Show Job Controls
Bid Cobra

TRAVIS FM 734 (3417-03-024)

Items: 52

County: TRAVIS
Length: N/A
Highway: FM 734
District: AUSTIN
Control Number: 3417-03-024
DBE Goal: N/A
Project: NH 1802(402)
Guaranty: N/A
Time: 130 WORKING DAYS
Engineer's Estimate: $436,659.78
Date: 07/10/2018 (7 years ago)
Contract Number: N/A
Type: ADDING 2ND LEFT TURN LANE TO 2 INTERESECTIONS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$436,659.78
Over/Under Est: -11.04% -$48,212.78
Over/Under Est: -0.29% -$1,257.58
Amt Left: 12.09% $46,955.20
Over/Under Est: 4.93% $21,512.74
Amt Left: 17.95% $69,725.52
Delta: -5.23% -$22,770.32
Over/Under Est: 11.96% $52,202.79
Amt Left: 25.85% $100,415.57
Delta: -6.70% -$30,690.05
$583,918.72
Over/Under Est: 33.72% $147,258.94
Amt Left: 50.32% $195,471.72
Delta: -19.44% -$95,056.15

Bid Items & Bid Tabulations

52 Total 0 of 52
TRAVIS  |  FM 734  |  AUSTIN  |  3417-03-024  |  07/10/2018  |  $436,659.78  |  NH 1802(402)  |  ADDING 2ND LEFT TURN LANE TO 2 INTER...  |  130 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
AARON CONCRETE CONTRACTORS, L.P.
JOE BLAND CONSTRUCTION, L.P.
ANGEL BROTHERS HOLDINGS CORP.
CAPITAL EXCAVATION COMPANY
DENBOW COMPANY INC.
PREPARING ROW
STA 17.000 $1,000.000 $500.000 $1,000.000 $2,400.000 $2,000.000 $3,400.000
REMOVING CONC (MISC)
SY 7.200 $139.000 $90.000 $120.000 $64.000 $75.000 $168.000
REMOVING STAB BASE & ASPH PAV (8"-14")
SY 2,489.000 $5.500 $5.000 $9.000 $2.000 $10.000 $19.000
EXCAVATION (ROADWAY)
CY 1,896.100 $17.000 $18.000 $22.000 $15.000 $10.000 $24.250
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 500.000 $20.000 $18.000 $18.000 $9.000 $25.000 $19.000
FURNISHING AND PLACING TOPSOIL (4")
SY 830.000 $0.880 $5.000 $4.000 $4.200 $11.000 $5.500
DRILL SEEDING (TEMP) (WARM)
SY 830.000 $0.270 $0.600 $1.000 $0.500 $0.600 $0.150
VEGETATIVE WATERING
MG 0.170 $25.150 $500.000 $1,000.000 $1,650.000 $500.000 $240.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 830.000 $0.850 $1.300 $1.200 $1.750 $1.150 $1.800
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)
CY 873.600 $60.000 $65.000 $48.000 $69.000 $73.500 $68.000
LIME (HYDRATED LIME (SLURRY))
TON 37.100 $157.000 $200.000 $250.000 $186.000 $180.000 $215.000
LIME TRT (EXST MATL) (6")
SY 2,730.200 $2.000 $6.000 $5.500 $8.600 $12.000 $9.000
PRIME COAT(MC-30 OR AE-P)
GAL 1,310.200 $5.250 $4.000 $3.350 $3.750 $3.750 $4.000
D-GR HMA(SQ) TY-B PG70-22
TON 671.000 $105.000 $86.000 $79.400 $73.000 $85.000 $100.000
D-GR HMA(SQ) TY-C PG70-22
TON 274.000 $125.000 $89.000 $81.500 $125.000 $87.000 $100.000
STONE-MTRX-ASPH SMA-C SAC-A PG76-22
TON 274.000 $165.000 $130.000 $118.600 $180.000 $130.000 $140.000
PLAN & TEXT ASPH CONC PAV(0" TO 2")
SY 1,577.000 $3.250 $3.000 $2.600 $4.400 $3.000 $3.000
RIPRAP (CONC)(4 IN)
CY 0.600 $480.000 $1,900.000 $1,500.000 $1,300.000 $2,584.430 $1,000.000
RC PIPE (CL III)(18 IN)
LF 7.000 $55.000 $50.000 $120.000 $440.000 $300.000 $300.000
JCTBOX(COMPL)(PJB)(4FTX4FT)
EA 1.000 $2,800.000 $4,200.000 $7,800.000 $4,500.000 $5,000.000 $5,800.000
INLET (COMPL)(PSL)(FG)(4FTX4FT-4FTX4FT)
EA 1.000 $4,300.000 $4,700.000 $7,553.110 $5,700.000 $6,000.000 $6,900.000
REMOV STR (INLET)
EA 1.000 $1,200.000 $900.000 $800.000 $830.000 $2,000.000 $650.000
MOBILIZATION
LS 1.000 $39,500.000 $30,000.000 $43,540.220 $46,000.000 $47,000.000 $57,479.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $5,000.000 $1,000.000 $2,500.000 $2,000.000 $1,000.000 $6,000.000
SANDBAGS FOR EROSION CONTROL (6")
LF 95.000 $2.000 $6.500 $5.000 $7.000 $6.000 $12.500
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,476.000 $2.750 $2.250 $1.800 $2.500 $2.100 $2.200
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,476.000 $0.750 $0.500 $0.500 $0.500 $0.500 $0.500
CURB RAMPS (TY 21)
EA 1.000 $1,500.000 $2,500.000 $4,100.000 $1,475.000 $4,730.570 $3,400.000
GROUND BOX TY D (162922)W/APRON
EA 2.000 $1,824.000 $3,600.000 $3,337.100 $1,750.000 $1,500.000 $2,020.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $520.000 $580.000 $370.000 $690.000 $542.000 $490.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 4.000 $351.000 $430.000 $150.000 $450.000 $400.000 $404.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 2,044.000 $0.800 $1.100 $1.000 $1.900 $1.000 $1.300
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 112.000 $3.000 $4.300 $4.000 $3.250 $4.000 $5.300
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 101.000 $7.600 $8.600 $8.000 $10.250 $8.000 $10.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 8.000 $150.000 $130.000 $122.000 $160.000 $122.000 $160.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 8.000 $200.000 $150.000 $137.000 $170.000 $137.000 $180.000
REFL PAV MRK TY II (W) 8" (SLD)
LF 2,044.000 $0.300 $0.550 $0.500 $1.050 $0.500 $0.600
REFL PAV MRK TY II (W) 12" (SLD)
LF 112.000 $0.900 $3.200 $3.000 $2.150 $3.000 $4.000
REFL PAV MRK TY II (W) 24" (SLD)
LF 101.000 $3.000 $6.500 $6.000 $3.100 $6.000 $8.000
REFL PAV MRK TY II (W) (ARROW)
EA 8.000 $70.000 $83.000 $77.000 $110.000 $77.000 $103.000
REFL PAV MRK TY II (W) (WORD)
EA 8.000 $130.000 $83.000 $77.000 $115.000 $77.000 $103.000
REFL PAV MRK TY II (Y) 4" (SLD)
LF 1,476.000 $0.100 $0.550 $0.500 $0.550 $0.500 $0.600
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 1,476.000 $0.450 $3.200 $3.000 $1.450 $3.000 $4.000
REFL PAV MRKR TY I-C
EA 103.000 $5.000 $22.000 $20.000 $10.500 $20.000 $26.000
INSTALL HWY TRF SIG (UPGRADE)
EA 2.000 $6,500.000 $1,800.000 $1,669.000 $3,800.000 $3,300.000 $4,444.000
VEH SIG SEC (12")LED(GRN ARW)
EA 2.000 $210.000 $345.000 $322.600 $450.000 $400.000 $538.000
VEH SIG SEC (12")LED(YEL ARW)
EA 2.000 $208.000 $345.000 $322.600 $450.000 $400.000 $538.000
VEH SIG SEC (12")LED(RED ARW)
EA 2.000 $214.000 $345.000 $322.600 $450.000 $400.000 $538.000
BACK PLATE (12")(3 SEC)ALUM
EA 2.000 $125.000 $90.000 $83.500 $120.000 $110.000 $148.000
TRF SIG CBL (TY A)(14 AWG)(5 CONDR)
LF 260.000 $1.400 $19.000 $17.800 $6.000 $5.500 $7.000
PED POLE ASSEMBLY
EA 2.000 $2,535.000 $4,300.000 $4,004.500 $4,800.000 $4,300.000 $5,790.000
TMA (STATIONARY)
EA 2.000 $7,300.000 $4,300.000 $15,000.000 $7,000.000 $19,000.000 $5,000.000
Totals: $436,659.776 $388,447.000 $435,402.200 $458,172.520 $488,862.578 $583,918.725