TOM GREEN VARIOUS (0907-00-232)
Items: 6
County: TOM GREEN
Length: 0.0000 MILES
Highway: VARIOUS
District: SAN ANGELO
Control Number: 0907-00-232
DBE Goal: 0.0%
Project: C 907-00-232
Guaranty: $7,000.00
Time: 38 WORKING DAYS
Engineer's Estimate: $363,785.00
Date: 06/05/2025 (1 year ago)
Contract Number: 6253229
Type: BRIDGE MAINTENANCE
Project ID: A00196848
Project Description: CLEAN AND SEAL EXISTING BRIDGE JOINTS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
THOMAS GATLIN
NATHANIEL MOORE
TOM GREEN VARIOUS (0907-00-232)
Project Name: N/A
Project: C 907-00-232
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: VARIOUS ROADWAYS IN SJT DISTRICT
Limits To: .
Project Description: CLEAN AND SEAL EXISTING BRIDGE JOINTS
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$363,785.00 | |||
| $274,353.00 |
-24.58%
-$89,432.00
|
|||
| $274,477.00 |
-24.55%
-$89,308.00
|
0.05%
$124.00
|
||
| $364,325.50 |
0.15%
$540.50
|
32.79%
$89,972.50
|
-32.73%
-$89,848.50
|
|
| $372,006.00 |
2.26%
$8,221.00
|
35.59%
$97,653.00
|
-2.11%
-$7,680.50
|
|
| $385,623.00 |
6%
$21,838.00
|
40.56%
$111,270.00
|
-3.66%
-$13,617.00
|
|
| $396,295.00 |
8.94%
$32,510.00
|
44.45%
$121,942.00
|
-2.77%
-$10,672.00
|
E
Engineer's Estimate
$363,785.00
1
Awarded
$274,353.00
Over/Under Est:
-24.58%
-$89,432.00
$274,477.00
Over/Under Est:
-24.55%
-$89,308.00
Amt Left:
0.05%
$124.00
$364,325.50
Over/Under Est:
0.15%
$540.50
Amt Left:
32.79%
$89,972.50
Delta:
-32.73%
-$89,848.50
$372,006.00
Over/Under Est:
2.26%
$8,221.00
Amt Left:
35.59%
$97,653.00
Delta:
-2.11%
-$7,680.50
$385,623.00
Over/Under Est:
6%
$21,838.00
Amt Left:
40.56%
$111,270.00
Delta:
-3.66%
-$13,617.00
$396,295.00
Over/Under Est:
8.94%
$32,510.00
Amt Left:
44.45%
$121,942.00
Delta:
-2.77%
-$10,672.00
Bid Items & Bid Tabulations
6
Total
0 of 6
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $1,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $1,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $3,000.00 |
| Total: | $5,000.00 |