PREPARING ROW
|
AC
|
1.000
|
$8,030.000
|
$15,000.000
|
$2,500.000
|
$30,000.000
|
|
|
REMOVING CONC (SIDEWALKS)
|
SY
|
74.000
|
$13.200
|
$15.000
|
$23.000
|
$21.060
|
|
|
REMOVING CONC (DRIVEWAYS)
|
SY
|
2,447.000
|
$19.800
|
$15.000
|
$26.000
|
$12.940
|
|
|
REMOVING CONC (CURB)
|
LF
|
3,645.000
|
$18.700
|
$5.000
|
$5.500
|
$14.040
|
|
|
REMOVING CONC (MISC)
|
SY
|
320.000
|
$24.200
|
$15.000
|
$18.000
|
$42.120
|
|
|
REMOVING STAB BASE AND ASPH PAV (3")
|
SY
|
1,549.000
|
$11.000
|
$20.000
|
$18.000
|
$8.190
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY B)
|
CY
|
400.000
|
$9.900
|
$20.000
|
$69.000
|
$51.380
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
5,353.000
|
$1.650
|
$1.000
|
$10.500
|
$1.540
|
|
|
BLOCK SODDING
|
SY
|
5,353.000
|
$4.400
|
$3.000
|
$20.800
|
$3.470
|
|
|
VEGETATIVE WATERING
|
MG
|
321.180
|
$16.500
|
$5.000
|
$110.000
|
$41.420
|
|
|
HMCL ACP TY-D AC-1.5
|
TON
|
5.000
|
$220.000
|
$100.000
|
$200.000
|
$421.170
|
|
|
FLEX PAVEMENT STRUCTURE REPAIR (2-8")
|
SY
|
1,593.000
|
$99.000
|
$100.000
|
$220.000
|
$105.290
|
|
|
RIPRAP (CONC) (CL B) (6")
|
CY
|
92.000
|
$522.500
|
$500.000
|
$625.000
|
$480.280
|
|
|
RIPRAP (STONE TY F)(GROUT)(6 IN)
|
CY
|
32.500
|
$550.000
|
$500.000
|
$375.000
|
$280.780
|
|
|
BEDDING MATERIAL (3 IN)
|
CY
|
6.000
|
$165.000
|
$100.000
|
$165.000
|
$163.650
|
|
|
RAIL (HANDRAIL)(TY B)
|
LF
|
459.000
|
$88.000
|
$150.000
|
$139.000
|
$113.080
|
|
|
CMP (GAL STL 24 IN)
|
LF
|
17.000
|
$93.500
|
$100.000
|
$80.000
|
$140.730
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
68.000
|
$88.000
|
$100.000
|
$100.000
|
$153.460
|
|
|
RC PIPE (CL III)(30 IN)
|
LF
|
10.000
|
$110.000
|
$140.000
|
$150.000
|
$515.190
|
|
|
INLET (COMPL)(PCO)(5FT)(NONE)
|
EA
|
1.000
|
$7,150.000
|
$6,500.000
|
$6,500.000
|
$16,552.660
|
|
|
INLET (COMP) (TY SIDEWALK BRIDGE)
|
EA
|
14.000
|
$18,700.000
|
$16,500.000
|
$4,200.000
|
$21,664.050
|
|
|
SET (TY II) (24 IN) (CMP) (6: 1) (P)
|
EA
|
1.000
|
$1,650.000
|
$2,500.000
|
$2,850.000
|
$7,019.460
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (C)
|
EA
|
4.000
|
$2,508.000
|
$2,500.000
|
$3,250.000
|
$3,005.730
|
|
|
ADJUSTING MANHOLES
|
EA
|
1.000
|
$572.000
|
$500.000
|
$1,250.000
|
$1,403.890
|
|
|
ADJUSTING MANHOLES (WATER VALVE BOX)
|
EA
|
8.000
|
$522.500
|
$500.000
|
$650.000
|
$1,403.890
|
|
|
ADJUSTING MANHOLES (WATER METER)
|
EA
|
7.000
|
$440.000
|
$500.000
|
$975.000
|
$1,403.890
|
|
|
REMOV STR (SET)
|
EA
|
1.000
|
$473.000
|
$500.000
|
$500.000
|
$1,123.110
|
|
|
REMOVE STR (BOLLARD)
|
EA
|
2.000
|
$104.500
|
$100.000
|
$320.000
|
$421.170
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$267,877.250
|
$250,000.000
|
$80,000.000
|
$350,972.930
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
12.000
|
$4,950.000
|
$6,000.000
|
$720.000
|
$28,077.830
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
7,916.000
|
$2.750
|
$5.000
|
$8.750
|
$1.730
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
7,916.000
|
$0.830
|
$1.000
|
$3.750
|
$0.850
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
1,584.000
|
$3.300
|
$5.000
|
$9.700
|
$4.260
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
1,584.000
|
$3.300
|
$1.000
|
$5.000
|
$1.300
|
|
|
COLORED TEXTURED CONC (6")
|
SY
|
20.000
|
$165.000
|
$200.000
|
$490.000
|
$407.330
|
|
|
REMOVE AND RELAY PAVERS
|
SY
|
38.000
|
$121.000
|
$200.000
|
$180.000
|
$124.160
|
|
|
CONC CURB (TY II)
|
LF
|
4,754.000
|
$14.300
|
$20.000
|
$38.100
|
$13.950
|
|
|
CONC CURB (TY C1)
|
LF
|
1,596.000
|
$77.000
|
$120.000
|
$96.000
|
$135.420
|
|
|
CONC CURB (TY F1)
|
LF
|
433.000
|
$110.000
|
$100.000
|
$114.000
|
$212.870
|
|
|
DRIVEWAYS (CONC)
|
SY
|
2,830.000
|
$82.500
|
$80.000
|
$95.000
|
$62.870
|
|
|
CONC SIDEWALKS (5")
|
SY
|
6,591.000
|
$66.000
|
$90.000
|
$81.000
|
$57.310
|
|
|
CURB RAMPS (TY 1)
|
EA
|
14.000
|
$2,200.000
|
$1,600.000
|
$1,650.000
|
$1,807.070
|
|
|
CURB RAMPS (TY 2)
|
EA
|
1.000
|
$2,200.000
|
$1,600.000
|
$1,870.000
|
$5,777.440
|
|
|
CURB RAMPS (TY 3)
|
EA
|
5.000
|
$2,475.000
|
$1,600.000
|
$2,450.000
|
$2,693.650
|
|
|
CURB RAMPS (TY 6)
|
EA
|
19.000
|
$2,200.000
|
$2,100.000
|
$2,770.000
|
$1,701.160
|
|
|
CURB RAMPS (TY 7)
|
EA
|
45.000
|
$2,200.000
|
$1,600.000
|
$1,825.000
|
$1,752.950
|
|
|
CURB RAMPS (TY 10)
|
EA
|
15.000
|
$1,980.000
|
$1,600.000
|
$1,825.000
|
$1,915.560
|
|
|
CONCRETE SIDEWALK (STEPS)
|
SY
|
1.000
|
$440.000
|
$1,000.000
|
$1,575.000
|
$2,976.810
|
|
|
RELOCATE EXISTING MAILBOX
|
EA
|
3.000
|
$715.000
|
$500.000
|
$350.000
|
$575.600
|
|
|
CONDT (PVC) (SCH 40) (1")
|
LF
|
75.000
|
$13.480
|
$20.000
|
$18.300
|
$9.130
|
|
|
CONDT (PVC) (SCH 40) (3")
|
LF
|
850.000
|
$18.700
|
$20.000
|
$34.700
|
$9.130
|
|
|
CONDT (PVC) (SCH 40) (3") (BORE)
|
LF
|
1,358.000
|
$33.000
|
$45.000
|
$105.000
|
$13.900
|
|
|
GROUND BOX TY BATTERY (162915)
|
EA
|
6.000
|
$1,254.000
|
$2,000.000
|
$2,310.000
|
$1,333.700
|
|
|
GROUND BOX TY D (162922)
|
EA
|
17.000
|
$1,254.000
|
$800.000
|
$1,770.000
|
$1,193.310
|
|
|
GROUND BOX TY D (162922)W/APRON
|
EA
|
6.000
|
$1,336.500
|
$1,000.000
|
$1,980.000
|
$1,193.310
|
|
|
REMOVE GROUND BOX
|
EA
|
20.000
|
$181.500
|
$200.000
|
$450.000
|
$210.580
|
|
|
ALUMINUM SIGNS (TY A)
|
SF
|
106.000
|
$44.000
|
$40.000
|
$80.000
|
$42.600
|
|
|
REPLACE EXISTING ALUMINUM SIGNS(TY A)
|
SF
|
1.000
|
$49.500
|
$40.000
|
$450.000
|
$62.310
|
|
|
RELOCATE SM RD SN SUP&AM TY 10BWG
|
EA
|
84.000
|
$506.000
|
$500.000
|
$350.000
|
$581.770
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
4.000
|
$104.500
|
$100.000
|
$100.000
|
$119.880
|
|
|
INSTL DEL ASSM (D-SW)SZ 2(WC)GND
|
EA
|
4.000
|
$55.000
|
$100.000
|
$100.000
|
$87.600
|
|
|
INSTL OM ASSM (OM-2X)(WC)GND
|
EA
|
2.000
|
$93.500
|
$100.000
|
$800.000
|
$108.860
|
|
|
REMOVE DELIN & OBJECT MARKER ASSMS
|
EA
|
4.000
|
$22.000
|
$25.000
|
$100.000
|
$24.070
|
|
PREFAB PAV MRK TY B (W)(24")(SLD)
|
LF
|
6,476.000
|
$27.500
|
$30.000
|
$44.000
|
$56.160
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
267.000
|
$0.330
|
$1.000
|
$11.000
|
$14.040
|
|
|
ELIM EXT PAV MRK & MRKS (8")
|
LF
|
1,186.000
|
$1.270
|
$1.000
|
$5.500
|
$7.020
|
|
|
ELIM EXT PAV MRK & MRKS (12")
|
LF
|
2,404.000
|
$2.090
|
$4.000
|
$5.500
|
$7.020
|
|
|
ELIM EXT PAV MRK & MRKS (24")
|
LF
|
1,453.000
|
$3.850
|
$5.000
|
$5.500
|
$7.020
|
|
|
VEH SIG SEC (12")LED(YEL)
|
EA
|
8.000
|
$286.000
|
$500.000
|
$390.000
|
$522.440
|
|
|
VEH SIG SEC (12")LED(RED)
|
EA
|
2.000
|
$286.000
|
$500.000
|
$390.000
|
$510.430
|
|
|
PED SIG SEC (LED)(COUNTDOWN)
|
EA
|
11.000
|
$660.000
|
$1,000.000
|
$1,050.000
|
$1,255.560
|
|
|
TRF SIG CBL (TY A)(12 AWG)(2 CONDR)
|
LF
|
5,492.000
|
$1.380
|
$2.000
|
$2.200
|
$3.850
|
|
|
TRF SIG CBL (TY A)(12 AWG)(4 CONDR)
|
LF
|
4,551.000
|
$2.480
|
$3.000
|
$3.200
|
$4.460
|
|
|
TRF SIG CBL (TY A)(14 AWG)(5 CONDR)
|
LF
|
225.000
|
$2.200
|
$4.000
|
$2.700
|
$4.360
|
|
|
INSTL RDSD FLSH BCN ASSM (SOLAR PWRD)
|
EA
|
6.000
|
$4,070.000
|
$9,999.000
|
$8,700.000
|
$15,397.130
|
|
|
PED POLE ASSEMBLY
|
EA
|
13.000
|
$2,310.000
|
$2,100.000
|
$3,240.000
|
$4,370.410
|
|
|
RELOCATE PED POLE ASSEMBLY
|
EA
|
5.000
|
$2,310.000
|
$1,200.000
|
$2,940.000
|
$3,893.930
|
|
|
REMOVE PED POLE ASSEMBLY
|
EA
|
4.000
|
$550.000
|
$500.000
|
$300.000
|
$997.830
|
|
|
PED DETECT PUSH BUTTON (APS)
|
EA
|
16.000
|
$918.500
|
$1,100.000
|
$1,176.000
|
$1,697.870
|
|
|
PED DETECTOR CONTROLLER UNIT
|
EA
|
2.000
|
$3,806.000
|
$5,000.000
|
$4,500.000
|
$6,424.490
|
|
|
REMOVAL OF SIGNAL HEAD ASSM
|
EA
|
11.000
|
$132.000
|
$100.000
|
$372.000
|
$253.180
|
|
|
REMOVAL OF SIGNAL RELATED SIGNS
|
EA
|
6.000
|
$187.000
|
$100.000
|
$138.000
|
$421.170
|
|
|
REMOVAL OF PEDESTRIAN PUSH BUTTONS
|
EA
|
6.000
|
$82.500
|
$100.000
|
$300.000
|
$153.580
|
|
|
REPLACE OF PEDESTRIAN PUSH BUTTONS
|
EA
|
1.000
|
$242.000
|
$300.000
|
$1,350.000
|
$463.280
|
|
|
RELOCATE OF PEDESTRIAN PUSH BUTTON
|
EA
|
10.000
|
$445.500
|
$300.000
|
$930.000
|
$853.330
|
|
|
TREE PROTECTION
|
EA
|
23.000
|
$473.000
|
$500.000
|
$275.000
|
$421.170
|
|
Totals: |
$2,734,692.330
|
$2,965,162.900
|
$3,358,541.000
|
$3,531,467.246
|