1,400.000 $2,000.000
SET (TY II) (36 IN) (RCP) (3: 1) (C)
EA 3.000 $2,000.000 $2,940.000 $2,500.000 $2,800.000 $2,000.000 $2,600.000
CLEAN EXIST CULVERTS
EA 6.000 $1,500.000 $1,050.000 $4,600.000 $1,000.000 $5,000.000 $3,000.000
REMOV STR (PIPE)
EA 26.000 $400.000 $262.500 $530.000 $250.000 $400.000 $450.000
MOBILIZATION
LS 1.000 $826,500.000 $550,000.000 $810,000.000 $659,000.000 $820,000.000 $650,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 16.000 $5,000.000 $7,000.000 $3,500.000 $7,442.000 $2,000.000 $10,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 210.000 $25.000 $35.000 $30.000 $27.000 $30.000 $30.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 1,200.000 $35.000 $38.000 $35.000 $31.000 $35.000 $35.000
ROCK FILTER DAMS (REMOVE)
LF 1,410.000 $10.000 $4.500 $9.000 $8.000 $9.000 $9.000
EARTHWORK (EROSN & SEDMT CONT, IN VEH)
CY 1,000.000 $20.000 $20.000 $18.500 $25.000 $9.000 $35.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 100.000 $75.000 $70.000 $185.000 $35.000 $55.000 $85.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 10,000.000 $2.500 $3.300 $3.100 $2.800 $3.000 $3.150
TEMP SEDMT CONT FENCE (REMOVE)
LF 10,000.000 $0.800 $1.050 $0.700 $0.600 $0.600 $0.650
TRACKHOE WORK (EROSION & SEDMT CONT)
HR 100.000 $110.000 $100.000 $250.000 $35.000 $90.000 $100.000
INTERSECTIONS (ACP)
SY 300.000 $40.000 $70.000 $58.000 $80.000 $68.000 $55.000
DRIVEWAYS (ACP)
SY 2,074.000 $35.000 $41.000 $40.000 $55.000 $45.000 $40.000
DRIVEWAYS (CONC) (HES)
SY 46.000 $100.000 $105.000 $95.000 $110.000 $116.000 $135.000
RUMBLE STRIPS (SHOULDER)
LF 67,474.000 $0.200 $0.150 $0.120 $0.170 $0.300 $0.200
RUMBLE STRIPS (CENTERLINE)
LF 33,237.000 $0.200 $0.200 $0.160 $0.170 $0.300 $0.200
MTL W-BEAM GD FEN (TIM POST)
LF 1,388.000 $22.000 $22.750 $28.000 $21.500 $30.000 $28.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 12.000 $1,600.000 $1,785.000 $1,925.000 $2,000.000 $2,000.000 $1,950.000
SHORT RADIUS
LF 25.000 $35.000 $26.250 $71.500 $25.000 $75.000 $75.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $1,200.000 $1,155.000 $1,520.000 $1,100.000 $1,600.000 $1,550.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 87.500 $70.000 $73.500 $96.500 $70.000 $105.000 $100.000
REMOVE METAL BEAM GUARD FENCE
LF 900.000 $3.000 $2.100 $6.000 $2.000 $3.000 $3.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 12.000 $310.000 $236.250 $165.000 $225.000 $175.000 $170.000
GUARDRAIL END TREATMENT (INSTALL)
EA 15.000 $2,600.000 $2,887.500 $3,330.000 $2,750.000 $3,500.000 $3,350.000
GUARDRAIL END TREATMENT (REMOVE)
EA 12.000 $300.000 $236.250 $220.000 $225.000 $230.000 $225.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 13.000 $250.000 $294.000 $360.000 $225.000 $380.000 $315.000
MAILBOX INSTALL-D (TWG-POST) TY 2
EA 3.000 $325.000 $315.000 $400.000 $270.000 $425.000 $335.000
MAILBOX INSTALL-M (TWG-POST) TY 2
EA 2.000 $500.000 $577.500 $765.000 $775.000 $800.000 $610.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 23.000 $625.000 $686.000 $900.000 $970.000 $950.000 $725.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 2.000 $700.000 $882.000 $1,085.000 $1,240.000 $1,150.000 $925.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 3.000 $1,020.000 $1,029.000 $1,600.000 $2,000.000 $1,700.000 $1,100.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 42.000 $380.000 $451.500 $485.000 $385.000 $515.000 $475.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 14.000 $500.000 $456.750 $630.000 $590.000 $665.000 $485.000
RELOCATE SM RD SN SUP&AM TY TWT
EA 3.000 $350.000 $409.500 $395.000 $2,000.000 $415.000 $435.000
REMOVE SM RD SN SUP&AM
EA 79.000 $85.000 $105.000 $103.000 $115.000 $110.000 $110.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 24.000 $30.000 $19.000 $16.500 $18.000 $18.000 $20.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 54.000 $30.000 $21.000 $33.000 $20.000 $35.000 $35.000
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
EA 58.000 $100.000 $147.000 $60.500 $34.000 $65.000 $65.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 87,780.000 $0.200 $0.190 $0.170 $0.180 $0.200 $0.170
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 40.000 $3.000 $5.250 $5.500 $5.000 $5.850 $5.500
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 79,240.000 $0.200 $0.190 $0.170 $0.180 $0.200 $0.170
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 40.000 $10.000 $5.250 $11.000 $5.000 $5.850 $11.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 3,534.000 $1.000 $1.100 $1.350 $3.000 $1.150 $2.000
WK ZN PAV MRK SHT TERM RMV (Y)(4")
LF 15,903.000 $0.400 $1.100 $1.350 $1.650 $1.450 $1.750
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
LF 295.000 $1.000 $1.050 $1.100 $1.000 $1.150 $1.100
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 888.000 $0.900 $1.000 $1.100 $0.950 $1.100 $1.100
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 3,728.000 $0.350 $0.420 $1.320 $0.400 $0.500 $1.100
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 68,494.000 $0.300 $0.390 $0.560 $0.370 $0.450 $0.550
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 2,635.000 $0.350 $0.420 $1.100 $0.400 $0.450 $1.100
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 53,824.000 $0.300 $0.390 $0.560 $0.370 $0.450 $0.550
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 1,900.000 $0.750 $3.150 $5.500 $3.000 $3.500 $5.500
REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL)
LF 768.000 $0.750 $3.150 $5.500 $3.000 $3.500 $5.500
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 300.000 $0.750 $3.150 $5.500 $3.000 $3.500 $5.500
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 230.000 $12.000 $15.750 $13.550 $15.000 $18.000 $13.500
PREFAB PAV MRK TY C (W) (LNDP ARROW)
EA 4.000 $400.000 $472.500 $358.000 $450.000 $525.000 $360.000
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 10.000 $35.000 $36.750 $71.500 $35.000 $41.000 $72.000
REFL PAV MRKR TY I-A
EA 66.000 $3.000 $4.460 $4.400 $4.250 $5.000 $4.500
REFL PAV MRKR TY I-C
EA 187.000 $3.000 $4.460 $4.400 $4.250 $5.000 $4.500
REFL PAV MRKR TY II-A-A
EA 827.000 $2.800 $4.460 $3.850 $4.250 $5.000 $3.850
D-GR HMA TY-D PG64-22
TON 101.000 $180.000 $255.000 $135.000 $173.250 $207.000 $185.000
SP MIXES SP-B PG64-22
TON 701.000 $150.000 $145.000 $120.000 $135.500 $142.000 $136.000
SP MIXES SP-C PG64-22
TON 11,669.000 $105.000 $131.000 $122.000 $135.500 $130.000 $143.000
SP MIXES SP-D PG64-22 (LEVEL-UP)
TON 3,307.000 $150.000 $150.000 $140.000 $130.250 $134.000 $155.000
SP MIXES SP-D PG70-22
TON 216.000 $150.000 $181.000 $133.000 $177.500 $167.000 $175.000
TACK COAT
GAL 6,882.000 $2.500 $4.000 $4.700 $3.000 $3.500 $4.500
PFC-C (PG76 MIX) SAC-A
TON 14,231.000 $175.000 $173.000 $157.000 $156.000 $209.550 $210.000
TACK COAT
GAL 18,975.000 $2.500 $4.000 $4.500 $3.000 $3.500 $4.500
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 28.000 $200.000 $800.000 $100.000 $200.000 $85.000 $200.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $20,000.000 $19,000.000 $15,000.000 $6,000.000 $20,000.000
PREFORMED CENTERLINE RUMBLE STRIP
LF 488.000 $8.000 $10.500 $13.000 $10.000 $11.500 $13.000
TMA (STATIONARY)
DAY 220.000 $150.000 $250.000 $150.000 $155.000 $100.000 $225.000
TMA (MOBILE OPERATION)
DAY 30.000 $150.000 $500.000 $200.000 $135.000 $150.000 $250.000
Totals: $8,429,563.200 $8,769,308.820 $8,793,990.130 $9,101,349.579 $9,671,130.900 $9,978,572.120