TRAVIS HARRIS BRANCH PKWY (0914-04-364)
Items: 73
County: TRAVIS
Length: 0.0000 MILES
Highway: HARRIS BRANCH PKWY
District: AUSTIN
Control Number: 0914-04-364
DBE Goal: 0.0%
Project: STP 2026(656)VRUG
Guaranty: $12,000.00
Time: 80 WORKING DAYS
Engineer's Estimate: $516,136.30
Date: 06/03/2026 (7 days ago)
Contract Number: 6263225
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00206735
Contract Type: Federal
Project Description: INSTALL TRAFFIC SIGNAL
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
BRENDA GUERRA
MATTHEW KELLY
KEVIN MACKAN
MAHENDRAN THIVAKARAN
YETNAYET BOGALE
CORY JUCIUS
SRIDHAR RAMAIYENGAR
TRAVIS HARRIS BRANCH PKWY (0914-04-364)
Project Name: N/A
Project: STP 2026(656)VRUG
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: AT GILES LN
Limits To: .
Project Description: INSTALL TRAFFIC SIGNAL
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$516,136.30 | |||
| $405,662.40 |
-21.4%
-$110,473.90
|
|||
| $449,983.00 |
-12.82%
-$66,153.30
|
10.93%
$44,320.60
|
||
| $482,028.48 |
-6.61%
-$34,107.82
|
18.83%
$76,366.08
|
-7.12%
-$32,045.48
|
|
| $497,834.99 |
-3.55%
-$18,301.31
|
22.72%
$92,172.59
|
-3.28%
-$15,806.51
|
|
| $527,561.70 |
2.21%
$11,425.40
|
30.05%
$121,899.30
|
-5.97%
-$29,726.71
|
|
| $649,000.00 |
25.74%
$132,863.70
|
59.99%
$243,337.60
|
-23.02%
-$121,438.30
|
|
| $813,541.24 |
57.62%
$297,404.94
|
100.55%
$407,878.84
|
-25.35%
-$164,541.24
|
E
Engineer's Estimate
$516,136.30
$405,662.40
Over/Under Est:
-21.4%
-$110,473.90
$449,983.00
Over/Under Est:
-12.82%
-$66,153.30
Amt Left:
10.93%
$44,320.60
$482,028.48
Over/Under Est:
-6.61%
-$34,107.82
Amt Left:
18.83%
$76,366.08
Delta:
-7.12%
-$32,045.48
$497,834.99
Over/Under Est:
-3.55%
-$18,301.31
Amt Left:
22.72%
$92,172.59
Delta:
-3.28%
-$15,806.51
$527,561.70
Over/Under Est:
2.21%
$11,425.40
Amt Left:
30.05%
$121,899.30
Delta:
-5.97%
-$29,726.71
$649,000.00
Over/Under Est:
25.74%
$132,863.70
Amt Left:
59.99%
$243,337.60
Delta:
-23.02%
-$121,438.30
$813,541.24
Over/Under Est:
57.62%
$297,404.94
Amt Left:
100.55%
$407,878.84
Delta:
-25.35%
-$164,541.24
Bid Items & Bid Tabulations
73
Total
0 of 73
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $3,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $4,000.00 |
| MATERIALS FURNISHED BY CITY (PART) | $95,590.20 |
| Total: | $102,590.20 |