UPTON US 385 (0229-04-060)
Items: 57
County: UPTON
Length: N/A
Highway: US 385
District: ODESSA
Control Number: 0229-04-060
DBE Goal: N/A
Project: F 2022(979)
Guaranty: N/A
Time: 120 WORKING DAYS
Engineer's Estimate: $5,194,897.98
Date: 01/05/2023 (3 years ago)
Contract Number: N/A
Type: ROADWAY REHABILITATION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (2)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$5,194,897.98 | |||
| $5,995,947.22 |
15.42%
$801,049.24
|
|||
| $8,039,555.81 |
54.76%
$2,844,657.83
|
34.08%
$2,043,608.59
|
E
Engineer's Estimate
$5,194,897.98
$5,995,947.22
Over/Under Est:
15.42%
$801,049.24
$8,039,555.81
Over/Under Est:
54.76%
$2,844,657.83
Amt Left:
34.08%
$2,043,608.59
| Subcontractor | Percentage | Amount |
|---|---|---|
| BOLER EQUIPMENT SERVICE, INC | 14.74% | $881,893.76 |
| A L CONCRETE CONSTRUCTION, LLC | 10.99% | $657,531.37 |
| DOUBLE A CONTRACTING, L.P. | 2.01% | $120,258.24 |
| TEXOP CONSTRUCTION | 1.68% | $100,514.35 |
| CONTRACTORS SERVICE, LTD. | 1.20% | $71,795.96 |
| DK CONTRACTING, LLC | 0.75% | $44,872.48 |
| R.E.B.D. TRUCKING LLC | 0.01% | $598.30 |
| Total: | 31.38% | $1,877,464.46 |
Bid Items & Bid Tabulations
57
Total
0 of 57