VAL VERDE US 90 (0022-09-056)

Items: 17

County: VAL VERDE
Length: 0.8210 MILES
Highway: US 90
District: LAREDO
Control Number: 0022-09-056
DBE Goal: 0.0%
Project: STP 2026(177)HES
Guaranty: $12,000.00
Time: 45 WORKING DAYS
Engineer's Estimate: $576,948.57
Date: 12/03/2025 (6 months ago)
Contract Number: 12253228
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00206655
Contract Type: Federal
Project Description: US 90 SAFETY ILLUNINATION INCLUDE OFF-RAMPS
Mail/Deliver Bids To: N/A
JOSE TOVIASTORRES
ANGEL MARTINEZ
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$576,948.57
$571,506.10
Over/Under Est: -0.94% -$5,442.47
Over/Under Est: 1.31% $7,538.18
Amt Left: 2.27% $12,980.65
Over/Under Est: 15.59% $89,974.05
Amt Left: 16.7% $95,416.52
Delta: -14.10% -$82,435.87
Over/Under Est: 28.51% $164,512.88
Amt Left: 29.74% $169,955.35
Delta: -11.18% -$74,538.83

Bid Items & Bid Tabulations

17 Total 0 of 17
VAL VERDE  |  US 90  |  LAREDO  |  0022-09-056  |  12/03/2025  |  $576,948.57  |  STP 2026(177)HES  |  HAZARD ELIM & SAFETY  |  45 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
STRUCTURAL INTEGRITY GROUP LLC
TRIPLE H FIELD SERVICES, LLC
THE LEVY COMPANY, LLC
E-Z BEL CONSTRUCTION, LLC
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 328.000 $340.000 $260.000 $420.000 $308.610 $500.000
RIPRAP (CONC)(CL B)
CY 14.350 $515.000 $1,131.000 $480.000 $2,289.870 $1,100.000
MOBILIZATION
LS 1.000 $49,952.480 $50,000.000 $36,000.000 $66,692.260 $70,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $4,643.750 $9,118.000 $3,500.000 $10,698.040 $1,600.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $11,628.570 $2,475.000 $3,000.000 $3,035.630 $1,450.000
TMA (STATIONARY)
DAY 90.000 $123.450 $100.000 $150.000 $69.160 $350.000
IN RD IL (U/P) (TY 2) (150W EQ) LED
EA 4.000 $1,600.000 $1,105.000 $2,000.000 $2,046.220 $2,700.000
IN RD IL (TY SA) 40T-8 (250W EQ) LED
EA 41.000 $3,700.000 $4,417.000 $4,000.000 $4,959.400 $5,350.000
CONDT (PVC) (SCH 40) (2")
LF 7,080.000 $13.000 $11.260 $13.000 $11.340 $11.250
CONDT (PVC) (SCH 80) (2") (BORE)
LF 1,315.000 $29.670 $27.690 $25.000 $32.540 $38.800
CONDT (RM) (1 1/4")
LF 215.000 $37.000 $40.090 $28.000 $31.930 $41.300
ELEC CONDR (NO.10) BARE
LF 195.000 $1.500 $1.880 $1.800 $1.870 $1.620
ELEC CONDR (NO.10) INSULATED
LF 390.000 $1.500 $1.950 $1.850 $1.810 $1.720
ELEC CONDR (NO.8) BARE
LF 8,415.000 $1.670 $1.430 $1.900 $2.150 $1.950
ELEC CONDR (NO.8) INSULATED
LF 16,945.000 $1.830 $1.560 $1.950 $1.760 $2.200
GROUND BOX TY C (162911)W/APRON
EA 6.000 $1,056.000 $1,392.000 $1,300.000 $1,769.120 $1,350.000
ELC SRV TY A 120/240 060(NS)SS(E)SP(O)
EA 2.000 $5,200.000 $10,238.000 $6,500.000 $10,346.810 $10,000.000
Totals: $576,948.570 $571,506.100 $584,486.750 $666,922.624 $741,461.450