UVALDE SH0055 (6411-75-001)
Items: 18
County: UVALDE
Length: N/A
Highway: SH0055
District: SAN ANTONIO
Control Number: 6411-75-001
DBE Goal: N/A
Project: BPM - 641175001
Guaranty: N/A
Time: 16 W
Engineer's Estimate: $111,697.08
Date: 12/14/2022 (3 years ago)
Contract Number: N/A
Type: EROSION REPAIR
Mail/Deliver Bids To: N/A
HENRY FOJTIK
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$111,697.08 | |||
| $108,840.00 |
-2.56%
-$2,857.08
|
|||
| $117,200.00 |
4.93%
$5,502.92
|
7.68%
$8,360.00
|
||
| $125,894.00 |
12.71%
$14,196.92
|
15.67%
$17,054.00
|
-7.42%
-$8,694.00
|
|
| $127,901.00 |
14.51%
$16,203.92
|
17.51%
$19,061.00
|
-1.59%
-$2,007.00
|
|
| $141,148.00 |
26.37%
$29,450.92
|
29.68%
$32,308.00
|
-10.36%
-$13,247.00
|
|
| $148,010.00 |
32.51%
$36,312.92
|
35.99%
$39,170.00
|
-4.86%
-$6,862.00
|
|
| $150,710.00 |
34.93%
$39,012.92
|
38.47%
$41,870.00
|
-1.82%
-$2,700.00
|
|
| $176,510.00 |
58.03%
$64,812.92
|
62.17%
$67,670.00
|
-17.12%
-$25,800.00
|
E
Engineer's Estimate
$111,697.08
1
Awarded
$108,840.00
Over/Under Est:
-2.56%
-$2,857.08
$117,200.00
Over/Under Est:
4.93%
$5,502.92
Amt Left:
7.68%
$8,360.00
$125,894.00
Over/Under Est:
12.71%
$14,196.92
Amt Left:
15.67%
$17,054.00
Delta:
-7.42%
-$8,694.00
$127,901.00
Over/Under Est:
14.51%
$16,203.92
Amt Left:
17.51%
$19,061.00
Delta:
-1.59%
-$2,007.00
$141,148.00
Over/Under Est:
26.37%
$29,450.92
Amt Left:
29.68%
$32,308.00
Delta:
-10.36%
-$13,247.00
$148,010.00
Over/Under Est:
32.51%
$36,312.92
Amt Left:
35.99%
$39,170.00
Delta:
-4.86%
-$6,862.00
$150,710.00
Over/Under Est:
34.93%
$39,012.92
Amt Left:
38.47%
$41,870.00
Delta:
-1.82%
-$2,700.00
$176,510.00
Over/Under Est:
58.03%
$64,812.92
Amt Left:
62.17%
$67,670.00
Delta:
-17.12%
-$25,800.00
Bid Items & Bid Tabulations
18
Total
0 of 18