TRAVIS IH 35 (0015-13-414)

Items: 26

County: TRAVIS
Length: N/A
Highway: IH 35
District: AUSTIN
Control Number: 0015-13-414
DBE Goal: N/A
Project: NH 2019(992)
Guaranty: N/A
Time: 63 WORKING DAYS
Engineer's Estimate: $227,301.55
Date: 06/04/2019 (7 years ago)
Contract Number: N/A
Type: LANDSCAPE DEVELOPMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$227,301.55
$246,618.00
Over/Under Est: 8.5% $19,316.45
Over/Under Est: 10.54% $23,949.89
Amt Left: 1.88% $4,633.44
Over/Under Est: 17.86% $40,588.20
Amt Left: 8.63% $21,271.75
Delta: -6.62% -$16,638.31
Over/Under Est: 20.72% $47,087.55
Amt Left: 11.26% $27,771.10
Delta: -2.43% -$6,499.35
Over/Under Est: 97.46% $221,521.45
Amt Left: 81.99% $202,205.00
Delta: -63.57% -$174,433.90

Bid Items & Bid Tabulations

26 Total 0 of 26
TRAVIS  |  IH 35  |  AUSTIN  |  0015-13-414  |  06/04/2019  |  $227,301.55  |  NH 2019(992)  |  LANDSCAPE DEVELOPMENT  |  63 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS ROAD CONSTRUCTION, LLC
TIGHT LINE CONSTRUCTION, LLC
ENCINO LANDSCAPE, INC.
APEX LANDSCAPE & IRRIGATION, LLC
CENTRAL NORTH CONSTRUCTION, LLC
GENERAL USE COMPOST (4")
SY 1,951.000 $4.000 $5.000 $4.000 $3.000 $3.600 $4.500
IRRIGATION SYSTEM
LS 1.000 $20,000.000 $15,000.000 $25,000.000 $25,000.000 $30,000.000 $55,000.000
PLANT MATERIAL (5-GAL)
EA 1,045.000 $25.000 $30.000 $28.000 $30.000 $25.000 $15.000
PLANT MATERIAL (15-GAL)
EA 241.000 $130.000 $150.000 $110.000 $125.000 $130.000 $110.000
PLANT MATERIAL (30-GAL)
EA 11.000 $240.000 $300.000 $225.000 $225.000 $250.000 $190.000
MULCH
SY 1,951.000 $3.500 $4.000 $4.000 $2.000 $5.000 $3.250
PLANT BED PREPARATION
SY 1,951.000 $3.000 $4.000 $2.000 $2.000 $2.000 $1.250
PLANT MAINTENANCE
MO 24.000 $250.000 $1,000.000 $750.000 $1,000.000 $850.000 $900.000
PLANT REPLACEMENT (5-GAL)
EA 100.000 $25.000 $20.000 $0.010 $1.000 $25.000 $5.000
IRRIGATION SYSTEM OPER AND MAINT
MO 24.000 $150.000 $1,000.000 $1,000.000 $500.000 $550.000 $900.000
PLANT REPLACEMENT (15 GAL)
EA 30.000 $130.000 $100.000 $0.010 $1.000 $130.000 $5.000
PLANT REPLACEMENT (30 GAL)
EA 3.000 $240.000 $100.000 $0.010 $1.000 $250.000 $5.000
TRENCH EXCAVATION PROTECTION
LF 50.000 $10.000 $20.000 $0.010 $0.010 $1.000 $0.100
TEMPORARY SPL SHORING
SF 50.000 $10.000 $35.000 $0.010 $0.010 $1.000 $0.100
CL B CONC (MISC)
CY 52.000 $218.000 $200.000 $650.000 $800.000 $325.000 $2,000.000
RETAINING WALL (SPECIAL)
SF 856.000 $50.000 $25.000 $25.000 $40.000 $77.500 $125.000
RIPRAP (CONC)(5 IN)
CY 1.000 $550.000 $1,000.000 $0.010 $1,000.000 $1.000 $2,500.000
MOBILIZATION
LS 1.000 $23,290.050 $20,000.000 $35,000.000 $30,000.000 $25,000.000 $40,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $1,500.000 $1,500.000 $1,750.000 $1,500.000 $1,750.000 $5,000.000
SANDBAGS FOR EROSION CONTROL
EA 50.000 $5.000 $5.000 $10.000 $1.000 $1.000 $0.100
TEMP SEDMT CONT FENCE (INSTALL)
LF 200.000 $2.500 $4.000 $0.010 $1.000 $2.000 $0.100
TEMP SEDMT CONT FENCE (REMOVE)
LF 200.000 $1.000 $1.000 $0.010 $1.000 $0.500 $0.100
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 865.000 $4.000 $6.000 $5.000 $10.000 $2.000 $0.100
BIODEG EROSN CONT LOGS (REMOVE)
LF 865.000 $1.000 $1.000 $1.000 $0.010 $0.500 $0.100
TREE PROTECTION
EA 36.000 $500.000 $300.000 $100.000 $200.000 $75.000 $261.000
TMA (STATIONARY)
DAY 10.000 $175.000 $250.000 $0.010 $0.010 $200.000 $500.000
Totals: $227,301.550 $246,618.000 $251,251.440 $267,889.750 $274,389.100 $448,823.000