VAL VERDE US0277 (6352-67-001)

Items: 31

County: VAL VERDE
Length: N/A
Highway: US0277
District: LAREDO
Control Number: 6352-67-001
DBE Goal: N/A
Project: BPM - 635267001
Guaranty: N/A
Time: 90 W
Engineer's Estimate: $426,507.00
Date: 01/10/2020 (6 years ago)
Contract Number: N/A
Type: REHAB OF VARIOUS BRIDGE FACILITIES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$426,507.00
$508,480.00
Over/Under Est: 19.22% $81,973.00
Over/Under Est: 20.75% $88,493.00
Amt Left: 1.28% $6,520.00
Over/Under Est: 47.92% $204,389.00
Amt Left: 24.07% $122,416.00
Delta: -22.50% -$115,896.00
Over/Under Est: 65.21% $278,138.32
Amt Left: 38.58% $196,165.32
Delta: -11.69% -$73,749.32
Over/Under Est: 134.24% $572,523.00
Amt Left: 96.47% $490,550.00
Delta: -41.78% -$294,384.68

Bid Items & Bid Tabulations

31 Total 0 of 31
VAL VERDE  |  US0277  |  LAREDO  |  6352-67-001  |  01/10/2020  |  $426,507.00  |  BPM - 635267001  |  REHAB OF VARIOUS BRIDGE FACILITIES  |  90 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
CHAMPION INFRASTRUCTURE, LLC
SJ&J CONSTRUCTION, LLC
VECTOR UTILITIES LLC
ACME BRIDGE COMPANY, INC.
ALLEN KELLER COMPANY
PREPARING ROW
STA 13.000 $1,200.000 $1,500.000 $800.000 $2,000.000 $1,580.000 $5,400.000
PREPARING ROW(TREE)(5" TO 12" DIA)
EA 43.000 $300.000 $400.000 $300.000 $600.000 $1,100.000 $1,700.000
REMOVE CONC (WINGWALL)
CY 2.000 $500.000 $2,500.000 $500.000 $250.000 $1,580.000 $2,500.000
EMBANKMENT (FINAL)(ORD COMP)(TY A)
CY 224.000 $30.000 $32.000 $32.000 $45.000 $84.100 $150.000
BLADING
HR 24.000 $120.000 $140.000 $100.000 $185.000 $3,180.000 $550.000
FLOWABLE BACKFILL
CY 136.500 $210.000 $450.000 $250.000 $275.000 $368.000 $760.000
CL C CONC (COLUMN ENCASEMENT)
CY 12.500 $4,400.000 $2,800.000 $3,000.000 $985.000 $1,580.000 $3,200.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 198.600 $160.000 $145.000 $160.000 $375.000 $158.000 $270.000
RIPRAP (CONC)(CL B)(5 IN)
CY 0.500 $500.000 $1,600.000 $1,000.000 $800.000 $2,103.060 $4,000.000
RIPRAP (STONE TY R)(GROUT)(8 IN)
CY 79.000 $700.000 $190.000 $350.000 $205.000 $789.000 $700.000
RIPRAP (STONE TY F)(GROUT)(8 IN)
CY 1.000 $800.000 $2,100.000 $500.000 $225.000 $1,260.000 $3,500.000
ANCHOR BOLTS
EA 36.000 $75.000 $160.000 $70.000 $880.000 $52.600 $61.000
GABION MATTRESSES (GALV)(12 IN)
SY 536.000 $70.000 $160.000 $135.000 $148.000 $131.000 $220.000
WINGWALL (FW - 0) (HW=5 FT)
EA 0.500 $14,000.000 $6,500.000 $12,000.000 $12,500.000 $6,309.180 $22,000.000
CLEAN EXIST CULVERTS
EA 3.000 $1,000.000 $3,200.000 $1,000.000 $2,500.000 $1,580.000 $10,000.000
MOBILIZATION
LS 1.000 $35,588.000 $45,000.000 $145,805.000 $57,200.000 $70,000.000 $95,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $3,500.000 $4,500.000 $4,000.000 $6,500.000 $8,000.000 $10,100.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 562.000 $25.000 $50.000 $20.000 $90.000 $68.400 $90.000
ROCK FILTER DAMS (REMOVE)
LF 562.000 $8.000 $10.000 $8.000 $25.000 $21.000 $30.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 624.000 $35.000 $30.000 $12.000 $42.000 $18.900 $25.000
CONSTRUCTION EXITS (REMOVE)
SY 624.000 $8.000 $10.000 $8.000 $15.000 $2.100 $3.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 16.000 $70.000 $150.000 $80.000 $165.000 $52.600 $270.000
SANDBAGS FOR EROSION CONTROL (12")
LF 20.000 $14.000 $10.000 $5.000 $15.000 $21.000 $30.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 320.000 $5.000 $4.000 $3.500 $3.500 $6.300 $9.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 320.000 $1.000 $2.000 $1.500 $1.000 $4.200 $5.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 20.000 $8.000 $10.000 $10.000 $8.500 $5.300 $7.000
CONC CURB (MONO) (TY II)
LF 10.000 $50.000 $120.000 $60.000 $15.000 $131.000 $390.000
DITCH CLEAN / RESHAPING(CU YD IN PLACE)
CY 50.000 $100.000 $60.000 $50.000 $20.000 $52.600 $140.000
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 155.000 $70.000 $90.000 $60.000 $205.000 $263.000 $200.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $9,000.000 $7,000.000 $12,000.000 $9,000.000 $10,500.000 $16,000.000
TMA (STATIONARY)
DAY 58.000 $200.000 $400.000 $200.000 $350.000 $150.000 $350.000
Totals: $426,507.000 $508,480.000 $515,000.000 $630,896.000 $704,645.320 $999,030.000