Bid Cobra

TRAVIS VA (0914-00-393)

Items: 47

County: TRAVIS
Length: N/A
Highway: VA
District: AUSTIN
Control Number: 0914-00-393
DBE Goal: N/A
Project: STP 2017(768)TP
Guaranty: N/A
Time: 180 WORKING DAYS
Engineer's Estimate: $515,634.80
Date: 10/03/2017 (8 years ago)
Contract Number: N/A
Type: INSTALL SIDEWALKS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (11)
E
Engineer's Estimate
$515,634.80
1
$496,481.33
Over/Under Est: -3.71% -$19,153.47
Over/Under Est: -3.57% -$18,389.30
Amt Left: 0.15% $764.17
$504,284.00
Over/Under Est: -2.2% -$11,350.80
Amt Left: 1.57% $7,802.67
Delta: -1.42% -$7,038.50
Over/Under Est: 1.76% $9,058.60
Amt Left: 5.68% $28,212.07
Delta: -4.05% -$20,409.40
Over/Under Est: 2.08% $10,729.20
Amt Left: 6.02% $29,882.67
Delta: -0.32% -$1,670.60
$526,493.10
Over/Under Est: 2.11% $10,858.30
Amt Left: 6.04% $30,011.77
Delta: -0.02% -$129.10
Over/Under Est: 12.05% $62,126.20
Amt Left: 16.37% $81,279.67
Delta: -9.74% -$51,267.90
Over/Under Est: 23.91% $123,301.45
Amt Left: 28.69% $142,454.92
Delta: -10.59% -$61,175.25
Over/Under Est: 25.75% $132,800.03
Amt Left: 30.61% $151,953.50
Delta: -1.49% -$9,498.58
Over/Under Est: 27.39% $141,225.20
Amt Left: 32.3% $160,378.67
Delta: -1.30% -$8,425.17
Over/Under Est: 46.41% $239,300.40
Amt Left: 52.06% $258,453.87
Delta: -14.93% -$98,075.20

Bid Items & Bid Tabulations

47 Total 0 of 47
TRAVIS  |  VA  |  AUSTIN  |  0914-00-393  |  10/03/2017  |  $515,634.80  |  STP 2017(768)TP  |  INSTL SIDEWALKS  |  180 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TREVWAY, INC.
TI-ZACK CONCRETE, INC.
DENBOW COMPANY INC.
A GREATER AUSTIN DEVELOPMENT COMPANY, LTD.
HIGHWAY 19 CONSTRUCTION LLC
RELMCO, INC.
ENCINO LANDSCAPE, INC.
ROY JORGENSEN ASSOCIATES, INC.
PROJECT ALLIED RESOURCES, LLC
FNH CONSTRUCTION, LLC
AARON CONCRETE CONTRACTORS, L.P.
REMOVING CONC (RIPRAP)
SY 85.000 $30.000 $55.000 $25.000 $13.000 $13.000 $50.000 $33.000 $15.000 $37.000 $22.000 $20.000 $60.000
REMOVING CONC (SIDEWALKS)
SY 20.000 $50.000 $55.000 $25.000 $27.000 $13.000 $50.000 $92.000 $15.000 $52.000 $24.600 $20.000 $90.000
REMOVING CONC (DRIVEWAYS)
SY 89.000 $25.000 $55.000 $25.000 $13.000 $13.000 $50.000 $34.000 $15.000 $20.000 $26.800 $20.000 $100.000
REMOVING CONC (CURB AND GUTTER)
LF 42.000 $25.000 $35.400 $25.000 $22.000 $8.000 $10.000 $47.000 $10.000 $18.000 $16.800 $20.000 $20.000
REMOVING STAB BASE & ASPH PAV (0-6")
SY 41.000 $40.000 $100.000 $25.000 $13.000 $15.000 $25.000 $48.000 $15.000 $15.000 $26.000 $20.000 $25.000
EXCAVATION (SPECIAL)
CY 55.000 $100.000 $27.040 $40.000 $21.000 $20.000 $100.000 $42.000 $20.000 $60.000 $86.000 $40.000 $40.000
BACKFILL (TY A OR B)
CY 305.000 $20.000 $34.660 $40.000 $85.000 $20.000 $50.000 $35.000 $30.000 $75.000 $62.000 $50.000 $40.000
FURNISHING AND PLACING TOPSOIL (3")
SY 3,999.000 $3.500 $4.000 $3.000 $4.000 $4.000 $5.000 $5.500 $3.000 $1.750 $3.480 $4.500 $5.000
BLOCK SODDING
SY 3,999.000 $4.700 $7.000 $4.500 $4.500 $4.400 $5.000 $4.350 $5.000 $13.000 $6.100 $5.500 $5.000
VEGETATIVE WATERING
MG 81.000 $40.000 $50.000 $25.000 $17.000 $56.000 $50.000 $80.000 $20.000 $75.000 $1.210 $50.000 $30.000
CL C CONC (MISC)
CY 5.500 $750.000 $545.260 $1,000.000 $660.000 $280.000 $1,100.000 $1,631.500 $1,000.000 $1,500.000 $1,350.000 $1,100.000 $1,500.000
RIPRAP (CONC)(5 IN)
CY 64.000 $500.000 $300.000 $650.000 $517.000 $480.000 $500.000 $537.160 $800.000 $500.000 $1,010.000 $650.000 $550.000
RAIL (TY C223)
LF 37.000 $250.000 $144.660 $105.000 $202.500 $225.000 $150.000 $225.880 $100.000 $95.000 $167.000 $210.000 $500.000
RAIL (HANDRAIL)(TY D)
LF 61.000 $100.000 $153.000 $105.000 $121.000 $120.000 $110.000 $205.530 $150.000 $135.000 $172.000 $210.000 $165.000
RAIL (HANDRAIL)(TY E)
LF 114.000 $125.000 $147.000 $105.000 $113.000 $120.000 $110.000 $198.590 $120.000 $145.000 $78.000 $300.000 $150.000
CONC BOX CULV (7 FT X 6 FT)(EXTEND)
LF 100.000 $775.000 $800.000 $800.000 $630.000 $525.000 $700.000 $463.910 $1,500.000 $800.000 $719.000 $750.000 $1,800.000
RC PIPE (CL III)(18 IN)
LF 94.000 $100.000 $77.000 $80.000 $82.000 $130.000 $45.000 $50.700 $50.000 $75.000 $81.000 $85.000 $105.000
INLET (COMPL)(PSL)(FG)(3FTX3FT-3FTX3FT)
EA 1.000 $4,500.000 $4,041.000 $5,000.000 $3,100.000 $5,600.000 $500.000 $4,524.000 $5,000.000 $3,500.000 $4,630.000 $5,800.000 $4,000.000
WINGWALL (PW - 1) (HW=8 FT)
EA 1.000 $18,000.000 $16,000.000 $25,000.000 $17,000.000 $48,000.000 $16,000.000 $16,827.200 $7,500.000 $29,000.000 $24,400.000 $19,000.000 $35,000.000
SET (TY II) (18 IN) (RCP) (3: 1) (C)
EA 2.000 $1,000.000 $1,388.000 $1,000.000 $1,900.000 $1,700.000 $700.000 $1,251.250 $1,000.000 $400.000 $1,720.000 $1,850.000 $2,700.000
CAST-IN-PLACE TRENCH DRAIN
LF 2.000 $500.000 $757.000 $450.000 $2,155.000 $800.000 $300.000 $918.000 $100.000 $700.000 $3,660.000 $1,000.000 $1,500.000
REMOV STR (WINGWALL)
EA 1.000 $3,500.000 $5,000.000 $1,500.000 $2,600.000 $2,800.000 $1,000.000 $1,760.000 $2,000.000 $2,700.000 $3,280.000 $2,500.000 $2,500.000
REMOV STR (HEADWALL)
EA 1.000 $2,000.000 $5,000.000 $1,500.000 $1,200.000 $2,800.000 $500.000 $1,755.000 $1,000.000 $1,100.000 $2,170.000 $2,500.000 $2,500.000
REMOVE STR (BOLLARD)
EA 1.000 $462.000 $700.000 $500.000 $82.000 $1,100.000 $500.000 $850.000 $100.000 $100.000 $646.000 $100.000 $500.000
REMOV STR (RR TIMBER TIES)
EA 7.000 $195.000 $200.000 $100.000 $58.000 $840.000 $100.000 $850.000 $700.000 $20.000 $336.000 $1,100.000 $500.000
MOBILIZATION
LS 1.000 $60,000.000 $50,000.000 $59,000.000 $50,000.000 $52,469.340 $50,000.000 $50,000.000 $80,000.000 $60,000.000 $64,000.000 $65,000.000 $80,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $2,500.000 $1,263.000 $1,000.000 $2,000.000 $4,500.000 $5,000.000 $7,500.000 $3,000.000 $10,000.000 $7,650.000 $12,500.000 $2,500.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 40.000 $45.000 $28.000 $50.000 $31.000 $52.000 $55.000 $50.600 $50.000 $50.000 $80.000 $30.000 $50.000
ROCK FILTER DAMS (REMOVE)
LF 40.000 $13.000 $4.000 $5.000 $1.000 $11.000 $10.000 $11.000 $10.000 $20.000 $14.000 $15.000 $14.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,314.000 $3.000 $4.000 $1.000 $2.000 $2.500 $3.000 $2.480 $3.000 $11.000 $4.030 $4.000 $3.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,314.000 $1.000 $1.000 $0.500 $0.500 $0.590 $1.000 $0.550 $1.000 $1.000 $1.140 $2.000 $0.600
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 38.000 $8.000 $5.000 $5.000 $4.500 $5.600 $5.000 $5.500 $5.000 $5.000 $12.700 $12.000 $4.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 38.000 $1.500 $1.000 $1.000 $0.500 $2.800 $1.000 $2.750 $1.000 $5.000 $1.690 $8.000 $0.600
CONC CURB (TY II)
LF 824.000 $20.000 $6.320 $20.000 $32.000 $16.000 $25.000 $11.450 $10.000 $33.000 $20.700 $30.000 $25.000
DRIVEWAYS (CONC)
SY 217.000 $91.000 $75.000 $70.000 $93.000 $79.000 $75.000 $97.080 $70.000 $81.000 $110.000 $85.000 $110.000
CONC SIDEWALKS (5")
SY 1,743.000 $65.000 $70.000 $70.000 $68.000 $68.000 $75.000 $65.000 $60.000 $71.000 $83.000 $65.000 $80.000
CONC SIDEWALKS (6")
SY 153.000 $75.000 $66.000 $70.000 $72.000 $87.000 $75.000 $57.430 $70.000 $76.000 $90.000 $72.000 $90.000
CURB RAMPS (TY 2)
EA 1.000 $1,700.000 $1,500.000 $1,500.000 $1,720.000 $1,700.000 $1,100.000 $1,196.000 $2,000.000 $2,000.000 $2,960.000 $1,850.000 $1,500.000
CURB RAMPS (TY 7)
EA 6.000 $2,000.000 $1,500.000 $1,000.000 $1,650.000 $1,500.000 $1,100.000 $1,163.500 $1,500.000 $2,100.000 $2,430.000 $1,850.000 $2,000.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 4.000 $400.000 $195.000 $150.000 $497.000 $630.000 $350.000 $597.060 $300.000 $400.000 $602.000 $650.000 $500.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 4.000 $95.000 $315.000 $150.000 $17.000 $28.000 $20.000 $27.500 $50.000 $200.000 $28.900 $50.000 $20.000
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
LF 307.000 $6.000 $13.000 $10.000 $12.000 $12.500 $10.000 $12.100 $20.000 $11.000 $13.200 $20.000 $20.000
ELIM EXT PAV MRK & MRKS (24")
LF 40.000 $9.000 $11.000 $10.000 $10.000 $10.000 $1.000 $9.900 $10.000 $5.000 $9.700 $20.000 $20.000
TREE REMOVAL (4" - 12" DIA)
EA 1.000 $460.000 $700.000 $150.000 $970.000 $220.000 $1,000.000 $1,100.000 $500.000 $200.000 $1,490.000 $1,000.000 $1,000.000
TREE REMOVAL (12" - 18" DIA)
EA 1.000 $850.000 $800.000 $500.000 $970.000 $510.000 $1,000.000 $1,600.000 $1,000.000 $300.000 $2,260.000 $1,000.000 $2,500.000
TREE TRIMMING AND BRUSH REMOVAL
LF 104.000 $52.500 $12.000 $16.000 $56.000 $110.000 $50.000 $50.000 $20.000 $30.000 $30.400 $125.000 $150.000
TREE PROTECTION
EA 11.000 $500.000 $350.000 $150.000 $139.000 $12.500 $500.000 $450.000 $200.000 $250.000 $246.000 $500.000 $300.000
Totals: $515,634.800 $496,481.330 $497,245.500 $504,284.000 $524,693.400 $526,364.000 $526,493.100 $577,761.000 $638,936.250 $648,434.830 $656,860.000 $754,935.200