Show Job Controls
Bid Cobra

TYLER CR (0920-13-036)

Items: 34

County: TYLER
Length: N/A
Highway: CR
District: BEAUMONT
Control Number: 0920-13-036
DBE Goal: N/A
Project: BR 1902(442)
Guaranty: N/A
Time: 66 WORKING DAYS
Engineer's Estimate: $649,658.16
Date: 06/29/2022 (3 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$649,658.16
$659,766.00
Over/Under Est: 1.56% $10,107.84
Over/Under Est: 22.64% $147,069.34
Amt Left: 20.76% $136,961.50
Over/Under Est: 42.89% $278,617.64
Amt Left: 40.7% $268,509.80
Delta: -16.51% -$131,548.30

Bid Items & Bid Tabulations

34 Total 0 of 34
TYLER  |  CR  |  BEAUMONT  |  0920-13-036  |  06/29/2022  |  $649,658.16  |  BR 1902(442)  |  BRIDGE REPL  |  66 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CROSS PLUS CONSTRUCTION, LLC
DREWERY CONSTRUCTION COMPANY, INCORPORATED
TEXAS MATERIALS GROUP, INC.
PREPARING ROW (TREE) (6" TO 24" DIA)
EA 5.000 $2,380.000 $1,650.000 $9,000.000 $16,400.000
EXCAVATION (ROADWAY)
CY 265.000 $23.000 $11.000 $52.000 $22.000
SUBGRADE WIDENING (ORD COMP)
STA 2.000 $800.000 $5,500.000 $3,200.000 $3,400.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 264.000 $50.000 $66.000 $73.000 $61.000
EMBANKMENT (FINAL)(ORD COMP)(TY D)
CY 265.000 $50.000 $33.000 $47.000 $62.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 672.000 $0.180 $1.000 $3.000 $2.100
BROADCAST SEED (TEMP) (WARM)
SY 336.000 $0.100 $1.000 $3.500 $3.550
BROADCAST SEED (TEMP) (COOL)
SY 336.000 $0.100 $1.000 $3.500 $3.550
VEGETATIVE WATERING
MG 6.000 $20.000 $110.000 $190.000 $111.000
PROOF ROLLING
HR 10.000 $100.000 $275.000 $130.000 $100.000
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 173.000 $210.000 $83.000 $195.000 $200.000
PRIME COAT (AE-P)
GAL 248.000 $22.000 $11.000 $9.000 $9.000
CEM STABIL BKFL
CY 33.000 $230.000 $330.000 $210.000 $250.000
PRESTR CONC PIL (18 IN SQ)
LF 381.000 $168.000 $72.000 $130.000 $210.000
CL C CONC (ABUT)
CY 18.400 $2,000.000 $2,750.000 $1,200.000 $2,900.000
REINF CONC SLAB (SLAB BEAM)
SF 1,300.000 $30.000 $55.000 $25.000 $84.000
APPROACH SLAB
CY 19.000 $800.000 $550.000 $1,500.000 $1,300.000
PRESTR CONC SLAB BEAM (5SB15)
LF 247.500 $250.000 $330.000 $357.000 $330.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 394.000 $200.000 $220.000 $170.000 $204.000
RAIL (TY T223)
LF 124.000 $160.000 $275.000 $137.000 $287.000
ARMOR JOINT
LF 44.000 $120.000 $248.000 $158.000 $130.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $35,000.000 $16,500.000 $21,000.000 $59,000.000
MOBILIZATION
LS 1.000 $83,000.000 $71,500.000 $223,000.000 $102,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $3,000.000 $3,300.000 $2,600.000 $3,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 50.000 $60.000 $110.000 $58.000 $56.000
ROCK FILTER DAMS (REMOVE)
LF 50.000 $16.000 $11.000 $11.000 $11.000
MTL W-BEAM GD FEN (TIM POST)
LF 100.000 $40.000 $110.000 $38.000 $37.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,250.000 $3,300.000 $3,600.000 $2,250.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,000.000 $3,850.000 $3,300.000 $3,150.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 8.000 $21.000 $28.000 $16.000 $43.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 8.000 $28.000 $28.000 $30.000 $63.000
TACK COAT
GAL 124.000 $16.000 $6.000 $10.000 $10.000
D-GR HMA TY-D PG 64-22 (EXEMPT)
TON 137.000 $350.000 $330.000 $210.000 $300.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $4,400.000 $8,000.000 $14,800.000
Totals: $649,658.160 $659,766.000 $796,727.500 $928,275.800