TRAVIS US0183 (6314-88-001)

Items: 19

County: TRAVIS
Length: N/A
Highway: US0183
District: AUSTIN
Control Number: 6314-88-001
DBE Goal: N/A
Project: RMC - 631488001
Guaranty: N/A
Time: 29 W
Engineer's Estimate: $132,770.30
Date: 09/12/2017 (8 years ago)
Contract Number: N/A
Type: GRADING, RIPRAP, DRAINAGE STRUCTURES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$132,770.30
$130,633.00
Over/Under Est: -1.61% -$2,137.30
Over/Under Est: 12.07% $16,024.20
Amt Left: 13.9% $18,161.50
Over/Under Est: 17.15% $22,771.50
Amt Left: 19.07% $24,908.80
Delta: -4.53% -$6,747.30
$168,024.00
Over/Under Est: 26.55% $35,253.70
Amt Left: 28.62% $37,391.00
Delta: -8.02% -$12,482.20
Over/Under Est: 41.63% $55,270.20
Amt Left: 43.95% $57,407.50
Delta: -11.91% -$20,016.50
Over/Under Est: 50.98% $67,683.40
Amt Left: 53.45% $69,820.70
Delta: -6.60% -$12,413.20

Bid Items & Bid Tabulations

19 Total 0 of 19
TRAVIS  |  US0183  |  AUSTIN  |  6314-88-001  |  09/12/2017  |  $132,770.30  |  RMC - 631488001  |  GRADING, RIPRAP, DRAINAGE STRUCTS  |  29 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
LANAT ENTERPRISES LLC
MHB CONSTRUCTION, INC.
OPPORTUNITY EXCAVATION/CONCRETE, LLC
DENBOW COMPANY INC.
TCB CONSTRUCTION, INC
BECK-REIT & SONS, LTD.
PREPARING ROW
AC 2.050 $8,458.130 $4,158.000 $2,200.000 $3,000.000 $7,040.000 $5,500.000 $9,500.000
REMOVING CONC (RIPRAP)
SY 17.000 $15.000 $130.000 $22.000 $30.000 $30.000 $65.000 $50.000
EXCAVATION (SPECIAL)
CY 1,292.000 $25.000 $16.900 $8.000 $18.000 $16.000 $29.000 $28.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 1,466.000 $11.850 $27.000 $22.000 $33.000 $33.000 $33.000 $38.000
FURNISHING AND PLACING TOPSOIL (6")
SY 106.000 $1.070 $4.500 $3.000 $10.000 $9.000 $20.000 $35.000
BROADCAST SEED (PERM) (URBAN) (CLAY)
SY 6,018.000 $0.260 $0.370 $1.000 $0.500 $0.500 $0.250 $0.250
VEGETATIVE WATERING
MG 120.400 $12.940 $12.000 $65.000 $99.500 $20.000 $30.000 $28.000
TRENCH EXCAVATION PROTECTION
LF 45.000 $8.820 $33.000 $10.000 $60.000 $1.000 $25.000 $20.000
RIPRAP (CONC)(5 IN)
CY 47.000 $440.000 $253.000 $474.000 $220.000 $500.000 $550.000 $488.000
GABION MATTRESSES (GALV)(6 IN)
SY 72.000 $75.000 $56.000 $35.000 $60.000 $93.000 $75.000 $177.000
GABIONS (3' X 3')(GALV)
CY 46.000 $155.000 $175.000 $175.000 $70.000 $250.000 $250.000 $255.000
RC PIPE (CL III)(24 IN)
LF 62.500 $90.000 $84.000 $75.000 $78.000 $80.000 $150.000 $66.000
HEADWALL (CH - FW - 0) (DIA= 24 IN)
EA 1.000 $6,000.000 $5,576.000 $6,800.000 $12,000.000 $8,000.000 $6,500.000 $4,100.000
SET (TY II) (24 IN) (RCP) (3: 1) (C)
EA 1.000 $1,000.000 $1,388.840 $1,000.000 $500.000 $1,600.000 $1,800.000 $1,550.000
REMOV STR (PIPE)
LF 100.000 $20.000 $22.000 $20.000 $15.000 $17.000 $25.000 $12.000
REMOVE STR (GABION)
LF 126.000 $40.000 $50.000 $60.000 $10.000 $19.000 $60.000 $15.000
MOBILIZATION
LS 1.000 $8,650.000 $7,435.000 $30,000.000 $20,000.000 $16,500.000 $10,000.000 $18,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 121.000 $2.220 $3.000 $10.000 $2.000 $4.500 $5.000 $3.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 121.000 $0.640 $3.000 $5.000 $2.000 $1.500 $3.000 $1.000
Totals: $132,770.302 $130,633.000 $148,794.500 $155,541.800 $168,024.000 $188,040.500 $200,453.700