Show Job Controls
Bid Cobra

TYLER US 190 (0213-06-044)

Items: 32

County: TYLER
Length: N/A
Highway: US 190
District: BEAUMONT
Control Number: 0213-06-044
DBE Goal: N/A
Project: STP 2020(020)
Guaranty: N/A
Time: 60 WORKING DAYS
Engineer's Estimate: $11,079,889.15
Date: 09/05/2019 (6 years ago)
Contract Number: N/A
Type: SEAL COAT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (1)
E
Engineer's Estimate
$11,079,889.15
$12,309,357.08
Over/Under Est: 11.1% $1,229,467.93

Bid Items & Bid Tabulations

32 Total 0 of 32
TYLER  |  US 190  |  BEAUMONT  |  0213-06-044  |  09/05/2019  |  $11,079,889.15  |  STP 2020(020)  |  SEAL COAT  |  60 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CLARK CONSTRUCTION OF TEXAS, INC.
ASPH (TIER I)
TON 4,161.000 $700.000 $690.000
ASPH (TIER II)
TON 1,659.000 $700.000 $690.000
AGGR (TY-PD GR-4 OR TY-PL GR-4)(SAC-B)
CY 8,026.000 $150.000 $155.000
AGGR (TY-PB GR-4 OR TY-PL GR-4 SAC-A)
CY 19,578.000 $150.000 $155.000
AGGR (TY-PD GR-5 OR TY-PL GR-5)(SAC-B)
CY 2,116.000 $160.000 $165.000
MOBILIZATION
LS 1.000 $1,000,000.000 $1,550,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $7,500.000 $12,500.000
INTERSECTIONS (SURF TREAT)
SY 40,785.000 $4.500 $3.990
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 6,343.000 $1.250 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 28,062.000 $1.250 $1.000
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 280.000 $1.100 $3.250
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 15,743.000 $1.100 $0.850
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 47,360.000 $0.350 $0.430
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 1,725,041.000 $0.350 $0.430
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 185,630.000 $0.350 $0.430
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 942,535.000 $0.350 $0.430
PREFAB PAV MRK TY C (W) (12") (SLD)
LF 377.000 $7.500 $7.000
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 5,756.000 $10.000 $13.500
PREFAB PAV MRK TY C (W) (ARROW)
EA 61.000 $350.000 $260.000
PREFAB PAV MRK TY C (W) (NUMBER)
EA 2.000 $250.000 $325.000
PREFAB PAV MRK TY C (W) (WORD)
EA 57.000 $325.000 $325.000
PREFAB PAV MRK TY C (W) (RR XING)
EA 10.000 $525.000 $575.000
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 128.000 $35.000 $29.000
PREFAB PAV MRK TY C (Y) (24") (SLD)
LF 451.000 $15.000 $13.500
PREFAB PAV MRK TY C(EVAC SYM, BLUE/WHT)
EA 5.000 $575.000 $350.000
REFL PAV MRKR TY I-C
EA 2,051.000 $3.500 $3.500
REFL PAV MRKR TY II-A-A
EA 22,976.000 $3.500 $3.500
REFL PAV MRKR TY II-C-R
EA 1,240.000 $4.500 $5.750
ELIM EXT PV MRK & MRKS (RUMBLE STRIP)
LF 240.000 $20.000 $12.000
PREFORMED IN-LANE(TRANS) RUMBLE STRIP
LF 240.000 $20.000 $28.500
TMA (STATIONARY)
EA 2.000 $180.000 $20,000.000
TMA (MOBILE OPERATION)
DAY 60.000 $235.000 $5,500.000
Totals: $11,079,889.150 $12,309,357.080