TRAVIS FM 973 (1200-03-061)

Items: 64

County: TRAVIS
Length: N/A
Highway: FM 973
District: AUSTIN
Control Number: 1200-03-061
DBE Goal: N/A
Project: STP 2022(342)TP
Guaranty: N/A
Time: 66 WORKING DAYS
Engineer's Estimate: $877,614.30
Date: 02/04/2022 (4 years ago)
Contract Number: N/A
Type: BICYCLE AND PEDESTRIAN IMPROVEMENTS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (3)
E
Engineer's Estimate
$877,614.30
$969,301.45
Over/Under Est: 10.45% $91,687.15
$1,061,875.50
Over/Under Est: 21% $184,261.20
Amt Left: 9.55% $92,574.05
Over/Under Est: 87.75% $770,110.50
Amt Left: 69.99% $678,423.35
Delta: -55.17% -$585,849.30

Bid Items & Bid Tabulations

64 Total 0 of 64
TRAVIS  |  FM 973  |  AUSTIN  |  1200-03-061  |  02/04/2022  |  $877,614.30  |  STP 2022(342)TP  |  BICYCLE AND PEDESTRIAN IMPRVS  |  66 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
LONE STAR SITEWORK, LLC
DAN WILLIAMS COMPANY
AARON CONCRETE CONTRACTORS, L.P.
PREPARING ROW
STA 30.500 $2,500.000 $200.000 $3,000.000 $1,500.000
REMOVING CONC (RIPRAP)
SY 21.000 $10.000 $77.000 $45.000 $82.000
REMOVING CONC (RIPRAP)
CY 3.000 $180.000 $77.000 $170.000 $570.000
REMOVING CONC (SIDEWALKS)
SY 37.000 $10.000 $12.900 $25.000 $84.000
REMOVING CONC (CURB)
LF 40.000 $7.000 $10.000 $13.000 $43.000
EMBANKMENT (FINAL)(ORD COMP)(TY A)
CY 1.000 $25.000 $100.000 $200.000 $3,500.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 160.000 $10.000 $40.000 $50.000 $100.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
CY 165.000 $17.000 $40.000 $50.000 $100.000
FURNISHING AND PLACING TOPSOIL
CY 289.000 $25.000 $64.800 $13.000 $86.000
BLOCK SODDING
SY 2,576.000 $4.000 $6.900 $6.000 $7.000
VEGETATIVE WATERING
MG 66.000 $15.000 $85.000 $15.000 $35.000
CEM STABIL BKFL
CY 124.000 $139.000 $156.000 $200.000 $220.000
FLOWABLE BACKFILL
CY 39.000 $125.000 $165.000 $250.000 $215.000
TEMPORARY SPL SHORING
SF 864.000 $27.000 $15.000 $13.000 $88.000
CL A CONC (MISC)
CY 18.000 $300.000 $576.500 $75.000 $1,700.000
CL C CONC (ABUT)
CY 21.600 $888.000 $1,075.000 $1,600.000 $3,700.000
CL C CONC (FOOTING)
CY 18.400 $500.000 $950.000 $1,000.000 $3,100.000
CL S CONC(APPR SLAB)(MOD)
CY 5.200 $962.000 $625.000 $1,600.000 $5,000.000
PNEUMATICALLY PLACED CONC (REPAIR)
CF 42.000 $60.000 $86.000 $200.000 $1,600.000
RIPRAP (CONC)(4 IN)
CY 6.000 $375.000 $694.000 $850.000 $1,100.000
RIPRAP (CONC)(5 IN)
CY 18.500 $440.000 $725.000 $750.000 $1,000.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 57.000 $183.000 $282.000 $200.000 $275.000
RIPRAP (MOW STRIP)(4 IN)
CY 4.270 $430.000 $785.000 $500.000 $570.000
STR STEEL (MISC NON - BRIDGE)
LB 368.000 $14.000 $60.000 $20.000 $82.000
RAIL (HANDRAIL)(TY B)
LF 42.000 $100.000 $117.200 $110.000 $120.000
TYPE A JOINT
LF 28.000 $37.000 $200.000 $45.000 $300.000
RC PIPE (CL III)(12 IN)
LF 96.000 $100.000 $86.000 $150.000 $130.000
RC PIPE (CL III)(24 IN)
LF 18.000 $80.000 $136.000 $175.000 $260.000
SET (TY II) (12 IN) (RCP) (6: 1) (P)
EA 5.000 $700.000 $1,290.000 $1,350.000 $2,700.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 1.000 $1,400.000 $1,850.000 $1,600.000 $5,000.000
ADJUSTING MANHOLES (WATER VALVE BOX)
EA 1.000 $500.000 $500.000 $1,000.000 $1,500.000
REMOV STR (SET)
EA 3.000 $400.000 $500.000 $250.000 $1,350.000
MOBILIZATION
LS 1.000 $50,448.000 $17,000.000 $100,000.000 $150,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $8,000.000 $1,950.000 $12,000.000 $2,500.000
SANDBAGS FOR EROSION CONTROL
EA 24.000 $6.000 $10.000 $8.000 $18.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 4,451.000 $2.500 $4.000 $4.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 4,451.000 $0.500 $0.900 $1.000 $1.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 201.000 $1.000 $4.000 $4.000 $4.000
BIODEG EROSN CONT LOGS (INSTL) (6")
LF 201.000 $4.000 $0.900 $1.000 $1.000
CONC CURB (TY I)
LF 61.000 $15.000 $51.000 $50.000 $50.000
CONC CURB (TY F1)
LF 42.000 $90.000 $254.000 $125.000 $480.000
DRIVEWAYS (ACP)
SY 182.000 $40.000 $215.000 $170.000 $200.000
CONC SIDEWALKS (6")
SY 2,898.000 $70.000 $77.700 $60.000 $110.000
CURB RAMPS (TY 1)
EA 12.000 $1,700.000 $1,850.000 $2,000.000 $2,100.000
CURB RAMPS (TY 2)
EA 1.000 $1,700.000 $2,050.000 $2,000.000 $2,200.000
CURB RAMPS (TY 3)
EA 4.000 $1,700.000 $2,050.000 $2,000.000 $2,050.000
CURB RAMPS (TY 7)
EA 1.000 $1,700.000 $1,850.000 $2,000.000 $2,050.000
CURB RAMPS (TY 10)
EA 7.000 $1,700.000 $1,850.000 $2,000.000 $2,200.000
MTL W-BEAM GD FEN (TIM POST)
LF 75.000 $21.000 $35.600 $35.000 $37.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 1.000 $1,730.000 $2,283.000 $2,500.000 $2,400.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $1,330.000 $1,460.500 $1,500.000 $1,500.000
REMOVE METAL BEAM GUARD FENCE
LF 110.000 $2.500 $5.750 $5.000 $6.000
REMOVE TERMINAL ANCHOR SECTION
EA 1.000 $200.000 $173.000 $150.000 $180.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 1.000 $400.000 $201.000 $175.000 $206.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 10.000 $530.000 $710.000 $900.000 $993.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 10.000 $400.000 $480.000 $600.000 $665.000
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
LF 663.000 $6.000 $11.500 $8.000 $12.000
ELIM EXT PAV MRK & MRKS (24")
LF 467.000 $4.000 $11.500 $3.500 $5.700
PREFAB PED STL TRUSS BRG SPAN (93 FT)
EA 1.000 $215,667.000 $236,284.300 $225,000.000 $317,000.000
FIXED BOLLARD
EA 2.000 $750.000 $800.000 $1,250.000 $3,100.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 66.000 $100.000 $95.000 $100.000 $106.000
GROUND BOX W/ APRON (ADJUST)
EA 1.000 $1,200.000 $6,000.000 $800.000 $4,200.000
TMA (STATIONARY)
DAY 66.000 $180.000 $255.000 $225.000 $280.000
TMA (MOBILE OPERATION)
DAY 66.000 $300.000 $660.000 $225.000 $100.000
Totals: $877,614.300 $969,301.450 $1,061,875.500 $1,647,724.800