Show Job Controls
Bid Cobra

TYLER FM 1632 (2782-01-013)

Items: 35

County: TYLER
Length: N/A
Highway: FM 1632
District: BEAUMONT
Control Number: 2782-01-013
DBE Goal: N/A
Project: C 2782-1-13
Guaranty: N/A
Time: 129 WORKING DAYS
Engineer's Estimate: $4,524,468.30
Date: 06/02/2023 (3 years ago)
Contract Number: N/A
Type: SURFACING/ROADWAY RESTORATION
Mail/Deliver Bids To: N/A
DAVE COLLINS
TAYLOR KANE
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$4,524,468.30
$5,136,533.23
Over/Under Est: 13.53% $612,064.93
Over/Under Est: 34.82% $1,575,329.28
Amt Left: 18.75% $963,264.35
Subcontractor Percentage Amount
TEXAS MATERIALS GROUP, INC. 36.54% $1,876,889.25
STRIPING TECHNOLOGY, L.P. 2.68% $137,659.09
TEXOP CONSTRUCTION 1.90% $97,594.13
A R BROTHERS CONSTRUCTION SERVICES, INC. 0.93% $47,769.76
SOUTHWEST ENVIRONMENT SERVICES LLC 0.46% $23,628.05
PANOLA SIGN & BARRICADE, INC. 0.45% $23,114.40
WEST TEXAS ROCK RESOURCES, LLC 0.22% $11,300.37
AT STAFFING 0.00% $0.00
Total: 43.18% $2,217,955.05

Bid Items & Bid Tabulations

35 Total 0 of 35
TYLER  |  FM 1632  |  BEAUMONT  |  2782-01-013  |  06/02/2023  |  $4,524,468.30  |  C 2782-1-13  |  SURF/ROADWAY RESTOR  |  129 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
PINTO CONSTRUCTION CO., INC.
TEXAS MATERIALS GROUP, INC.
SUBGRADE WIDENING (ORD COMP)
STA 273.100 $1,000.000 $301.260 $778.210
BACKFILL (TY A OR B)
STA 273.100 $500.000 $496.210 $1,075.420
BLADING
HR 85.000 $175.000 $231.620 $708.310
CELL FBR MLCH SEED(PERM)(URBAN)(SANDY)
SY 18,206.000 $0.750 $0.440 $0.440
VEGETATIVE WATERING
MG 153.140 $20.000 $0.010 $156.610
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 7,140.000 $90.000 $129.870 $186.990
REWORK BS MTL (TY C) (8") (ORD COMP)
STA 273.100 $500.000 $923.970 $948.140
CEMENT
TON 1,058.000 $250.000 $262.550 $287.640
CEMENT TREAT (MX EXST MTL & NW BS)(8")
SY 84,964.000 $7.500 $5.000 $6.290
PRIME COAT (RC-250)
GAL 16,993.000 $15.000 $5.390 $6.310
AGGR (TY-B GR-5 OR TY-L GR-5)
CY 680.000 $150.000 $174.720 $191.520
PLANE ASPH CONC PAV(0" TO 2")
SY 624.000 $25.000 $42.350 $38.500
SET (REMOV & REINSTALL)
EA 2.000 $1,000.000 $1,534.420 $6,600.000
MOBILIZATION
LS 1.000 $293,020.000 $513,000.000 $575,643.240
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $3,500.000 $3,000.000 $25,598.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,700.000 $6.000 $9.350 $7.150
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,700.000 $1.500 $1.380 $1.650
INTRSCT, DRVWAYS, & TURNOUT (ACP)
SY 156.000 $70.000 $174.640 $126.780
DRIVEWAYS (BASE)
SY 923.000 $50.000 $41.470 $91.640
RUMBLE STRIPS (SHOULDER)
LF 54,620.000 $0.250 $0.160 $0.150
RUMBLE STRIPS (CENTERLINE)
LF 27,310.000 $0.180 $0.160 $0.150
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 53,420.000 $1.000 $0.550 $0.500
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 22.000 $2.500 $11.000 $9.900
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 3,400.000 $0.180 $0.550 $0.500
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 38,515.000 $0.180 $0.550 $0.790
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 3,984.000 $1.000 $5.280 $3.720
RE PM W/RET REQ TY I (W)6"(SLD)(090MIL)
LF 53,420.000 $0.500 $0.990 $0.680
RE PM W/RET REQ TY I (Y)6"(BRK)(090MIL)
LF 3,400.000 $0.500 $1.100 $0.720
RE PM W/RET REQ TY I (Y)6"(SLD)(090MIL)
LF 38,515.000 $0.300 $0.990 $0.680
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 22.000 $12.000 $27.500 $16.500
REFL PAV MRKR TY II-A-A
EA 660.000 $4.500 $5.500 $6.050
SP MIXES SP-C SAC-A PG76-22
TON 9,601.000 $150.000 $197.990 $174.500
TACK COAT
GAL 5,098.000 $6.000 $5.780 $5.260
TMA (STATIONARY)
DAY 80.000 $350.000 $350.000 $123.570
TMA (MOBILE OPERATION)
DAY 20.000 $400.000 $50.000 $49.430
Totals: $4,524,468.300 $5,136,533.245 $6,099,797.592