Show Job Controls
Bid Cobra

TRAVIS VA (0914-00-473)

Items: 26

County: TRAVIS
Length: N/A
Highway: VA
District: AUSTIN
Control Number: 0914-00-473
DBE Goal: N/A
Project: C 914-00-473
Guaranty: N/A
Time: 44 WORKING DAYS
Engineer's Estimate: $585,955.20
Date: 09/07/2022 (3 years ago)
Contract Number: N/A
Type: PREVENTIVE MAINTENANCE
Mail/Deliver Bids To: N/A
JASON HUDSON
JOHN PETERS
MASOUD MORADIAN
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$585,955.20
$442,394.99
Over/Under Est: -24.5% -$143,560.21
Over/Under Est: -4.92% -$28,838.45
Amt Left: 25.93% $114,721.76
Over/Under Est: -3.36% -$19,708.30
Amt Left: 28% $123,851.91
Delta: -1.64% -$9,130.15

Bid Items & Bid Tabulations

26 Total 0 of 26
TRAVIS  |  VA  |  AUSTIN  |  0914-00-473  |  09/07/2022  |  $585,955.20  |  C 914-00-473  |  PREVENT MAINT  |  44 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
D. I. J. CONSTRUCTION, INC.
TRP CONSTRUCTION GROUP, LLC
TOTAL HIGHWAY MAINTENANCE, LLC
MOBILIZATION
LS 1.000 $49,399.800 $32,000.000 $5,000.000 $40,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $8,500.000 $100.000 $500.000 $7,500.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 200.000 $3.000 $1.000 $5.000 $1.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 200.000 $0.750 $1.000 $1.000 $1.000
REFL PAV MRK TY I (W)8"(DOT)(060MIL)
LF 1,802.000 $0.850 $1.000 $1.500 $1.000
REFL PAV MRK TY I (W)8"(SLD)(060MIL)
LF 36,890.000 $0.850 $0.600 $0.800 $1.000
REFL PAV MRK TY I (W)12"(SLD)(060MIL)
LF 6,326.000 $4.000 $4.300 $4.500 $3.500
REFL PAV MRK TY I (W)24"(SLD)(060MIL)
LF 3,055.000 $6.900 $8.750 $8.500 $7.000
REFL PAV MRK TY I (W)(ARROW)(060MIL)
EA 224.000 $125.000 $155.000 $175.000 $105.000
REFL PAV MRK TY I (W)(WORD)(060MIL)
EA 180.000 $130.000 $210.000 $195.000 $145.000
REFL PAV MRK TY I (W)(RR XING)(060MIL)
EA 12.000 $600.000 $600.000 $550.000 $750.000
REF PAV MRK TY I(W)18"(YLD TRI)(060MIL)
EA 6.000 $25.000 $35.000 $60.000 $100.000
REF PAV MRK TY I(W)36"(YLD TRI)(060MIL)
EA 218.000 $50.000 $40.000 $60.000 $55.000
REFL PAV MRK TY I (Y)12"(SLD)(060MIL)
LF 1,476.000 $1.000 $3.900 $4.500 $3.500
REFL PAV MRK TY I (Y)24"(SLD)(060MIL)
LF 1,084.000 $6.500 $7.800 $8.500 $7.000
REFL PAV MRK TY I(Y)(MED NOSE)(060MIL)
EA 5.000 $250.000 $595.000 $500.000 $200.000
RE PM W/RET REQ TY I (W)4"(BRK)(060MIL)
LF 20,374.000 $0.400 $0.220 $0.400 $0.400
RE PM W/RET REQ TY I (W)4"(SLD)(060MIL)
LF 131,831.000 $0.400 $0.210 $0.400 $0.350
RE PM W/RET REQ TY I (Y)4"(BRK)(060MIL)
LF 30,805.000 $0.400 $0.220 $0.400 $0.400
RE PM W/RET REQ TY I (Y)4"(SLD)(060MIL)
LF 363,795.000 $0.400 $0.210 $0.400 $0.350
PREFAB PAV MRK TY C (MULTI) (SHIELD)
EA 5.000 $3,000.000 $1,950.000 $2,800.000 $3,400.000
REFL PAV MRKR TY I-C
EA 2,489.000 $3.500 $3.500 $3.750 $4.400
REFL PAV MRKR TY II-A-A
EA 7,159.000 $3.300 $3.500 $3.750 $4.400
REFL PAV MRKR TY II-C-R
EA 6,355.000 $3.500 $3.500 $3.750 $4.400
TRAFFIC BUTTON TY Y
EA 14,946.000 $3.500 $3.000 $3.000 $3.500
TMA (MOBILE OPERATION)
DAY 50.000 $220.000 $1.000 $250.000 $50.000
Totals: $585,955.200 $442,394.990 $557,116.750 $566,246.900