TRAVIS SL 360 (0113-13-195)

Items: 69

County: TRAVIS
Length: 0.0000 MILES
Highway: SL 360
District: AUSTIN
Control Number: 0113-13-195
DBE Goal: 0.0%
Project: CC 113-13-195
Guaranty: $100,000.00
Time: 141 WORKING DAYS
Engineer's Estimate: $6,572,485.59
Date: 05/01/2025 (1 year ago)
Contract Number: 5253005
Type: EMBANKMENT STABILIZATION
Project ID: A00212134
Project Description: ROCK EXCAVATION FOR STABILIZATION OF SLOPE
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
KYLE RUSSELL
JEREMY MIKES
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$6,572,485.59
$6,242,242.00
Over/Under Est: -5.02% -$330,243.59
Over/Under Est: 12.52% $822,846.33
Amt Left: 18.47% $1,153,089.92
Over/Under Est: 30.74% $2,020,254.41
Amt Left: 37.65% $2,350,498.00
Delta: -16.19% -$1,197,408.08
$9,730,931.09
Over/Under Est: 48.06% $3,158,445.50
Amt Left: 55.89% $3,488,689.09
Delta: -13.25% -$1,138,191.09
Subcontractor Percentage Amount
ENVIRONMENTAL SAFETY SERVICES, INC. 1.30% $81,149.15
TEXAS MATERIALS GROUP, INC. 1.18% $73,658.46
STRIPE IT UP, LLC 0.88% $54,931.73
RODD FRANK HOLDINGS LLC 0.65% $40,574.57
Total: 4.01% $250,313.91

Bid Items & Bid Tabulations

69 Total 0 of 69
TRAVIS  |  SL 360  |  AUSTIN  |  0113-13-195  |  05/01/2025  |  $6,572,485.59  |  CC 113-13-195  |  EMBANKMENT STABILIZATION  |  141 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
JORDAN FOSTER CONSTRUCTION, LLC
HARPER BROTHERS CONSTRUCTION LLC
GREY SKY CONSTRUCTION LLC
DAN WILLIAMS COMPANY
PREPARING ROW
STA 12.200 $13,000.000 $51,000.000 $9,000.000 $50,000.000 $70,000.000
TREE PROTECTION (INSTALL)
AC 1.370 $12,000.000 $15,000.000 $12,375.000 $15,000.000 $20,000.000
TREE PROTECTION (REMOVE)
AC 1.370 $5,000.000 $4,000.000 $3,500.000 $5,000.000 $5,000.000
EXCAV (SPECIAL)
CY 155,105.000 $32.500 $21.000 $39.500 $40.000 $47.000
FURN & PLACE TOPSOIL (4")
SY 5,716.000 $3.500 $15.000 $5.000 $10.000 $2.000
ROLL SODDING
SY 5,716.000 $4.500 $10.000 $7.000 $10.000 $7.000
BROADCAST SEED (TEMP_WARM_COOL)
SY 5,716.000 $0.400 $0.240 $0.200 $1.000 $0.200
VEGETATIVE WATERING
TGL 97.000 $45.000 $155.000 $75.000 $50.000 $20.000
RIPRAP (CONC)(5 IN)
CY 30.000 $850.000 $1,350.000 $950.000 $650.000 $750.000
RIPRAP (STONE COMMON)(GROUT)(6 IN)
CY 826.000 $175.000 $300.000 $275.000 $185.000 $100.000
MOBILIZATION
LS 1.000 $478,850.780 $624,000.000 $292,500.000 $800,000.000 $950,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $12,000.000 $58,000.000 $10,000.000 $8,500.000 $15,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $12,250.000 $30,000.000 $21,500.000 $16,500.000 $10,000.000
TMA (STATIONARY)
DAY 317.000 $250.000 $465.000 $25.000 $250.000 $1.000
TMA (MOBILE OPERATION)
DAY 31.000 $380.000 $975.000 $300.000 $550.000 $450.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 224.000 $35.000 $47.000 $37.000 $40.000 $37.000
CONSTRUCTION EXITS (REMOVE)
SY 224.000 $15.000 $25.000 $21.000 $20.000 $21.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,080.000 $4.000 $8.000 $3.500 $4.000 $3.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,080.000 $1.000 $1.000 $0.600 $2.000 $0.060
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 240.000 $6.500 $10.000 $5.850 $18.000 $7.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 240.000 $1.750 $1.500 $1.000 $9.000 $1.000
CONSTRUCTING DETOURS
SY 660.000 $175.000 $200.000 $150.000 $50.000 $155.000
PCTB (FUR&INST)(F-SHAPE OR SNGL SLP)TY1
LF 1,410.000 $70.000 $100.000 $75.000 $100.000 $25.000
PCTB (REMOVE)(F-SHAPE OR SNGL SLP)TY1
LF 1,410.000 $15.000 $21.000 $30.000 $30.000 $10.000
CRASH CUSH ATTEN (REMOVE)
EA 1.000 $1,500.000 $2,313.760 $600.000 $3,000.000 $1,000.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 1.000 $12,000.000 $24,000.000 $8,500.000 $21,000.000 $5,000.000
WIRE FENCE (TY B)
LF 1,470.000 $42.000 $28.000 $25.000 $5.000 $25.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 3.000 $700.000 $910.000 $860.000 $1,500.000 $800.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 4.000 $800.000 $1,200.000 $1,020.000 $1,500.000 $1,200.000
WK ZN PAV MRK REMOV (W)6"(BRK)
LF 190.000 $1.400 $1.500 $1.090 $2.000 $2.500
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 2,928.000 $1.200 $1.000 $0.800 $2.000 $1.600
WK ZN PAV MRK REMOV (W)8"(DOT)
LF 102.000 $1.600 $2.500 $2.000 $6.000 $2.050
WK ZN PAV MRK REMOV (W)8"(SLD)
LF 2,406.000 $1.500 $2.000 $1.520 $6.000 $1.600
WK ZN PAV MRK REMOV (W)12"(SLD)
LF 100.000 $7.250 $6.000 $5.000 $10.000 $10.600
WK ZN PAV MRK REMOV (W)(ARROW)
EA 4.000 $225.000 $210.000 $175.000 $250.000 $205.000
WK ZN PAV MRK REMOV (W)(WORD)
EA 4.000 $240.000 $275.000 $225.000 $250.000 $205.000
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 1,741.000 $2.500 $1.000 $0.800 $1.000 $1.600
REFL PAV MRK TY I (W)6"(DOT)(090MIL)
LF 74.000 $1.500 $3.700 $3.000 $3.000 $2.500
REFL PAV MRK TY I (W)8"(DOT)(090MIL)
LF 360.000 $2.150 $3.700 $3.000 $6.000 $2.500
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 1,243.000 $1.000 $1.600 $1.250 $6.000 $2.500
REFL PAV MRK TY I (W)12"(SLD)(090MIL)
LF 300.000 $4.300 $5.000 $4.000 $10.000 $2.500
REFL PAV MRK TY I (W)(ARROW)(090MIL)
EA 4.000 $250.000 $185.000 $150.000 $250.000 $250.000
REFL PAV MRK TY I (W)(WORD)(090MIL)
EA 4.000 $350.000 $220.000 $175.000 $250.000 $250.000
RE PM TY II (W) 6" (BRK)
LF 598.000 $1.750 $1.000 $0.750 $1.000 $0.770
RE PM TY II (W) 6" (DOT)
LF 74.000 $0.300 $2.500 $2.000 $1.000 $0.770
RE PM TY II (W) 6" (SLD)
LF 1,999.000 $1.200 $0.500 $0.400 $1.000 $0.770
RE PM TY II (W) 8" (DOT)
LF 360.000 $1.000 $1.500 $1.000 $4.000 $0.770
RE PM TY II (W) 8" (SLD)
LF 1,243.000 $1.400 $1.000 $0.650 $4.000 $0.770
RE PM TY II (W) 12" (SLD)
LF 300.000 $2.000 $6.000 $5.000 $10.000 $1.600
RE PM TY II (W) (ARROW)
EA 4.000 $85.000 $150.000 $85.000 $250.000 $106.000
RE PM TY II (W) (WORD)
EA 4.000 $120.000 $150.000 $95.000 $250.000 $106.000
RE PM TY II (Y) 6" (SLD)
LF 2,338.000 $1.150 $0.900 $0.650 $1.000 $0.770
REFL PAV MRK TY I (W)6"(BRK)(090MIL)
LF 598.000 $0.750 $1.000 $0.750 $1.000 $2.500
REFL PAV MRK TY I (W)6"(SLD)(090MIL)
LF 1,999.000 $3.500 $1.000 $0.750 $1.000 $2.050
REFL PAV MRK TY I (Y)6"(SLD)(090MIL)
LF 2,338.000 $2.500 $1.000 $0.750 $1.000 $2.050
REFL PAV MRKR TY I-C
EA 13.000 $8.000 $8.000 $6.000 $6.000 $7.000
REFL PAV MRKR TY II-C-R
EA 136.000 $7.500 $8.000 $6.000 $6.000 $7.000
ELIM EXT PM & MRKS (4")
LF 5,946.000 $0.400 $1.000 $0.500 $1.000 $1.060
ELIM EXT PM & MRKS (8")
LF 1,102.000 $0.750 $1.200 $0.750 $6.000 $1.060
ELIM EXT PM & MRKS (ARROW)
EA 3.000 $90.000 $125.000 $100.000 $250.000 $70.000
ELIM EXT PM & MRKS (WORD)
EA 3.000 $90.000 $160.000 $125.000 $250.000 $70.000
PAV SURF PREP FOR MRK (6")
LF 5,009.000 $0.640 $0.200 $0.120 $1.000 $0.160
PAV SURF PREP FOR MRK (8")
LF 1,603.000 $0.850 $0.300 $0.240 $4.000 $0.160
PAV SURF PREP FOR MRK (12")
LF 300.000 $1.000 $0.500 $0.360 $10.000 $0.700
PAV SURF PREP FOR MRK (ARROW)
EA 4.000 $48.000 $65.000 $50.000 $250.000 $5.200
PAV SURF PREP FOR MRK (WORD)
EA 4.000 $50.000 $65.000 $50.000 $250.000 $5.200
FULL - WIDTH MOWING
CYC 1.000 $4,500.000 $4,000.000 $1,500.000 $5,000.000 $1,200.000
LITTER REMOVAL
CYC 1.000 $2,500.000 $9,000.000 $3,500.000 $5,000.000 $600.000
CLEANING / SWEEPING (OUTSIDE MAIN LANE)
MI 12.000 $2,500.000 $3,500.000 $500.000 $5,000.000 $250.000
Totals: $6,572,485.590 $6,242,242.000 $7,395,331.920 $8,592,740.000 $9,730,931.090
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $60,936.35
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $35,000.00
ENVIRONMENTAL: CONTRACTOR FORCE ACCOUNT WORK (NONPART) $5,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $7,000.00
CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $12,000.00
Total: $119,936.35