TYLER CR (0920-13-034)

Items: 27

County: TYLER
Length: N/A
Highway: CR
District: BEAUMONT
Control Number: 0920-13-034
DBE Goal: N/A
Project: BR 2020(409)
Guaranty: N/A
Time: 60 WORKING DAYS
Engineer's Estimate: $335,544.50
Date: 03/04/2022 (4 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (3)
E
Engineer's Estimate
$335,544.50
Over/Under Est: 48.62% $163,131.00
Over/Under Est: 91.52% $307,074.90
Amt Left: 28.87% $143,943.90
Over/Under Est: 160.75% $539,386.50
Amt Left: 75.45% $376,255.50
Delta: -36.15% -$232,311.60

Bid Items & Bid Tabulations

27 Total 0 of 27
TYLER  |  CR  |  BEAUMONT  |  0920-13-034  |  03/04/2022  |  $335,544.50  |  BR 2020(409)  |  BRIDGE REPL  |  60 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DREWERY CONSTRUCTION COMPANY, INCORPORATED
PROJECT ALLIED RESOURCES, LLC
TEXAS MATERIALS GROUP, INC.
PREPARING ROW (TREE) (6" TO 24" DIA)
EA 5.000 $1,700.000 $3,000.000 $2,250.000 $2,000.000
EXCAVATION (ROADWAY)
CY 190.000 $16.000 $28.000 $29.600 $40.000
SUBGRADE WIDENING (ORD COMP)
STA 2.000 $305.000 $1,200.000 $2,240.000 $2,225.000
EMBANKMENT (FINAL)(ORD COMP)(TY D)
CY 149.000 $22.000 $30.000 $47.100 $92.000
PROOF ROLLING
HR 10.000 $92.000 $125.000 $184.000 $95.000
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 103.000 $150.000 $195.000 $218.000 $275.000
CEM STABIL BKFL
CY 25.000 $165.000 $210.000 $276.000 $355.000
PRESTR CONC PIL (18 IN SQ)
LF 366.000 $120.000 $130.000 $282.000 $260.000
CL C CONC (ABUT)
CY 18.400 $950.000 $1,000.000 $2,160.000 $3,430.000
REINF CONC SLAB (SLAB BEAM)
SF 1,300.000 $18.000 $25.000 $37.300 $95.000
APPROACH SLAB
CY 38.500 $620.000 $650.000 $834.000 $1,600.000
PRESTR CONC SLAB BEAM (5SB15)
LF 247.500 $185.000 $291.000 $397.000 $440.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 269.000 $130.000 $175.000 $226.000 $225.000
RAIL (TY T223)
LF 124.000 $105.000 $130.000 $203.000 $325.000
ARMOR JOINT
LF 44.000 $70.000 $142.000 $168.000 $300.000
RC PIPE (CL III)(24 IN)
LF 20.000 $80.000 $142.000 $236.000 $295.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $20,000.000 $21,000.000 $25,000.000 $92,500.000
MOBILIZATION
LS 1.000 $27,000.000 $101,000.000 $57,000.000 $80,200.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $1,500.000 $1,700.000 $3,610.000 $3,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 50.000 $35.000 $53.000 $75.000 $90.000
ROCK FILTER DAMS (REMOVE)
LF 50.000 $15.000 $16.000 $17.700 $30.000
MTL W-BEAM GD FEN (TIM POST)
LF 50.000 $29.000 $40.000 $49.200 $38.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,600.000 $3,400.000 $2,580.000 $2,100.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,700.000 $3,200.000 $3,700.000 $3,100.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 8.000 $15.000 $16.000 $33.500 $15.250
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 8.000 $28.000 $39.000 $55.000 $38.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $9,000.000 $8,000.000 $16,900.000 $7,500.000
Totals: $335,544.500 $498,675.500 $642,619.400 $874,931.000