TRAVIS US 290 (0114-01-068)

Items: 28

County: TRAVIS
Length: 0.0000 MILES
Highway: US 290
District: AUSTIN
Control Number: 0114-01-068
DBE Goal: 0.0%
Project: BR 2024(495)
Guaranty: $16,000.00
Time: 48 WORKING DAYS
Engineer's Estimate: $801,600.00
Date: 12/04/2024 (1 year ago)
Contract Number: 12243220
Type: BRIDGE MAINTENANCE
Project ID: A00197898
Project Description: RAIL REPAIR, CONCRETE STRUCTURAL REPAIR; JOINT REPAIR, BEARING REPLACEMENT; CLEANING/SEALING EXPANSION JOINTS; INSTALL SHEAR KEY, DOWNSPOUT CLEANING.
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$801,600.00
$768,495.00
Over/Under Est: -4.13% -$33,105.00
Over/Under Est: 2.61% $20,920.00
Amt Left: 7.03% $54,025.00
Over/Under Est: 24.49% $196,276.00
Amt Left: 29.85% $229,381.00
Delta: -21.32% -$175,356.00
$1,295,812.00
Over/Under Est: 61.65% $494,212.00
Amt Left: 68.62% $527,317.00
Delta: -29.86% -$297,936.00
Over/Under Est: 65.21% $522,710.00
Amt Left: 72.33% $555,815.00
Delta: -2.20% -$28,498.00

Bid Items & Bid Tabulations

28 Total 0 of 28
TRAVIS  |  US 290  |  AUSTIN  |  0114-01-068  |  12/04/2024  |  $801,600.00  |  BR 2024(495)  |  BRIDGE MAINT  |  48 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
AAD CONTRACTING INC.
TAYLOR CONTRACTING LLC
ROY JORGENSEN ASSOCIATES, INC.
ICOS MANAGEMENT, LLC
SOUTHERN ROAD & BRIDGE, LLC
PREPARING ROW
AC 0.150 $30,000.000 $10,000.000 $200,000.000 $100,000.000 $20,000.000 $65,000.000
SHEAR KEY
CY 1.000 $8,500.000 $1,400.000 $500.000 $24,000.000 $4,500.000 $50,000.000
BLAST FINISH
SF 3,600.000 $9.000 $12.000 $6.000 $4.000 $8.000 $32.000
SURFACE WATERPROOFING FINISH
SF 11,060.000 $10.000 $2.000 $4.000 $4.000 $16.000 $21.000
PENETRATING CONCRETE SURFACE TREATMENT
SY 1,350.000 $17.500 $7.000 $6.000 $20.000 $16.000 $32.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 23.000 $450.000 $275.000 $1,000.000 $350.000 $500.000 $1,150.000
CONC STR REPR(REMOVE AND REPL PEDESTAL)
CY 1.000 $7,000.000 $2,500.000 $7,500.000 $42,500.000 $6,500.000 $42,500.000
MOBILIZATION
LS 1.000 $60,325.000 $100,000.000 $60,000.000 $99,000.000 $150,000.000 $115,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $20,000.000 $10,000.000 $90,000.000 $6,500.000 $10,000.000 $72,500.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 1,000.000 $10.000 $4.000 $6.500 $20.000 $1.000 $25.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,000.000 $2.000 $1.000 $1.250 $5.000 $1.000 $25.000
CONDT (RM) (3/4")
LF 1.000 $300.000 $50.000 $5,000.000 $500.000 $500.000 $250.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 1.000 $1,100.000 $1,000.000 $950.000 $1,500.000 $800.000 $9,500.000
IN BRIDGE MNT CLEARANCE SGN ASSM(TY S)
EA 1.000 $4,500.000 $2,700.000 $2,900.000 $4,200.000 $8,500.000 $9,500.000
GRAFFITI REMOVAL (BLAST CLEANING)
SF 360.000 $20.000 $5.000 $35.000 $1.000 $20.000 $18.000
DRAIN INLET CLEANING
EA 18.000 $750.000 $200.000 $150.000 $250.000 $1,200.000 $1,500.000
DOWNSPOUT CLEANING
EA 18.000 $300.000 $200.000 $150.000 $250.000 $2,500.000 $1,500.000
CONCRETE RAIL REPAIR (IN-KIND)
LF 18.000 $850.000 $200.000 $800.000 $1,100.000 $3,200.000 $950.000
CONCRETE RAIL REPAIR (MISC)
LF 3.000 $1,000.000 $200.000 $2,000.000 $1,100.000 $4,000.000 $950.000
CONC RAIL REPAIR(REMOVE AND REPL RAIL)
LF 15.000 $1,200.000 $350.000 $1,000.000 $750.000 $5,000.000 $950.000
REP STL BRIDGE MEMBER (TIGHTEN MEMBER)
EA 3.000 $8,000.000 $20,000.000 $10,000.000 $4,500.000 $4,000.000 $2,500.000
REP STL BRDG MEMB (WELD REPAIR)
EA 1.000 $6,000.000 $30,000.000 $40,000.000 $8,500.000 $16,000.000 $6,500.000
BRIDGE JOINT REPAIR (SEJ)
LF 116.000 $800.000 $500.000 $625.000 $1,200.000 $600.000 $650.000
REPLACE ELASTOMERIC BEARING PADS
EA 19.000 $10,000.000 $12,000.000 $4,000.000 $14,000.000 $21,000.000 $4,480.000
REPLACE ELASTOMERIC BEARING PADS (LARGE
EA 4.000 $10,000.000 $15,000.000 $12,500.000 $18,000.000 $24,000.000 $9,500.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $9,000.000 $7,000.000 $1.000 $4,000.000 $10,000.000 $5,000.000
TMA (STATIONARY)
DAY 76.000 $100.000 $350.000 $250.000 $1,500.000 $1.000 $500.000
TMA (MOBILE OPERATION)
DAY 76.000 $100.000 $450.000 $1.000 $1.000 $1.000 $500.000
Totals: $801,600.000 $768,495.000 $822,520.000 $997,876.000 $1,295,812.000 $1,324,310.000