Show Job Controls
Bid Cobra

VAL VERDE UP0277 (6439-16-001)

Items: 60

County: VAL VERDE
Length: N/A
Highway: UP0277
District: LAREDO
Control Number: 6439-16-001
DBE Goal: N/A
Project: RMC - 643916001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $299,978.00
Date: 05/25/2023 (3 years ago)
Contract Number: N/A
Type: METAL BEAM GUARD FENCE REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (2)
E
Engineer's Estimate
$299,978.00
$295,831.00
Over/Under Est: -1.38% -$4,147.00
Over/Under Est: 15.27% $45,808.00
Amt Left: 16.89% $49,955.00

Bid Items & Bid Tabulations

60 Total 0 of 60
VAL VERDE  |  UP0277  |  LAREDO  |  6439-16-001  |  05/25/2023  |  $299,978.00  |  RMC - 643916001  |  METAL BEAM GUARD FENCE REPAIR  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ABOVE ALL CONSTRUCTION
ROSS SA ENTERPRISE LLC
REMOVING CONC (MISC)
SY 6.000 $32.000 $50.000 $10.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 10.000 $165.000 $50.000 $80.000
RIPRAP (MOW STRIP)(4 IN)
CY 5.000 $535.000 $500.000 $500.000
RETROFIT RAIL (TY PR11)
LF 25.000 $135.000 $200.000 $30.000
RETROFIT RAIL (TY PR22)
LF 10.000 $135.000 $200.000 $60.000
MOBILIZATION (CALLOUT 1)
EA 3.000 $600.000 $1.000 $1.000
MOBILIZATION (CALLOUT 2)
EA 5.000 $500.000 $1.000 $5,000.000
MOBILIZATION (CALLOUT 3)
EA 5.000 $500.000 $1.000 $5,000.000
MOBILIZATION (CALLOUT 4)
EA 3.000 $600.000 $1.000 $1,000.000
MOBILIZATION (EMERGENCY)
EA 2.000 $1,000.000 $500.000 $600.000
ONE-WAY TRAF CONT (PILOT CAR)
HR 10.000 $75.000 $100.000 $100.000
MTL W-BEAM GD FEN (TIM POST)
LF 250.000 $28.000 $30.000 $25.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 4.000 $1,700.000 $2,200.000 $1,000.000
MTL BM GD FEN (LONG SPAN SYSTEM)
LF 50.000 $55.000 $40.000 $22.000
MTL BM GD FEN TRANS (31"-28")
EA 8.000 $545.000 $400.000 $400.000
REMOVE METAL BEAM GUARD FENCE
LF 100.000 $5.000 $10.000 $20.000
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $240.000 $300.000 $150.000
GDRAIL END TRT(INST)(WOOD POST)(TY III)
EA 2.000 $3,000.000 $3,500.000 $4,000.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 15.000 $28.000 $25.000 $10.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 40.000 $28.000 $25.000 $10.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 15.000 $28.000 $25.000 $11.000
REPAIR RAIL ELEMENT (W - BEAM)
LF 2,200.000 $20.000 $23.000 $20.000
REPAIR RAIL ELEMENT (THRIE - BEAM)
LF 30.000 $35.000 $60.000 $10.000
REP RAIL ELMNT(THRIE-BM TRANS TO W -BM)
LF 6.000 $45.000 $60.000 $20.000
REPAIR RAIL ELEMENT (CURVED RAIL)
LF 100.000 $30.000 $50.000 $80.000
RAISE RAIL ELEMENT
LF 120.000 $7.000 $6.000 $6.000
REM / REPL TIMBER/STL POST W/O CONC FND
EA 170.000 $50.000 $50.000 $1.000
REM / REPL TIMBER / STL POST W/CONC FND
EA 35.000 $90.000 $75.000 $10.000
REALIGN POSTS
EA 70.000 $20.000 $25.000 $10.000
INSTALL BLOCKOUT (TYPE SPECIFIED)
EA 25.000 $20.000 $50.000 $50.000
REMOVE & REPLACE BLOCKOUT
EA 175.000 $23.000 $30.000 $20.000
REPLACE SINGLE GDRAIL TERMINAL RAIL
LF 300.000 $30.000 $30.000 $25.000
REPLACE SINGLE GDRAIL TERMINAL POST
EA 50.000 $68.000 $100.000 $60.000
REPAIR OF TERMINAL ANCHORS POSTS
EA 2.000 $68.000 $100.000 $60.000
REMOVE GDRAIL END TRT / REPL WITH SGT
EA 30.000 $3,550.000 $3,500.000 $4,950.000
REPL SINGLE GDRAIL TERM IMPACT HEAD
EA 12.000 $1,000.000 $900.000 $1,000.000
REM & RESET SGT IMPACT HEAD
EA 5.000 $400.000 $250.000 $300.000
REPLACE SGT CABLE ASSEMBLY
EA 12.000 $100.000 $100.000 $1.000
REPLACE SGT CABLE ANCHOR
EA 12.000 $100.000 $100.000 $1.000
REPLACE SGT STRUT
EA 12.000 $100.000 $100.000 $1.000
REPLACE SGT OBJECT MARKER
EA 12.000 $100.000 $50.000 $1.000
REPAIR STEEL POST WITH BASE PLATE
EA 2.000 $250.000 $250.000 $300.000
REPAIR MTL BM GD FEN(LONG SPAN SYS)
LF 25.000 $30.000 $40.000 $10.000
REPLACE POSTS (TL-3)
EA 35.000 $255.000 $200.000 $150.000
CABLE SPLICE / TURNBUCKLE (TL-3)
EA 2.000 $255.000 $250.000 $100.000
REPR OR REPLC CABLE BARR TERM SEC(TL-3)
EA 2.000 $1,700.000 $2,000.000 $5,300.000
REPLACE CABLE (TL-3)
LF 20.000 $10.000 $7.000 $8.000
CHECK / RE-TENSION CABLE
EA 5.000 $450.000 $200.000 $100.000
REPLACE POST HARDWARE (TL-3)
EA 5.000 $50.000 $40.000 $100.000
POST AND CABLE FENCE (NEW INSTALLATION)
LF 20.000 $20.000 $30.000 $20.000
POST AND CABLE FENCE (REPAIR)
LF 50.000 $15.000 $15.000 $10.000
REPAIR (REACT)
EA 1.000 $3,000.000 $4,000.000 $500.000
REPAIR (BEAT - SSCC)
EA 1.000 $2,900.000 $5,000.000 $500.000
REPAIR (STL PIPE PEDESTRIAN RAIL - PR1)
LF 20.000 $140.000 $250.000 $25.000
REP METAL POST W/ BASE PLATE(T101 RAIL)
EA 3.000 $250.000 $250.000 $150.000
REPAIR (W-BEAM - T101 RAIL)
LF 50.000 $50.000 $40.000 $60.000
REP METAL PST W/ BASE PLATE (TY T631)
EA 15.000 $200.000 $250.000 $100.000
CONCRETE RAIL REPAIR (IN-KIND)
LF 10.000 $350.000 $100.000 $150.000
CONCRETE RAIL REPLACEMENT (IN-KIND)
LF 5.000 $500.000 $100.000 $250.000
TMA (STATIONARY)
DAY 70.000 $80.000 $1.000 $1.000
Totals: $299,978.000 $295,831.000 $345,786.000