TRAVIS VARIOUS (0914-00-560)

Items: 38

County: TRAVIS
Length: 0.0000 MILES
Highway: VARIOUS
District: AUSTIN
Control Number: 0914-00-560
DBE Goal: 0.0%
Project: STP 2026(348)FRS
Guaranty: $17,000.00
Time: 101 WORKING DAYS
Engineer's Estimate: $832,204.16
Date: 02/04/2026 (4 months ago)
Contract Number: 2263024
Type: HIGHWAY/RAILROAD IMPROVEMENT
Project ID: A00214224
Contract Type: Federal
Project Description: INSTALLATION OF SIGNS AND MARKINGS TO IMPROVE SAFETY AT RAILROAD CROSSINGS ON VARIOUS ON-SYSTEM AND OFF-SYSTEM ROADWAYS WITHIN THE CITY OF AUSTIN IN TRAVIS AND WILLIAMSON COUNTY
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
BRENDA GUERRA
MAHENDRAN THIVAKARAN
YETNAYET BOGALE
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$832,204.16
$797,815.65
Over/Under Est: -4.13% -$34,388.51
Over/Under Est: 9.72% $80,879.60
Amt Left: 14.45% $115,268.11
Over/Under Est: 15.58% $129,694.69
Amt Left: 20.57% $164,083.20
Delta: -5.35% -$48,815.09
Over/Under Est: 43.95% $365,789.84
Amt Left: 50.16% $400,178.35
Delta: -24.54% -$236,095.15
$1,235,799.15
Over/Under Est: 48.5% $403,594.99
Amt Left: 54.9% $437,983.50
Delta: -3.16% -$37,805.15

Bid Items & Bid Tabulations

38 Total 0 of 38
TRAVIS  |  VARIOUS  |  AUSTIN  |  0914-00-560  |  02/04/2026  |  $832,204.16  |  STP 2026(348)FRS  |  HWY/RAILROAD IMPRV  |  101 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
STRIPE-A-ZONE, LLC
TRP INFRASTRUCTURE SERVICES, LLC
D. I. J. CONSTRUCTION, INC.
GREY SKY CONSTRUCTION LLC
STRIPE LINES, INC.
MOBILIZATION
LS 1.000 $60,000.000 $65,000.000 $27,500.000 $85,000.000 $82,000.000 $150,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $7,000.000 $7,500.000 $2,750.000 $10,000.000 $8,500.000 $2,500.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $11,000.000 $20,000.000 $7,777.000 $2,000.000 $10,000.000 $2,500.000
TMA (STATIONARY)
DAY 100.000 $280.000 $1.000 $70.000 $1.000 $250.000 $500.000
TMA (MOBILE OPERATION)
DAY 40.000 $300.000 $1.000 $106.000 $650.000 $550.000 $150.000
BIODEG EROSN CONT LOGS (INSTL) (6")
LF 1,360.000 $2.000 $0.500 $0.700 $1.000 $12.000 $55.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,360.000 $1.000 $0.500 $0.700 $1.000 $6.000 $55.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 233.000 $650.000 $850.000 $725.000 $910.000 $800.000 $1,261.980
REMOVE SM RD SN SUP&AM
EA 184.000 $100.000 $150.000 $115.000 $120.000 $120.000 $500.250
INSTL DEL ASSM (D-DY)SZ 1(YFLX)SRFLL
EA 94.000 $100.000 $133.000 $250.000 $85.000 $100.000 $188.000
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 224.000 $1.250 $1.500 $2.500 $1.500 $3.000 $0.990
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 21,283.000 $0.870 $1.150 $2.500 $1.450 $3.000 $1.170
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 22.000 $4.290 $10.000 $7.000 $4.500 $8.000 $4.410
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 7,525.000 $6.000 $7.000 $10.000 $12.000 $12.000 $5.530
REFL PAV MRK TY I (W)(RR XING)(090MIL)
EA 180.000 $550.000 $500.000 $700.000 $625.000 $500.000 $354.840
REFL PAV MRK TY I (W)(BIKE ARW)(100MIL)
EA 48.000 $170.000 $225.000 $160.000 $130.000 $500.000 $214.190
RFL PAV MRK TY I(W)BIKE RR XING(090MIL)
EA 53.000 $300.000 $375.000 $430.000 $375.000 $650.000 $265.730
REFL PAV MRK TY I(W)(BIKE SYML)(100MIL)
EA 49.000 $275.000 $250.000 $160.000 $205.000 $500.000 $212.080
RE PM TY II (W) 6" (DOT)
LF 224.000 $1.650 $0.200 $0.520 $0.650 $1.000 $0.440
RE PM TY II (W) 6" (SLD)
LF 23,573.000 $0.220 $0.200 $0.520 $0.500 $1.000 $0.440
RE PM TY II (W) 8" (SLD)
LF 21,283.000 $0.720 $0.300 $0.520 $0.600 $1.000 $0.880
RE PM TY II (W) 12" (SLD)
LF 22.000 $3.500 $2.000 $1.600 $2.500 $6.000 $4.060
RE PM TY II (W) 24" (SLD)
LF 7,525.000 $4.250 $2.500 $3.400 $5.000 $8.000 $4.500
RE PM TY II (W) (RR XING)
EA 180.000 $400.000 $100.000 $167.000 $165.000 $250.000 $249.450
RE PM TY II (W) (BIKE ARROW)
EA 48.000 $85.000 $50.000 $43.000 $50.000 $250.000 $201.620
RE PM TY II (W) (BIKE RR XING)
EA 53.000 $300.000 $75.000 $106.000 $75.000 $250.000 $201.620
RE PM TY II (W) (BIKE SYMBOL)
EA 49.000 $120.000 $50.000 $43.000 $50.000 $500.000 $201.620
RE PM TY II (Y) 6" (BRK)
LF 6,254.000 $0.210 $0.100 $0.520 $0.500 $1.000 $0.440
RE PM TY II (Y) 6" (SLD)
LF 37,979.000 $0.180 $0.100 $0.520 $0.500 $1.000 $0.440
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 23,573.000 $0.730 $0.850 $2.050 $1.300 $1.000 $1.180
REFL PAV MRK TY I (Y)6"(BRK)(090MIL)
LF 6,254.000 $0.740 $0.850 $2.050 $1.250 $1.000 $1.180
REFL PAV MRK TY I (Y)6"(SLD)(090MIL)
LF 37,979.000 $0.710 $0.850 $2.050 $1.300 $1.000 $1.180
REFL PAV MRKR TY I-C
EA 340.000 $4.600 $6.000 $12.500 $6.500 $6.000 $15.000
ELIM EXT PM & MRKS (24")
LF 6,462.000 $3.000 $4.000 $2.500 $3.000 $8.000 $3.000
ELIM EXT PM & MRKS (RR XING)
EA 156.000 $275.000 $250.000 $350.000 $160.000 $250.000 $147.200
ELIM EXT PM & MARKS (BIKE ARROW)
EA 29.000 $100.000 $70.000 $50.000 $80.000 $250.000 $57.200
ELIM EXT PM & MARKS (BIKE RR XING)
EA 9.000 $100.000 $100.000 $250.000 $31.000 $250.000 $57.200
ELIM EXT PM & MARKS (BIKE SYMBOL)
EA 19.000 $100.000 $70.000 $50.000 $90.000 $250.000 $57.200
Totals: $832,204.160 $797,815.650 $913,083.760 $961,898.850 $1,197,994.000 $1,235,799.150
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $40,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $15,000.00
Total: $60,000.00