Show Job Controls
Bid Cobra

TRAVIS VA (0914-00-457)

Items: 86

County: TRAVIS
Length: N/A
Highway: VA
District: AUSTIN
Control Number: 0914-00-457
DBE Goal: N/A
Project: STP 2022(643)
Guaranty: N/A
Time: 178 WORKING DAYS
Engineer's Estimate: $2,734,692.33
Date: 06/02/2022 (4 years ago)
Contract Number: N/A
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Mail/Deliver Bids To: N/A
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$2,734,692.33
$2,965,162.90
Over/Under Est: 8.43% $230,470.57
Over/Under Est: 22.81% $623,848.67
Amt Left: 13.27% $393,378.10
$3,531,467.24
Over/Under Est: 29.14% $796,774.91
Amt Left: 19.1% $566,304.34
Delta: -5.15% -$172,926.24
Subcontractor Percentage Amount
D. I. J. CONSTRUCTION, INC. 5.88% $174,351.58
CLASSIC TEJAS CONSTRUCTION, INC. 1.18% $34,988.92
Total: 7.06% $209,340.50

Bid Items & Bid Tabulations

86 Total 0 of 86
TRAVIS  |  VA  |  AUSTIN  |  0914-00-457  |  06/02/2022  |  $2,734,692.33  |  STP 2022(643)  |  CONSTRUCT PEDESTRIAN INFRASTRUCT  |  178 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ENCINO LANDSCAPE, INC.
LONE STAR SITEWORK, LLC
ALTUS CONSTRUCTION LLC
PREPARING ROW
AC 1.000 $8,030.000 $15,000.000 $2,500.000 $30,000.000
REMOVING CONC (SIDEWALKS)
SY 74.000 $13.200 $15.000 $23.000 $21.060
REMOVING CONC (DRIVEWAYS)
SY 2,447.000 $19.800 $15.000 $26.000 $12.940
REMOVING CONC (CURB)
LF 3,645.000 $18.700 $5.000 $5.500 $14.040
REMOVING CONC (MISC)
SY 320.000 $24.200 $15.000 $18.000 $42.120
REMOVING STAB BASE AND ASPH PAV (3")
SY 1,549.000 $11.000 $20.000 $18.000 $8.190
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 400.000 $9.900 $20.000 $69.000 $51.380
FURNISHING AND PLACING TOPSOIL (4")
SY 5,353.000 $1.650 $1.000 $10.500 $1.540
BLOCK SODDING
SY 5,353.000 $4.400 $3.000 $20.800 $3.470
VEGETATIVE WATERING
MG 321.180 $16.500 $5.000 $110.000 $41.420
HMCL ACP TY-D AC-1.5
TON 5.000 $220.000 $100.000 $200.000 $421.170
FLEX PAVEMENT STRUCTURE REPAIR (2-8")
SY 1,593.000 $99.000 $100.000 $220.000 $105.290
RIPRAP (CONC) (CL B) (6")
CY 92.000 $522.500 $500.000 $625.000 $480.280
RIPRAP (STONE TY F)(GROUT)(6 IN)
CY 32.500 $550.000 $500.000 $375.000 $280.780
BEDDING MATERIAL (3 IN)
CY 6.000 $165.000 $100.000 $165.000 $163.650
RAIL (HANDRAIL)(TY B)
LF 459.000 $88.000 $150.000 $139.000 $113.080
CMP (GAL STL 24 IN)
LF 17.000 $93.500 $100.000 $80.000 $140.730
RC PIPE (CL III)(24 IN)
LF 68.000 $88.000 $100.000 $100.000 $153.460
RC PIPE (CL III)(30 IN)
LF 10.000 $110.000 $140.000 $150.000 $515.190
INLET (COMPL)(PCO)(5FT)(NONE)
EA 1.000 $7,150.000 $6,500.000 $6,500.000 $16,552.660
INLET (COMP) (TY SIDEWALK BRIDGE)
EA 14.000 $18,700.000 $16,500.000 $4,200.000 $21,664.050
SET (TY II) (24 IN) (CMP) (6: 1) (P)
EA 1.000 $1,650.000 $2,500.000 $2,850.000 $7,019.460
SET (TY II) (24 IN) (RCP) (6: 1) (C)
EA 4.000 $2,508.000 $2,500.000 $3,250.000 $3,005.730
ADJUSTING MANHOLES
EA 1.000 $572.000 $500.000 $1,250.000 $1,403.890
ADJUSTING MANHOLES (WATER VALVE BOX)
EA 8.000 $522.500 $500.000 $650.000 $1,403.890
ADJUSTING MANHOLES (WATER METER)
EA 7.000 $440.000 $500.000 $975.000 $1,403.890
REMOV STR (SET)
EA 1.000 $473.000 $500.000 $500.000 $1,123.110
REMOVE STR (BOLLARD)
EA 2.000 $104.500 $100.000 $320.000 $421.170
MOBILIZATION
LS 1.000 $267,877.250 $250,000.000 $80,000.000 $350,972.930
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $4,950.000 $6,000.000 $720.000 $28,077.830
TEMP SEDMT CONT FENCE (INSTALL)
LF 7,916.000 $2.750 $5.000 $8.750 $1.730
TEMP SEDMT CONT FENCE (REMOVE)
LF 7,916.000 $0.830 $1.000 $3.750 $0.850
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,584.000 $3.300 $5.000 $9.700 $4.260
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,584.000 $3.300 $1.000 $5.000 $1.300
COLORED TEXTURED CONC (6")
SY 20.000 $165.000 $200.000 $490.000 $407.330
REMOVE AND RELAY PAVERS
SY 38.000 $121.000 $200.000 $180.000 $124.160
CONC CURB (TY II)
LF 4,754.000 $14.300 $20.000 $38.100 $13.950
CONC CURB (TY C1)
LF 1,596.000 $77.000 $120.000 $96.000 $135.420
CONC CURB (TY F1)
LF 433.000 $110.000 $100.000 $114.000 $212.870
DRIVEWAYS (CONC)
SY 2,830.000 $82.500 $80.000 $95.000 $62.870
CONC SIDEWALKS (5")
SY 6,591.000 $66.000 $90.000 $81.000 $57.310
CURB RAMPS (TY 1)
EA 14.000 $2,200.000 $1,600.000 $1,650.000 $1,807.070
CURB RAMPS (TY 2)
EA 1.000 $2,200.000 $1,600.000 $1,870.000 $5,777.440
CURB RAMPS (TY 3)
EA 5.000 $2,475.000 $1,600.000 $2,450.000 $2,693.650
CURB RAMPS (TY 6)
EA 19.000 $2,200.000 $2,100.000 $2,770.000 $1,701.160
CURB RAMPS (TY 7)
EA 45.000 $2,200.000 $1,600.000 $1,825.000 $1,752.950
CURB RAMPS (TY 10)
EA 15.000 $1,980.000 $1,600.000 $1,825.000 $1,915.560
CONCRETE SIDEWALK (STEPS)
SY 1.000 $440.000 $1,000.000 $1,575.000 $2,976.810
RELOCATE EXISTING MAILBOX
EA 3.000 $715.000 $500.000 $350.000 $575.600
CONDT (PVC) (SCH 40) (1")
LF 75.000 $13.480 $20.000 $18.300 $9.130
CONDT (PVC) (SCH 40) (3")
LF 850.000 $18.700 $20.000 $34.700 $9.130
CONDT (PVC) (SCH 40) (3") (BORE)
LF 1,358.000 $33.000 $45.000 $105.000 $13.900
GROUND BOX TY BATTERY (162915)
EA 6.000 $1,254.000 $2,000.000 $2,310.000 $1,333.700
GROUND BOX TY D (162922)
EA 17.000 $1,254.000 $800.000 $1,770.000 $1,193.310
GROUND BOX TY D (162922)W/APRON
EA 6.000 $1,336.500 $1,000.000 $1,980.000 $1,193.310
REMOVE GROUND BOX
EA 20.000 $181.500 $200.000 $450.000 $210.580
ALUMINUM SIGNS (TY A)
SF 106.000 $44.000 $40.000 $80.000 $42.600
REPLACE EXISTING ALUMINUM SIGNS(TY A)
SF 1.000 $49.500 $40.000 $450.000 $62.310
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 84.000 $506.000 $500.000 $350.000 $581.770
REMOVE SM RD SN SUP&AM
EA 4.000 $104.500 $100.000 $100.000 $119.880
INSTL DEL ASSM (D-SW)SZ 2(WC)GND
EA 4.000 $55.000 $100.000 $100.000 $87.600
INSTL OM ASSM (OM-2X)(WC)GND
EA 2.000 $93.500 $100.000 $800.000 $108.860
REMOVE DELIN & OBJECT MARKER ASSMS
EA 4.000 $22.000 $25.000 $100.000 $24.070
PREFAB PAV MRK TY B (W)(24")(SLD)
LF 6,476.000 $27.500 $30.000 $44.000 $56.160
ELIM EXT PAV MRK & MRKS (4")
LF 267.000 $0.330 $1.000 $11.000 $14.040
ELIM EXT PAV MRK & MRKS (8")
LF 1,186.000 $1.270 $1.000 $5.500 $7.020
ELIM EXT PAV MRK & MRKS (12")
LF 2,404.000 $2.090 $4.000 $5.500 $7.020
ELIM EXT PAV MRK & MRKS (24")
LF 1,453.000 $3.850 $5.000 $5.500 $7.020
VEH SIG SEC (12")LED(YEL)
EA 8.000 $286.000 $500.000 $390.000 $522.440
VEH SIG SEC (12")LED(RED)
EA 2.000 $286.000 $500.000 $390.000 $510.430
PED SIG SEC (LED)(COUNTDOWN)
EA 11.000 $660.000 $1,000.000 $1,050.000 $1,255.560
TRF SIG CBL (TY A)(12 AWG)(2 CONDR)
LF 5,492.000 $1.380 $2.000 $2.200 $3.850
TRF SIG CBL (TY A)(12 AWG)(4 CONDR)
LF 4,551.000 $2.480 $3.000 $3.200 $4.460
TRF SIG CBL (TY A)(14 AWG)(5 CONDR)
LF 225.000 $2.200 $4.000 $2.700 $4.360
INSTL RDSD FLSH BCN ASSM (SOLAR PWRD)
EA 6.000 $4,070.000 $9,999.000 $8,700.000 $15,397.130
PED POLE ASSEMBLY
EA 13.000 $2,310.000 $2,100.000 $3,240.000 $4,370.410
RELOCATE PED POLE ASSEMBLY
EA 5.000 $2,310.000 $1,200.000 $2,940.000 $3,893.930
REMOVE PED POLE ASSEMBLY
EA 4.000 $550.000 $500.000 $300.000 $997.830
PED DETECT PUSH BUTTON (APS)
EA 16.000 $918.500 $1,100.000 $1,176.000 $1,697.870
PED DETECTOR CONTROLLER UNIT
EA 2.000 $3,806.000 $5,000.000 $4,500.000 $6,424.490
REMOVAL OF SIGNAL HEAD ASSM
EA 11.000 $132.000 $100.000 $372.000 $253.180
REMOVAL OF SIGNAL RELATED SIGNS
EA 6.000 $187.000 $100.000 $138.000 $421.170
REMOVAL OF PEDESTRIAN PUSH BUTTONS
EA 6.000 $82.500 $100.000 $300.000 $153.580
REPLACE OF PEDESTRIAN PUSH BUTTONS
EA 1.000 $242.000 $300.000 $1,350.000 $463.280
RELOCATE OF PEDESTRIAN PUSH BUTTON
EA 10.000 $445.500 $300.000 $930.000 $853.330
TREE PROTECTION
EA 23.000 $473.000 $500.000 $275.000 $421.170
Totals: $2,734,692.330 $2,965,162.900 $3,358,541.000 $3,531,467.246