TYLER VA (0920-13-040)

Items: 26

County: TYLER
Length: N/A
Highway: VA
District: BEAUMONT
Control Number: 0920-13-040
DBE Goal: N/A
Project: STP 2023(148)TAPS
Guaranty: N/A
Time: 22 WORKING DAYS
Engineer's Estimate: $257,263.58
Date: 06/02/2023 (3 years ago)
Contract Number: N/A
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Mail/Deliver Bids To: N/A
DAVE COLLINS
TAYLOR KANE
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$257,263.58
$262,629.95
Over/Under Est: 2.09% $5,366.37
Over/Under Est: 15.04% $38,688.42
Amt Left: 12.69% $33,322.05
Over/Under Est: 40.45% $104,061.83
Amt Left: 37.58% $98,695.46
Delta: -22.09% -$65,373.41
Subcontractor Percentage Amount
FLEX SUPPLY, LLC 3.10% $8,141.53
HIGHWAY 1 LLC 1.36% $3,571.77
Total: 4.46% $11,713.30

Bid Items & Bid Tabulations

26 Total 0 of 26
TYLER  |  VA  |  BEAUMONT  |  0920-13-040  |  06/02/2023  |  $257,263.58  |  STP 2023(148)TAPS  |  CONSTRUCT PEDESTRIAN INFRASTRUCT  |  22 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TI-ZACK CONCRETE, INC.
FNH CONSTRUCTION, LLC
PROJECT ALLIED RESOURCES, LLC
EXCAVATION (SPECIAL)
CY 49.330 $55.000 $55.000 $100.000 $49.800
EMBANKMENT (FINAL)(ORD COMP)(TY D)
CY 72.990 $41.750 $55.000 $100.000 $102.000
BLOCK SODDING
SY 971.000 $4.600 $10.000 $10.000 $17.900
VEGETATIVE WATERING
MG 3.350 $20.000 $1.000 $500.000 $63.000
ADJUSTING MANHOLES
EA 2.000 $2,200.000 $550.000 $5,000.000 $2,360.000
MOBILIZATION
LS 1.000 $49,000.000 $25,000.000 $30,000.000 $37,300.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $7,000.000 $1,500.000 $8,500.000 $3,430.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 215.000 $4.600 $1.000 $4.000 $9.200
TEMP SEDMT CONT FENCE (REMOVE)
LF 215.000 $2.320 $1.000 $2.000 $2.590
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 100.000 $5.800 $1.000 $18.000 $12.900
BIODEG EROSN CONT LOGS (REMOVE)
LF 100.000 $1.550 $1.000 $9.000 $3.770
CONC CURB (TY I)
LF 131.000 $21.500 $55.000 $60.000 $31.000
INTERSECTIONS (CONC)
SY 220.000 $150.000 $220.000 $150.000 $215.000
DRIVEWAYS (CONC)
SY 209.000 $115.000 $180.000 $150.000 $177.000
DRIVEWAYS (ACP)
SY 410.000 $35.000 $100.000 $65.000 $111.000
CONC SIDEWALKS (6")
SY 293.000 $115.000 $180.000 $85.000 $177.000
CURB RAMPS (TY 7)
SY 70.000 $160.000 $180.000 $400.000 $432.000
CURB RAMPS (TY 10)
SY 28.000 $160.000 $180.000 $400.000 $432.000
CURB RAMPS (TY 21)
SY 11.000 $740.000 $180.000 $400.000 $432.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 4.000 $630.000 $500.000 $1,500.000 $1,510.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 2.000 $1,155.000 $500.000 $1,500.000 $2,090.000
IN SM RD SN SUP&AM TYS80(1)SB(U-BM)
EA 1.000 $1,155.000 $500.000 $1,500.000 $2,090.000
REMOVE SM RD SN SUP&AM
EA 7.000 $105.000 $500.000 $100.000 $255.000
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 114.000 $14.300 $25.000 $20.000 $33.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $15,615.000 $1.000 $12,500.000 $8,110.000
TMA (STATIONARY)
DAY 22.000 $275.000 $1.000 $250.000 $630.000
Totals: $257,263.582 $262,629.950 $295,952.000 $361,325.414