Show Job Controls
Bid Cobra

TRAVIS CR 1397 (0914-04-356)

Items: 30

County: TRAVIS
Length: 0.0000 MILES
Highway: CR 1397
District: AUSTIN
Control Number: 0914-04-356
DBE Goal: 0.0%
Project: STP 2026(654)HESG
Guaranty: $8,000.00
Time: 43 WORKING DAYS
Engineer's Estimate: $406,871.00
Date: 06/02/2026 (8 days ago)
Contract Number: 6263026
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00193151
Contract Type: Federal
Project Description: SAFETY TREAT FIXED OBJECTS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
ORLANDO GALLEGOS
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$406,871.00
Over/Under Est: -4.49% -$18,273.00
Over/Under Est: -3.42% -$13,925.25
Amt Left: 1.12% $4,347.75
Over/Under Est: -1.91% -$7,771.30
Amt Left: 2.7% $10,501.70
Delta: -1.57% -$6,153.95
Over/Under Est: 11.03% $44,868.85
Amt Left: 16.25% $63,141.85
Delta: -13.19% -$52,640.15
Over/Under Est: 20.41% $83,052.00
Amt Left: 26.07% $101,325.00
Delta: -8.45% -$38,183.15
$543,439.59
Over/Under Est: 33.57% $136,568.59
Amt Left: 39.85% $154,841.59
Delta: -10.92% -$53,516.59
Over/Under Est: 46.89% $190,765.36
Amt Left: 53.79% $209,038.36
Delta: -9.97% -$54,196.77

Bid Items & Bid Tabulations

30 Total 0 of 30
TRAVIS  |  CR 1397  |  AUSTIN  |  0914-04-356  |  06/02/2026  |  $406,871.00  |  STP 2026(654)HESG  |  HAZARD ELIM & SAFETY  |  43 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
GARRET SHIELDS INFRASTRUCTURE
DEAN WORD COMPANY, LTD.
DAN WILLIAMS COMPANY
ICOS MANAGEMENT, LLC
DIGG COMMERCIAL, LLC
STX CIVIL
E-Z BEL CONSTRUCTION, LLC
PREPARING ROW
STA 10.000 $3,250.000 $1,000.000 $3,150.000 $2,000.000 $1,050.000 $3,323.000 $2,075.190 $2,200.000
REMOV CONC (RIPRAP)
SY 442.000 $16.000 $40.000 $22.000 $11.750 $26.250 $15.000 $24.320 $1.000
REMOVE STAB BASE AND ASPH PAV (6"-20")
SY 448.000 $8.000 $20.000 $19.500 $7.000 $26.250 $10.000 $53.010 $20.000
EXCAV (ROADWAY)
CY 47.000 $14.000 $50.000 $123.500 $65.000 $210.000 $75.000 $38.890 $20.000
EMBANK (FNL)(OC)(TY A)
CY 555.000 $21.000 $35.000 $63.500 $30.000 $68.250 $75.000 $51.780 $70.000
FURN & PLACE TOPSOIL (4")
SY 3,664.000 $2.000 $5.000 $3.000 $1.300 $8.400 $4.000 $4.160 $5.400
BOND FBR MTRX SEED (TEMP)(WARM)
SY 1,832.000 $1.000 $0.500 $1.500 $2.500 $1.100 $1.000 $1.520 $1.350
BOND FBR MTRX SEED (TEMP)(COOL)
SY 1,832.000 $1.000 $0.500 $1.500 $2.500 $1.100 $6.000 $1.520 $1.350
VEGETATIVE WATERING
TGL 110.000 $28.000 $20.000 $43.250 $5.000 $10.500 $50.000 $48.110 $31.000
TRENCH EXCAVATION PROTECTION
LF 736.000 $14.500 $1.000 $5.000 $1.000 $6.300 $8.000 $22.550 $0.010
RC PIPE (CL III)(24 IN)
LF 1,019.000 $110.000 $120.000 $78.000 $95.000 $105.000 $108.000 $159.450 $235.000
INL(CMP)(PAZD-CZ)(FG)(4FTX4FT-4FTX4FT)
EA 6.000 $7,750.000 $5,000.000 $5,696.000 $9,000.000 $8,400.000 $8,000.000 $7,578.730 $17,000.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 2.000 $2,300.000 $2,500.000 $4,060.000 $2,250.000 $1,890.000 $4,000.000 $2,982.510 $3,700.000
REMOV STR (SET)
EA 14.000 $575.000 $500.000 $492.500 $200.000 $420.000 $454.000 $343.480 $100.000
REMOV STR (PIPE)
LF 364.000 $21.000 $10.000 $34.250 $20.000 $12.600 $20.000 $27.780 $25.000
MOBILIZATION
LS 1.000 $40,850.000 $30,000.000 $35,000.000 $37,500.000 $28,500.000 $50,000.000 $42,573.600 $45,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $7,500.000 $5,000.000 $11,069.250 $15,000.000 $1.100 $15,000.000 $2,286.690 $2,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $8,500.000 $1,000.000 $4,310.250 $7,000.000 $5,250.000 $8,802.000 $7,846.780 $3,100.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 160.000 $60.000 $20.000 $47.750 $47.500 $21.000 $47.000 $51.710 $47.500
ROCK FILTER DAMS (REMOVE)
LF 160.000 $21.000 $5.000 $17.750 $21.500 $10.500 $13.000 $19.560 $21.500
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 120.000 $6.000 $5.000 $4.500 $8.750 $10.500 $50.000 $4.970 $8.750
BIODEG EROSN CONT LOGS (REMOVE)
LF 120.000 $1.300 $1.000 $1.250 $3.750 $5.250 $1.000 $1.330 $3.750
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 240.000 $40.000 $80.000 $13.000 $20.000 $105.000 $60.000 $89.060 $18.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 120.000 $45.000 $80.000 $22.000 $25.000 $105.000 $60.000 $89.060 $25.000
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 240.000 $13.000 $20.000 $8.000 $15.000 $21.000 $15.000 $50.070 $18.000
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 120.000 $20.000 $20.000 $12.000 $15.000 $21.000 $15.000 $48.980 $25.000
DRIVEWAYS (ACP)
SY 502.000 $70.000 $100.000 $87.750 $118.000 $115.500 $75.000 $115.360 $100.000
REMOVE METAL BEAM GUARD FENCE
LF 451.000 $4.000 $5.000 $7.250 $5.000 $4.200 $5.000 $1.990 $10.000
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $508.000 $500.000 $313.000 $210.000 $840.000 $175.000 $248.750 $10.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $398.000 $500.000 $313.000 $225.000 $840.000 $237.000 $331.770 $450.000
Totals: $406,871.000 $388,598.000 $392,945.750 $399,099.700 $451,739.850 $489,923.000 $543,439.590 $597,636.360
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $7,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $35,000.00
Total: $42,000.00