TRAVIS VARIOUS (0914-00-517)
Items: 14
County: TRAVIS
Length: 0.0000 MILES
Highway: VARIOUS
District: AUSTIN
Control Number: 0914-00-517
DBE Goal: 0.0%
Project: C 914-00-517
Guaranty: $15,000.00
Time: 60 WORKING DAYS
Engineer's Estimate: $727,725.50
Date: 07/02/2025 (11 months ago)
Contract Number: 7253232
Type: INSTALL/REPLACE SIGNS
Project ID: A00197327
Project Description: SMALL SIGN UPGRADES (FY 25)
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
KYLE RUSSELL
JEREMY MIKES
TRAVIS VARIOUS (0914-00-517)
Project Name: N/A
Project: C 914-00-517
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: VARIOUS LOCATIONS IN TRAVIS
Limits To: AND WILLIAMSON COUNTIES
Project Description: SMALL SIGN UPGRADES (FY 25)
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$727,725.50 | |||
| $504,526.50 |
-30.67%
-$223,199.00
|
|||
| $570,757.50 |
-21.57%
-$156,968.00
|
13.13%
$66,231.00
|
||
| $589,290.00 |
-19.02%
-$138,435.50
|
16.8%
$84,763.50
|
-3.25%
-$18,532.50
|
|
| $635,236.25 |
-12.71%
-$92,489.25
|
25.91%
$130,709.75
|
-7.80%
-$45,946.25
|
|
| $661,873.75 |
-9.05%
-$65,851.75
|
31.19%
$157,347.25
|
-4.19%
-$26,637.50
|
|
| $665,430.00 |
-8.56%
-$62,295.50
|
31.89%
$160,903.50
|
-0.54%
-$3,556.25
|
|
| $859,820.00 |
18.15%
$132,094.50
|
70.42%
$355,293.50
|
-29.21%
-$194,390.00
|
E
Engineer's Estimate
$727,725.50
1
Awarded
$504,526.50
Over/Under Est:
-30.67%
-$223,199.00
$570,757.50
Over/Under Est:
-21.57%
-$156,968.00
Amt Left:
13.13%
$66,231.00
$589,290.00
Over/Under Est:
-19.02%
-$138,435.50
Amt Left:
16.8%
$84,763.50
Delta:
-3.25%
-$18,532.50
$635,236.25
Over/Under Est:
-12.71%
-$92,489.25
Amt Left:
25.91%
$130,709.75
Delta:
-7.80%
-$45,946.25
$661,873.75
Over/Under Est:
-9.05%
-$65,851.75
Amt Left:
31.19%
$157,347.25
Delta:
-4.19%
-$26,637.50
$665,430.00
Over/Under Est:
-8.56%
-$62,295.50
Amt Left:
31.89%
$160,903.50
Delta:
-0.54%
-$3,556.25
$859,820.00
Over/Under Est:
18.15%
$132,094.50
Amt Left:
70.42%
$355,293.50
Delta:
-29.21%
-$194,390.00
Bid Items & Bid Tabulations
14
Total
0 of 14
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $5,000.00 |
| RAILROAD FLAGGING: RAILROAD FORCE ACCOUNT WORK (NON-PART) | $7,500.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $30,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $5,000.00 |
| Total: | $47,500.00 |